SafeSequence › UK Safety Template Library › High-Volume UK RAMS › Birmingham Falsework & Temporary Works Erection 5x5 RAMS (BS 5975 TWC Checklist)
Reference UK RAMS Example • High-Volume UK RAMS

Birmingham Falsework & Temporary Works Erection 5x5 RAMS (BS 5975 TWC Checklist)

Under BS 5975:2019 (Code of Practice for Temporary Works Procedures and the Permissible Stress Design of Falsework), CDM 2015 Regulation 19 (stability of structures), and Work at Height Regulations 2005, all falsework and temporary works erection in Birmingham must be designed, checked, and supervised by competent Temporary Works Coordinators (TWC), with formal TWC permits, load calculations, and inspection regimes to prevent structural collapse. This RAMS mandates 5x5 risk assessment, BS EN-certified PPE, sequential erection protocols, and hold-points to reduce catastrophic failure risk from initial 5×5=25 (Very High) to residual 2×3=6 (Low). Suitable for Birmingham infrastructure, bridge, and high-rise projects requiring audit-grade CDM and BS 5975 compliance for Principal Contractors, Temporary Works Supervisors, and scaffolding/formwork subcontractors.

Statutory FrameworkBS 5975:2019 (Code of Practice for Temporary Works & Falsework), CDM 2015 Reg 19, Work at Height Regs 2005
ClassificationNot applicable. This RAMS governs structural falsework and temporary works erection under BS 5975:2019, CDM 2015, and Work at Height Regulations 2005. No hazardous substances are in scope; however, hydraulic oils in props and release agents on formwork panels must comply with COSHH 2002 and have site-specific COSHH assessments. All structural steel and aluminium components must bear CE/UKCA marking and manufacturer's load certificates.
Required Plant / KitProprietary falsework system (e.g. RMD, PERI, MEVA) with valid design calculations and TWC permit • Hydraulic adjustable props and load-bearing beams (with current test certificates and SWL markings) • Spirit levels, laser levels, and surveying equipment for verticality and alignment checks • Torque wrenches (calibrated to manufacturer's specification) for bolted connections • Mobile Elevated Work Platforms (MEWPs) or tower scaffolds (LOLER-inspected) for safe access during erection
Site Sign-Off StatusRequires Competent Person Verification
Bid-Winning PCI Tender Studio or Instant Voice Customization

Bidding a Contract or Need This RAMS Customized for Your Site?

Drop your client's Pre-Construction Information (PCI) PDF into our Tender Studio to generate a page-cited 5×5 RAMS & PQQ pack—or download our free blank Word (.doc) shell below.

Auto-Fill via 45s Voice / CLP

1. Mandatory Personal Protective Equipment (BS EN Standards)

BS EN 397:2012+A1:2012
Safety helmet with chin strap (white for supervisors, yellow for operatives)
Mandatory head protection against falling objects, overhead loads, and struck-by hazards during falsework erection and lifting operations.
BS EN ISO 20471:2013
High-visibility Class 3 vest or jacket (orange for falsework gangs)
Essential for visibility to crane operators, plant drivers, and site traffic in congested Birmingham construction zones.
BS EN ISO 20345:2011 S3
Safety boots with steel toe-cap, midsole protection, and slip-resistant sole
Protection against crush injuries from heavy falsework components, penetration from protruding reinforcement, and slips on wet concrete.
BS EN 388:2016
Work gloves with cut and abrasion resistance (Level C/Level 3 minimum)
Hand protection during manual handling of steel beams, props, and formwork panels with sharp edges and splinters.

2. 5×5 Hazard Risk Assessment Matrix (HASAWA 1974 / CDM 2015)

Identified Hazard & HarmInitial Risk (L×S)Mandatory Engineering, Isolation & Procedural ControlsResidual Risk
1. Structural collapse of falsework during erection due to inadequate design, overloading, or premature striking
Harm: Multiple fatalities, catastrophic structural failure, major injuries to operatives and public, HSE prosecution under CDM 2015 Reg 19
5 × 5 = 25Appoint competent Temporary Works Coordinator (TWC) and Temporary Works Supervisor (TWS) per BS 5975:2019 Clause 7. Issue formal TWC Design Brief and obtain signed TWC Permit before erection. Verify all falsework components against design drawings and load schedules. Install load monitoring devices and settlement markers. Prohibit any loading until TWC issues Permit to Load. Conduct daily pre-shift inspections and after adverse weather. Implement exclusion zones and barriers beneath falsework.2 × 3 = 6
2. Falls from height during falsework assembly, adjustment, and striking operations
Harm: Fatal or life-changing injuries from falls >2m, fractures, head trauma, spinal injuries
5 × 4 = 20Erect edge protection (guardrails, mid-rails, toe-boards to BS EN 13374 Class A) on all working platforms before operatives access. Use LOLER-inspected MEWPs or tower scaffolds for access; prohibit ladders for work activities. Provide full-body harnesses (BS EN 361:2002) with twin-lanyard fall-arrest systems and anchor points rated ≥15kN where edge protection cannot be installed. Conduct pre-use MEWP checks and operator competence verification (IPAF/PASMA). Implement rescue plan for suspended casualties.2 × 4 = 8
3. Struck-by or crushed-by falling falsework components, props, or beams during lifting and positioning
Harm: Crush injuries, amputations, multiple fractures, fatalities from uncontrolled loads
4 × 5 = 20Appoint Appointed Person (Lifting Operations) per BS 7121 and LOLER 1998. Prepare lift plans for all components >500kg. Use certified lifting equipment (chains, slings, shackles) with current thorough examination certificates. Establish 5m exclusion zones around crane operations; use banksmen with two-way radios. Secure all components immediately upon landing; prohibit working beneath suspended loads. Conduct pre-lift toolbox talks and emergency stop drills.2 × 4 = 8
4. Manual handling injuries during movement of heavy props, beams, and formwork panels
Harm: Musculoskeletal disorders, back injuries, hernias, trapped fingers, crush injuries to hands and feet
5 × 3 = 15Eliminate manual handling where possible using mechanical aids (telehandlers, pallet trucks, trolleys). Limit manual lifts to two-person teams for loads >25kg per operative. Provide Manual Handling training per HSE guidance (HSG60). Use lifting aids (beam clamps, prop handlers) to reduce grip force. Ensure clear, level haul routes free from trip hazards. Rotate operatives to reduce repetitive strain. Conduct dynamic risk assessments before each lift.3 × 2 = 6
5. Ground instability, settlement, or bearing capacity failure beneath falsework base plates
Harm: Progressive collapse of falsework, multiple fatalities, structural damage to permanent works
4 × 5 = 20Commission geotechnical survey and ground bearing capacity assessment by Chartered Civil Engineer. Install concrete foundation pads or timber sole plates sized per BS 5975 Clause 10.3 to distribute loads. Verify ground conditions match design assumptions before erection. Install settlement monitoring pegs and daily levelling regime. Prohibit excavation or services installation within 5m of falsework without TWC approval. Implement drainage to prevent water accumulation and ground softening. Establish trigger levels for settlement (typically 5mm) requiring immediate work stoppage.2 × 4 = 8

3. Step-by-Step Safe Sequence of Operations & Hold-Points

1

Obtain TWC Design Brief, Permit, and Conduct Site Readiness Inspection

Pre-Erection Planning & TWC Approval

Temporary Works Coordinator (TWC) issues Design Brief specifying loads, dimensions, and performance criteria. Designer (Chartered Engineer or competent falsework designer) prepares calculations and erection drawings. TWC checks and approves design, then issues TWC Permit to Erect. Temporary Works Supervisor (TWS) conducts site inspection to verify ground conditions, access routes, overhead hazards (power lines, structures), and availability of all specified components. Confirm all operatives hold CISRS/CITB Falsework Awareness or equivalent. Hold pre-start briefing covering sequence, hazards, and emergency procedures.

Critical Hold-Point: HOLD POINT: Do NOT commence erection until TWC Permit to Erect is signed and displayed on site. Verify all falsework components match design schedule and bear manufacturer's identification and load ratings. Confirm exclusion zones and barriers are in place.
2

Install Base Plates, Sole Plates, and Settlement Monitoring

Foundation & Base Preparation

Excavate and compact ground to design level; install concrete foundation pads or timber sole plates as specified. Position adjustable base plates ensuring full contact with sole plates and correct spacing per drawings. Install settlement monitoring pegs adjacent to each base plate. Use laser level or theodolite to establish datum levels and record baseline readings. Verify ground is free from water, debris, and services. Mark out falsework footprint with spray paint and barrier tape.

Critical Hold-Point: HOLD POINT: TWS must verify and sign off foundation preparation before any vertical components are erected. Check ground bearing capacity matches design assumptions. Photograph all base conditions for record.
3

Erect Standards, Props, and Primary Beams in Sequence

Vertical & Horizontal Member Erection

Erect vertical standards or adjustable props in sequence from one end, maintaining temporary bracing at all times. Use spirit levels to verify verticality (tolerance ±1:200). Install primary beams and ledgers, securing all connections with pins, clips, or bolts torqued to manufacturer's specification. Install diagonal bracing in both directions to provide lateral stability. Work from MEWPs or edge-protected platforms; never climb falsework during erection. Lift heavy beams using crane with certified lifting gear and exclusion zones. Check alignment and levels continuously against design drawings.

Critical Hold-Point: HOLD POINT: Do NOT proceed to next lift/level until current level is fully braced, connected, and checked by TWS. Ensure all operatives remain within edge-protected zones or use fall-arrest harnesses.
4

Install Formwork Panels, Decking, and Edge Protection

Formwork & Decking Installation

Position formwork panels (plywood, steel, or proprietary) onto primary beams, ensuring full bearing and correct laps per design. Secure panels with clamps or fixings to prevent displacement. Install working decks (scaffold boards or proprietary platforms) for access, ensuring no gaps >25mm. Erect edge protection (guardrails, mid-rails, toe-boards) to BS EN 13374 Class A on all open edges. Install access ladders or stair towers at designated locations. Verify all walking surfaces are level, clean, and free from trip hazards.

Critical Hold-Point: HOLD POINT: TWS must inspect and approve all edge protection and working platforms before operatives access upper levels. Confirm formwork alignment and levels match design tolerances (typically ±5mm).
5

Conduct Joint Inspection and Obtain Permit to Load

Final Inspection & TWC Permit to Load

TWS conducts detailed inspection of entire falsework system, checking all connections, bracing, verticality, and alignment against design drawings. Complete BS 5975 Falsework Inspection Checklist (Appendix C). TWC and Designer (if required) conduct joint inspection and witness load test if specified. TWC issues Permit to Load specifying maximum loads, loading sequence, and any restrictions. Display Permit to Load at site access point. Brief all trades (concretors, steel fixers) on loading restrictions and sequence. Install load monitoring devices (strain gauges, settlement markers) if specified.

Critical Hold-Point: HOLD POINT: Absolutely NO loading (concrete, materials, plant, operatives) permitted until TWC Permit to Load is issued and displayed. Any defects or non-conformances must be rectified and re-inspected before loading.
6

Daily Inspections, Load Monitoring, and Controlled Striking Sequence

In-Service Monitoring & Striking

Conduct daily pre-shift inspections by TWS, recording settlement readings, checking for damage, distortion, or movement. Inspect after adverse weather (high winds, heavy rain, frost). Monitor concrete curing and strength gain; do not strike until concrete achieves specified strength (typically 75% design strength, confirmed by cube tests). TWC issues Permit to Strike specifying sequence and any props to remain. Strike falsework in reverse sequence to erection, maintaining stability at all times. Lower components using mechanical aids; never drop or throw. Remove to designated storage area and inspect for damage before re-use.

Critical Hold-Point: HOLD POINT: Do NOT commence striking until TWC Permit to Strike is issued and concrete strength is confirmed by test certificates. Any settlement >5mm or visible distortion requires immediate work stoppage and TWC notification.

Emergency Rescue, First Aid & Spill Protocol

In the event of structural collapse, partial failure, or excessive settlement: EVACUATE all personnel from falsework and surrounding area immediately. Activate site emergency alarm and muster at assembly point. Site Manager to call 999 (Fire & Rescue for persons trapped, Ambulance for casualties). Do NOT re-enter collapse zone. Appoint competent person to control site access and preserve evidence. Notify TWC, Principal Contractor, and HSE (RIDDOR report required for structural failure or serious injury). For falls from height: Do NOT move casualty unless in immediate danger. Administer first aid by trained First Aider; treat for spinal injury. For suspended casualties in fall-arrest harnesses: Initiate rescue within 15 minutes to prevent suspension trauma; use MEWP or rescue kit. First Aid: Minimum two First Aiders on site during falsework operations; first aid room or vehicle within 200m. Nearest A&E: Queen Elizabeth Hospital Birmingham, Mindelsohn Way, B15 2TH (3.2 miles, 12 min). Site to hold emergency contact list including TWC, Designer, Principal Contractor, and HSE (0345 300 9923).

4. UK HSE & PQQ Compliance FAQs: Birmingham Falsework & Temporary Works Erection 5x5 RAMS (BS 5975 TWC Checklist)

Do I need a Temporary Works Coordinator for falsework on a Birmingham construction project under CDM 2015?

Yes, absolutely. BS 5975:2019 Clause 7 and CDM 2015 Regulation 19 require a competent Temporary Works Coordinator (TWC) for all falsework and temporary works that support permanent structures or present significant risk. The TWC must be appointed in writing, hold appropriate qualifications (e.g., IStructE TWC Certificate, CITB Temporary Works Supervisor), and issue formal Design Briefs, check designs, and issue Permits to Erect and Permits to Load. In Birmingham, Principal Contractors and Local Authority Building Control expect full BS 5975 compliance with documented TWC procedures for all bridge, slab, and high-rise falsework. Failure to appoint a TWC is a breach of CDM 2015 and can result in HSE enforcement, prohibition notices, and prosecution following collapse or near-miss incidents.

What is the difference between a 3x3 and 5x5 risk matrix for falsework RAMS and which does HSE prefer?

A 5x5 risk matrix (likelihood 1-5, severity 1-5, scores 1-25) provides finer granularity and is strongly preferred by UK HSE, Principal Contractors, and CDM auditors for high-risk activities like falsework erection. The 5x5 matrix better differentiates between 'High' and 'Very High' risks, allowing more precise control selection and residual risk evaluation. BS 5975:2019 and CDM 2015 do not mandate a specific matrix, but HSE guidance (e.g., HSG65) and industry best practice (CITB, Build UK) recommend 5x5 for construction activities with potential for multiple fatalities. Birmingham City Council and major infrastructure clients (HS2, National Highways) typically require 5x5 matrices in tender submissions and RAMS. A 3x3 matrix is considered insufficiently detailed for falsework and may be rejected during PQQ or pre-construction audits.

Can I use second-hand or hired falsework without new design calculations for a Birmingham site?

No, not without verification. BS 5975:2019 Clause 9 requires that all falsework, whether new, hired, or second-hand, must be designed for the specific application, loads, and site conditions. Even proprietary systems (RMD, PERI, MEVA) require a competent designer to produce project-specific calculations, erection drawings, and loading schedules. Hired falsework must be accompanied by manufacturer's load tables, test certificates, and inspection records; the TWC must verify suitability and issue a Design Brief. Second-hand components must be inspected for damage, corrosion, and distortion before re-use; any bent, cracked, or corroded items must be scrapped. In Birmingham, HSE inspectors and Principal Contractor audits will request TWC Permits, design calculations, and component inspection records; absence of these is a CDM 2015 breach and grounds for immediate prohibition notice.

5. Operative Toolbox Talk & Competent Person Sign-Off Register

Operative / Supervisor Name Trade / Role & CSCS No. Signature Date & Time
1. (Site Supervisor):     
2.     
3.     
4.     

Automate UK Safety Documentation with SafeSequence®

Need site-specific compliance documentation instead of a static template? Explore the core SafeSequence® UK software modules hosted in AWS London (eu-west-2):

45s Voice RAMS & COSHH Dictate site tasks or select CLP diamonds to generate UK 5×5 RAMS & Reg 6 COSHH PDFs. PCI Tender-to-RAMS Studio Upload 300-page Principal Contractor PCI PDFs for [Page X] cited RAMS & PAS 91 answers. Enterprise Visual SOPs Turn shop-floor POV walkthrough video into GDPR-redacted Visual SOPs, 6S OPLs & CAPAs. HSE Consultant Vaults Multi-client white-label RAMS, Visual SOP & COSHH software for CMIOSH consultants.

Related UK Safety & Tender Templates