Under PUWER 1998 Regulation 19, air handling unit (AHU) filter replacement requires documented isolation (LOTO) to prevent inadvertent start-up. COSHH 2002 mandates FFP3 respiratory protection against bioaerosols and particulate contamination. Work at Height Regulations 2005 and TR19 (Safe Management of Ventilation Systems) require risk-assessed access, edge protection, and competent person supervision to reduce residual risk to ≤8 (Tolerable). This RAMS provides a structured 5x5 matrix methodology, BS EN-compliant PPE specifications, and step-by-step safe system of work for facilities maintenance contractors, M&E engineers, and duty holders managing AHU filter change-outs in commercial, healthcare, and industrial environments across the UK.
| Identified Hazard & Harm | Initial Risk (L×S) | Mandatory Engineering, Isolation & Procedural Controls | Residual Risk |
|---|---|---|---|
| 1. Inadvertent AHU start-up during filter replacement (rotating fan, damper movement) Harm: Amputation, crush injury, entanglement, or fatality from contact with live fan blades or motorised dampers | 4 × 5 = 20 | PUWER 1998 Reg 19 LOTO: Isolate electrical supply at local isolator and main distribution board. Apply multi-point lockout hasp, individual padlocks (one per operative), and 'Danger – Men Working' tags. Verify dead using calibrated voltage tester and proving unit. Mechanical isolation of dampers using locking pins. Permit-to-work issued by Authorised Person (Electrical). Test fan rotation by hand before re-energisation. | 2 × 5 = 10 |
| 2. Inhalation of bioaerosols, fungal spores, bacteria, and accumulated dust during filter removal Harm: Occupational asthma, hypersensitivity pneumonitis, Legionnaires' disease, allergic rhinitis, or chronic respiratory disease | 5 × 3 = 15 | COSHH 2002 assessment completed. Mandatory FFP3 respirator (BS EN 149) fit-tested annually. Pre-dampen filters with fine water mist to suppress dust. Use HEPA-filtered vacuum (H13) to clean AHU chamber before and after filter change. Seal removed filters in double-layer polythene bags immediately. Limit personnel in AHU room to essential operatives only. Provide welfare facilities for decontamination and hand hygiene. | 2 × 3 = 6 |
| 3. Work at height: access to AHU plant room, rooftop units, or elevated filter banks (>2 m) Harm: Fall from height resulting in major injury (fractures, spinal injury) or fatality | 3 × 5 = 15 | Work at Height Regulations 2005: Avoid work at height where practicable. Use mobile scaffold tower (Class 3, inspected every 7 days, tagged) with guardrails, toe boards, and safe access ladder. Podium steps for <2.5 m access. Roof edge protection (guardrails or barriers) installed before access. Competent person supervises erection/dismantling. Harness and lanyard (BS EN 361/BS EN 355) only as last resort with anchor point load-tested to 15 kN. Weather restrictions: no work in wind >20 mph or wet/icy conditions. | 1 × 5 = 5 |
| 4. Manual handling of heavy, awkward filters (5–15 kg each, bulky dimensions up to 600×600×300 mm) Harm: Musculoskeletal disorders (MSD): back strain, shoulder injury, herniated disc, or repetitive strain injury | 5 × 2 = 10 | Manual Handling Operations Regulations 1992: Two-person lift for filters >10 kg or awkward dimensions. Use mechanical aids (filter trolley, sack truck) where access permits. Maintain neutral spine posture, bend knees, keep load close to body. Pre-task briefing on correct lifting technique. Rotate operatives every 30 minutes to reduce fatigue. Clear access routes and staging area. Filters stored at waist height (750–1050 mm) to minimise bending. | 2 × 2 = 4 |
| 5. Electrical shock from live AHU control panels, motor terminals, or auxiliary equipment (230/400 V AC) Harm: Electrocution, cardiac arrest, severe burns, or secondary fall from height due to electric shock | 2 × 5 = 10 | Electricity at Work Regulations 1989: Only competent, authorised electricians open control panels. LOTO isolation at main isolator and local starter. Voltage testing (proving unit + test + proving unit sequence) confirms dead. Barriers and warning signs around open panels. Insulated tools (BS EN 60900) used. Residual current device (RCD) protection on temporary supplies. Permit-to-work system for re-energisation. Minimum approach distance 0.5 m from live parts if isolation not possible (emergency fault-finding only). | 1 × 5 = 5 |
Conduct site-specific risk assessment and toolbox talk. Issue Permit-to-Work (Authorised Person). Notify building occupants of AHU shutdown and expected duration. Isolate electrical supply at main distribution board and local AHU isolator. Apply multi-point lockout hasp with individual padlocks (one per operative). Affix 'Danger – Men Working' tags. Verify dead using calibrated voltage tester (prove-test-prove sequence). Mechanically lock dampers in closed position. Erect barriers and signage around work area.
If AHU filter bank is >2 m above floor level, erect mobile scaffold tower (Class 3, 150 kg SWL) in accordance with manufacturer's instructions. Ensure all guardrails, toe boards, and outriggers are in place. Inspect tower and complete pre-use checklist (tag with inspection date and competent person signature). Secure tower to prevent movement. Alternatively, use podium steps for access <2.5 m. Ensure adequate lighting (minimum 200 lux) in AHU plant room.
Don full PPE: FFP3 respirator (fit-tested), nitrile gloves, safety spectacles, and coveralls. Pre-dampen filter faces with fine water mist to suppress dust release. Carefully release filter clamps or retaining clips. Support filter weight during removal to prevent dropping. Slide filter out horizontally, maintaining control. Immediately place removed filter into sealed polythene bag (double-bagged). Label bag 'Contaminated – Bioaerosol Hazard'. Transfer to rigid waste container. Use HEPA vacuum to clean filter housing and surrounding surfaces.
With filters removed, visually inspect AHU chamber for: corrosion, water ingress, blocked condensate drains, damaged coils, or biological growth (mould, algae). Photograph any defects and report to client/duty holder. Clean AHU chamber using HEPA-filtered vacuum and damp cloth (do not dry-sweep). Check filter seals and gaskets for damage or compression set. Verify filter frame dimensions match replacement filters. Clear condensate drain using hand pump or compressed air (wear face shield).
Verify new filters match specification (efficiency grade, dimensions, pressure drop rating). Check airflow direction arrow on filter frame. Slide new filter into housing, ensuring gasket or seal makes full contact around perimeter (no bypass gaps). Secure filter clamps or retaining clips. Repeat for all filter positions. Conduct visual inspection for gaps or misalignment. Record filter type, efficiency grade (e.g., F7, F9, H13), and installation date on AHU logbook or BMS.
Remove all tools, equipment, and personnel from AHU chamber. Close and secure access doors. Remove LOTO padlocks and tags (each operative removes own lock). Authorised Person re-energises electrical supply at isolator. Start AHU in manual mode and observe for abnormal noise, vibration, or airflow issues. Check differential pressure across new filters using manometer (record baseline reading). Verify damper operation and control system response. Hand over Permit-to-Work and update AHU maintenance log. Dispose of waste filters via licensed contractor (clinical waste route if healthcare setting).
**Emergency Contacts:** - Emergency Services: **999** (ambulance, fire, police) - Site First Aider: [Insert name and mobile] - Duty Holder / Responsible Person: [Insert name and mobile] - Electrical Authorised Person: [Insert name and mobile] - Out-of-hours facilities management: [Insert contact] **Emergency Procedures:** 1. **Electrical Shock / Electrocution:** - Do NOT touch the casualty if still in contact with live electrical source. - Isolate power immediately at main isolator or call emergency electrical contact. - Once safe, check responsiveness and breathing. Commence CPR if required (30 compressions : 2 breaths). - Call 999 and request ambulance. Use on-site AED (Automated External Defibrillator) if available. - Treat electrical burns with sterile dressing; do not apply creams or ointments. 2. **Fall from Height:** - Do not move casualty unless in immediate danger (fire, structural collapse). - Call 999 immediately. Assume spinal injury until proven otherwise. - Keep casualty warm and still. Monitor breathing and consciousness. - Provide reassurance. Site First Aider to attend and maintain airway if unconscious. 3. **Respiratory Distress / Bioaerosol Exposure:** - Move casualty to fresh air immediately. Remove contaminated PPE carefully. - Sit casualty upright to ease breathing. Loosen tight clothing. - If breathing is difficult, call 999. Administer oxygen if trained and equipment available. - If casualty has known asthma, assist with inhaler (salbutamol). - Monitor for signs of anaphylaxis (swelling, rash, difficulty breathing) and use EpiPen if prescribed. 4. **Crush Injury / Amputation:** - Call 999 immediately. Apply direct pressure to control severe bleeding using sterile dressing or clean cloth. - If amputation has occurred, wrap severed part in clean, damp cloth, place in sealed plastic bag, and keep cool (do not place directly on ice). - Treat for shock: lay casualty down, elevate legs (if no spinal injury suspected), keep warm. - Do not give food or drink. Monitor vital signs until ambulance arrives. 5. **Fire / Smoke in AHU Plant Room:** - Activate nearest fire alarm call point. - Evacuate area immediately via nearest safe exit. Close doors behind you. - Do NOT re-enter to retrieve tools or equipment. - Muster at designated assembly point and report to Fire Marshal. - Fire Service will isolate AHU and ventilation systems. **First Aid Facilities:** Ensure site has HSE-compliant first aid kit (BS 8599-1:2019) and accessible eyewash station. All operatives must know location of nearest first aid kit and first aider. Record all injuries, near-misses, and emergency incidents in site accident book and report under RIDDOR 2013 if: - Fatality or major injury (fracture, amputation, loss of consciousness) - Over-7-day injury (unable to perform normal work) - Occupational disease (e.g., occupational asthma from bioaerosol exposure) - Dangerous occurrence (e.g., failure of scaffold, electrical flashover) Report to HSE via online portal within 10 days (over-7-day injuries) or immediately (fatalities and major injuries).
Yes. PUWER 1998 Regulation 19 requires a formal Permit-to-Work system for maintenance on AHU systems to prevent inadvertent start-up. Electrical isolation must be applied at both the local AHU isolator and the main distribution board, with Lockout/Tagout (LOTO) devices (multi-point hasp, individual padlocks, and 'Danger – Men Working' tags). An Authorised Person (Electrical) must verify the system is dead using a calibrated voltage tester (prove-test-prove sequence) before work commences. Mechanical isolation of motorised dampers using locking pins is also required. The permit must detail the scope of work, isolation points, and authorised personnel, and must be closed out and signed off before re-energisation.
COSHH 2002 mandates a suitable and sufficient risk assessment for biological agents (bioaerosols, bacteria, fungi, dust mites) present in AHU filters. Based on typical exposure levels, FFP3 disposable respirators (BS EN 149:2001+A1:2009) with an Assigned Protection Factor (APF) of 20 are the minimum legal requirement. Operatives must be face-fit tested annually (HSE INDG479) and trained in correct donning, doffing, and seal checks. Reusable half-mask respirators with P3 filters (BS EN 140 + BS EN 143) are an acceptable alternative if maintained and fit-tested. FFP2 masks do not provide adequate protection for high bioaerosol environments such as healthcare or industrial AHUs. Employers must provide RPE free of charge and ensure operatives are clean-shaven in the seal area.
Work at Height Regulations 2005 require a hierarchy of control: (1) Avoid work at height where possible (e.g., design filters for ground-level access); (2) Use collective fall prevention (guardrails, edge protection, mobile scaffold towers with guardrails and toe boards); (3) Minimise fall distance and consequences (safety nets, airbags); (4) Personal fall arrest (harness and lanyard) only as last resort. For rooftop AHU access, install permanent edge protection (guardrails to BS EN 13374 Class A minimum) or erect temporary barriers before personnel access the roof. Mobile scaffold towers must be Class 3 (150 kg SWL), inspected every 7 days, and tagged by a competent person. Ladders are not acceptable as a working platform for filter replacement. Weather restrictions apply: no work in wind speeds >20 mph, rain, ice, or snow. A rescue plan must be in place if harnesses are used, as suspension trauma can be fatal within 20 minutes.
| Operative / Supervisor Name | Trade / Role & CSCS No. | Signature | Date & Time |
|---|---|---|---|
| 1. (Site Supervisor): | |||
| 2. | |||
| 3. | |||
| 4. |
Need site-specific compliance documentation instead of a static template? Explore the core SafeSequence® UK software modules hosted in AWS London (eu-west-2):