Under DSEAR 2002 Regulation 6 and BS EN 1834-1:2000, diesel engines operating in ATEX Zone 2 explosive atmospheres must incorporate certified flame arrestors (Chalwyn valves), exhaust temperature limitation, and air intake shut-off devices to prevent ignition sources. Energy Institute EI 15 mandates risk assessment, hot-work permits, and continuous monitoring. This RAMS delivers a 5×5 risk-scored methodology reducing residual ignition risk to ≤6 through Pyroban-certified modifications, pre-start DSEAR checks, and permit-to-work isolation, ensuring compliance with the Equipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres Regulations 2016 and HSE guidance HSG103 for safe operation of internal combustion engines in hazardous areas.
| Identified Hazard & Harm | Initial Risk (L×S) | Mandatory Engineering, Isolation & Procedural Controls | Residual Risk |
|---|---|---|---|
| 1. Ignition of explosive atmosphere by hot engine surfaces or exhaust (>450°C) Harm: Major explosion/fire causing multiple fatalities, extensive asset damage, and site evacuation | 4 × 5 = 20 | Install certified Chalwyn air intake shut-off valve (BS EN 1834-1) to starve engine of oxygen on overspeed/runaway. Fit exhaust spark arrestor and temperature limiter maintaining surface temp ≤135°C (T4 rating). Conduct pre-start DSEAR inspection checklist verifying all ATEX modifications intact. Establish 5m exclusion zone during operation. Continuous LEL monitoring with automatic shutdown at 10% LEL. | 2 × 3 = 6 |
| 2. Diesel fuel leak creating flammable vapour cloud in Zone 2 area Harm: Explosion/flash fire causing severe burns, respiratory injury, and structural damage | 4 × 4 = 16 | Use double-skinned fuel lines with leak detection. Install lockable fuel isolation valve with LOTO before maintenance. Conduct daily visual inspection of fuel system integrity. Provide Type B spill kit (50L absorbent capacity) within 5m. Ensure adequate natural/mechanical ventilation (≥10 air changes/hour). Hot-work permit mandatory for any work on fuel system. Bonding and earthing of fuel containers to prevent static accumulation. | 2 × 3 = 6 |
| 3. Engine runaway due to ingestion of external hydrocarbon vapours Harm: Uncontrolled overspeed leading to catastrophic mechanical failure, shrapnel projection, and secondary ignition | 3 × 5 = 15 | Mandatory Chalwyn valve fitted and tested weekly (manual trip test). Position engine air intake upwind and ≥3m from potential hydrocarbon sources. Install overspeed shutdown device (typically 115% rated speed). Operator trained to activate emergency stop and Chalwyn manual trip. Pre-start atmospheric monitoring to confirm <10% LEL. Engine enclosure with flame-proof electrical components to BS EN 60079-0. | 2 × 4 = 8 |
| 4. Electrostatic discharge during refuelling operations Harm: Ignition of diesel vapour causing flash fire and severe burns to operator | 3 × 4 = 12 | Bond fuel container to engine frame using 10mm² copper cable before opening tank. Use conductive fuel hose (resistance <10⁶ Ω). Operator wears anti-static footwear and coveralls (BS EN 1149-5). Refuel in well-ventilated area, engine off and cooled <50°C. No mobile phones or non-IS equipment within 3m. Earthing point tested annually (<10Ω resistance). Refuelling only by trained, authorised personnel. | 2 × 3 = 6 |
| 5. Failure of ATEX-certified safety devices (Pyroban modifications) due to lack of maintenance Harm: Loss of explosion protection leading to ignition event, multiple casualties, and HSE enforcement/prosecution | 4 × 5 = 20 | Implement manufacturer's maintenance schedule (typically 6-monthly inspection of Chalwyn valve, exhaust arrestor, temperature sensors). Maintain ATEX certification records and modification register. Weekly functional test of air intake shut-off (manual trip). Annual recertification by Pyroban-approved engineer. Defect reporting system with immediate withdrawal from service if any ATEX device fails. Competent person (DSEAR Regulation 7) conducts quarterly audit. Maintain spares inventory for critical safety components. | 2 × 4 = 8 |
Obtain Hot Work Permit and DSEAR Task-Specific Permit from Site Controller. Verify ATEX Zone 2 classification current (review area classification drawing to EI 15). Inspect Pyroban certification plate and modification date (<12 months). Check Chalwyn valve manual trip operation (pull cable, valve closes, reset). Verify exhaust temperature limiter and spark arrestor intact. Confirm all electrical components flame-proof (BS EN 60079-0). Conduct LEL monitoring at engine location and 5m radius – proceed only if <10% LEL. Check fuel system for leaks, ensure isolation valve accessible. Verify spill kit and fire extinguisher (9kg dry powder, 34A 233B C rating) within 5m.
If maintenance required, shut fuel isolation valve and apply LOTO (personal padlock and danger tag to BS 5378). Verify engine cooled to <50°C using IR thermometer. Establish 5m exclusion zone with barrier tape and signage ('ATEX Zone 2 – No Smoking, No Naked Flames, No Mobile Phones'). Test earthing point continuity (<10Ω to main earth). Bond any fuel containers to engine frame using 10mm² copper cable and clamps. Don full PPE: anti-static coveralls (BS EN 1149-5), S3 FO A boots, nitrile gloves (BS EN 374), safety spectacles (BS EN 166). Position spill kit and ensure fire extinguisher charged (pressure gauge in green).
Remove LOTO (if applied) and open fuel isolation valve. Position intrinsically safe (IS) multi-gas detector (BS EN 60079-11) within 2m of engine, set alarm at 10% LEL. Ensure Chalwyn valve reset (cable extended, valve open). Check cooling system level and oil pressure gauge functional. Operator stands upwind, clear of exhaust. Turn key to start – monitor for abnormal smoke, noise, or vibration. Allow 2-minute warm-up at idle, observe exhaust temperature gauge (<135°C). Check for fuel leaks at connections. Confirm overspeed shutdown device armed (test light illuminated). Monitor LEL continuously – if >10%, activate emergency stop and Chalwyn manual trip immediately.
Maintain continuous LEL monitoring with audible alarm. Inspect engine every 30 minutes: exhaust temperature <135°C, no fuel leaks, no abnormal vibration. Check Chalwyn valve cable free and accessible. Ensure exclusion zone maintained – challenge any unauthorised entry. Monitor weather conditions – if wind drops or vapour sources identified upwind, increase monitoring frequency to 15-minute intervals. Log readings on DSEAR operational checklist (exhaust temp, LEL %, oil pressure, coolant temp). Operator remains within 10m and maintains line of sight to emergency stop. No refuelling during operation. If LEL reaches 10%, initiate controlled shutdown (Step 5).
Reduce load gradually over 2 minutes to prevent thermal shock. Allow 3-minute cool-down at idle. Turn key to off position. Close fuel isolation valve. Conduct post-operation inspection: check for new fuel leaks, inspect exhaust system for damage, verify Chalwyn valve returned to open position. Record final exhaust temperature and LEL reading. Allow engine to cool to <50°C before any maintenance. If refuelling required, proceed to Step 6. Otherwise, complete permit closure section, return to Site Controller. Store IS gas detector on charge. Report any defects or near-misses on permit reverse.
Confirm engine off and cooled <50°C. Verify LEL <5% at tank location. Remove all ignition sources from 5m radius (mobile phones, lighters, vehicles). Connect 10mm² bonding cable from fuel container to engine frame before opening either cap. Use conductive fuel hose (test resistance <10⁶ Ω annually). Insert nozzle fully into tank before dispensing to prevent splash-back. Fill slowly (max 20 L/min) to avoid static generation. Do not overfill – leave 10% ullage for expansion. Remove nozzle, then disconnect bonding cable. Replace caps tightly. Wipe any spillage immediately with absorbent pads (dispose in sealed metal bin). Conduct LEL check post-refuelling – must remain <10% before restart. Record fuel quantity and date on engine log.
**EMERGENCY CONTACTS:** Site Emergency: [INSERT], Fire Brigade: 999, HSE Incident Contact Centre: 0345 300 9923. **ENGINE RUNAWAY:** Pull Chalwyn manual trip cable immediately, press emergency stop, evacuate 25m, call Fire Brigade. **FIRE:** Activate nearest call point, evacuate, use 9kg dry powder extinguisher only if safe (do not use water or foam on diesel fire). **FUEL SPILL:** Stop source, activate spill kit, contain with absorbent booms, ventilate area, monitor LEL continuously, report to Environment Agency if >10L enters drain (0800 807060). **EXPLOSION/FLASH FIRE:** Evacuate site, account for all personnel at muster point, call 999, do not re-enter until Fire Service declares safe. **FIRST AID – Burns:** Cool with running water 20 minutes, cover with sterile non-adhesive dressing, seek immediate medical attention for burns >5cm² or full-thickness. **Diesel Fuel Ingestion:** Do NOT induce vomiting (aspiration risk), rinse mouth, give water to drink, seek urgent medical attention – risk of chemical pneumonitis. **Inhalation of Diesel Vapour:** Move to fresh air, monitor for respiratory distress, administer oxygen if trained, seek medical attention if symptoms persist (headache, dizziness, nausea). **Eye Contact:** Irrigate with eyewash for 15 minutes, remove contact lenses, seek medical attention. All incidents reportable under RIDDOR if result in >7 day absence, specified injury, or dangerous occurrence (engine runaway/explosion).
Yes. DSEAR 2002 Regulation 6 and BS EN 1834-1:2000 require diesel engines in Zone 2 to be modified to prevent them becoming an ignition source. A Chalwyn valve (air intake shut-off device) is mandatory to prevent engine runaway if it ingests external flammable vapours. You also need exhaust spark arrestors, temperature limiters (max 135°C surface temp for T4 rating), and flame-proof electrical components. The engine must hold valid ATEX Category 2G certification (Equipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres Regulations 2016). Pyroban is the leading UK provider of such conversions, and certification must be maintained with 6-monthly inspections and annual recertification by a competent engineer. Operating an uncertified engine in Zone 2 is a breach of DSEAR and can result in HSE prohibition notices and prosecution.
Initial (inherent) risk for ignition of explosive atmosphere by hot engine surfaces is typically Likelihood 4 × Severity 5 = 20 (unacceptable). To reduce to ≤8 (typically required for PQQ/tender acceptance), you must implement: (1) Chalwyn air intake shut-off valve with weekly trip testing, (2) exhaust temperature limiter maintaining ≤135°C (T4), (3) continuous LEL monitoring with 10% alarm and auto-shutdown, (4) pre-start DSEAR inspection checklist, (5) 5m exclusion zone, (6) hot-work permit system, and (7) 6-monthly maintenance of all ATEX devices by competent person. With these controls, residual risk reduces to Likelihood 2 × Severity 4 = 8 (tolerable with monitoring). Document all controls in your RAMS with reference to BS EN 1834-1 and maintain audit trail of Chalwyn valve tests, ATEX certification, and LEL monitoring logs. Most UK principal contractors (Network Rail, National Grid, Tier 1 civils) mandate residual score ≤8 for DSEAR activities.
Mandatory PPE under DSEAR 2002 and ATEX Zone 2: (1) Anti-static flame-retardant coveralls to BS EN 1149-5:2018 (electrostatic dissipation) and BS EN ISO 11612:2015 (limited flame protection) – prevents static discharge ignition and provides burn protection; (2) Safety boots to BS EN ISO 20345:2011 S3 FO A with anti-static properties and fuel-resistant soles – dissipates static and resists diesel penetration; (3) Chemical-resistant gloves to BS EN 374-1:2016 Type B (KPT rating for diesel fuel) in nitrile or neoprene – protects against dermal exposure to GHS Category 3 flammable liquid; (4) Safety spectacles to BS EN 166:2001 Class 1 Optical F with side shields – protects from diesel spray under pressure. All PPE must be inspected pre-use for damage that could compromise anti-static properties. Non-compliant PPE (e.g. standard cotton coveralls, non-ESD footwear) can generate static discharge sufficient to ignite Zone 2 atmosphere. PPE records and training certificates must be available for HSE/client audit and are standard PQQ requirements for DSEAR work.
| Operative / Supervisor Name | Trade / Role & CSCS No. | Signature | Date & Time |
|---|---|---|---|
| 1. (Site Supervisor): | |||
| 2. | |||
| 3. | |||
| 4. |