UK HVAC, air conditioning, and Air Handling Unit (AHU) maintenance quotations must comply with F-Gas Regulations 2015 (refrigerant handling & leak checks), BESA SFG20 planned maintenance schedules, TR19 internal cleanliness standards, PUWER 1998 Lock-Off/Tag-Out (LOTO) isolation for rotating machinery, and CIS Domestic Reverse Charge VAT (VATA 1994 s.55A) for building services. This audit-grade template integrates a priced Bill of Quantities (BoQ) with 2026 UK trade rates (Materials, Plant, Labour in £ GBP), a pre-staged 5×5 Risk Assessment & Method Statement (RAMS) covering refrigerant exposure, electrical isolation, working at height (AHU access), Legionella control, and rotating machinery entanglement, and BS EN-coded PPE schedules. By locking a Client Purchase Order against this quotation, contractors automatically unlock the embedded RAMS, ensuring F-Gas-certified engineers execute LOTO isolation, TR19 hygiene swabs, and SFG20 task frequencies while maintaining full CIS VAT compliance. The 5×5 matrix demonstrates risk reduction from initial scores (e.g. 4×4=16 High) to residual (2×2=4 Low) through engineering controls, permit-to-work systems, and competent-person supervision, satisfying CDM 2015 Principal Contractor duties and client PQQ pre-qualification requirements for mechanical services frameworks.

Statutory FrameworkF-Gas Regulations, BESA SFG20, TR19, PUWER 1998 LOTO Isolation, CIS Reverse Charge VAT
ClassificationF-Gas Regulations 2015 (EU Reg 517/2014 retained UK law) mandate certified engineers (City & Guilds 2079 F-Gas Cat I) for refrigerant handling; common refrigerants include R410A (GWP 2088), R32 (GWP 675), R134a (GWP 1430). GHS Classification: Gases under pressure (H280), simple asphyxiant in confined spaces. TR19 (BESA 2013) specifies AHU internal cleanliness grades; SFG20 (2020 ed.) defines task frequencies (e.g. filter change quarterly, coil clean annually). PUWER 1998 Reg 19 requires isolation (LOTO) of fans/motors before maintenance. CIS Domestic Reverse Charge (VATA 1994 s.55A, effective 1 March 2021) applies to building/construction services; standard-rated supplies (e.g. refrigerant gas, filters) remain 20% VAT. COSHH: Coil cleaners (e.g. alkaline/acidic detergents) require SDS review; Legionella risk per HSG274 Part 2 (AHU humidifiers/cooling coils). EH40 WEL: R410A 1000 ppm (8-hr TWA).
Required Plant / KitF-Gas certified refrigerant recovery unit (e.g. Javac Bulldog) with electronic scales & hoses • Calibrated digital manifold gauge set (4-valve, 0–600 psi) for superheat/subcooling checks • Lockable electrical isolation kit: MCB lockout devices, hasp & padlock, 'Danger: Men Working' tags • TR19 hygiene sampling kit: sterile swabs, ATP luminometer, surface contact plates • Mobile scaffold tower (BS EN 1004:2020) or podium step (3 m working height) for AHU access
1-Click RAMS HandoverQuote + 5×5 RAMS Supported
Price This Job & Unlock the Matching 5×5 RAMS in 1 Click

Need a Priced Quote or Custom QUOTE for Your Site?

Dictate your job scope in our Voice-to-Quote Studio to generate a watermarked UK Trade BoQ preview (and unlock the matching 5×5 RAMS for £0 extra when the PO lands)—or download our free blank Word (.doc) shell below.

Price This Job + RAMS (Free Preview)

Benchmark 2026 UK Trade Bill of Quantities (BoQ) & Rate Card Schedule

Need to price this scope for a client buyer? Dictate your scope in the SafeSequence Voice-to-Quote Studio to compile a custom BoQ, auto-fill your blank .docx letterhead, and unlock the matching 5×5 RAMS below at £0 extra credit cost when the PO lands.

Code Trade Item & Specification Category Qty / Unit Unit Rate Net Total
M-HVAC-010R32 refrigerant gas (10 kg cylinder, virgin, GWP 675) – supply only, F-Gas certified handling. Standard-rated 20% VAT (not CIS reverse charge).Materials1 No. cylinder£285.00£285.00
M-HVAC-020MERV 8 pleated panel filter set (592×592×48 mm) for AHU – supply & fit, inc. disposal of used filters (EWC 15 01 02).Materials4 No. filters£38.50£154.00
P-HVAC-030Mobile aluminium scaffold tower hire (4 m platform height, BS EN 1004:2020) – 1 week hire inc. delivery, erection, inspection (PASMA cert).Plant1 No. week£175.00£175.00
L-HVAC-040JIB-approved HVAC Technician (ECS Gold Card + F-Gas Cat I cert) – planned maintenance visit: isolation, filter change, coil clean, refrigerant check, TR19 swab, re-commission. CIS Domestic Reverse Charge applies (VATA 1994 s.55A); client accounts for VAT.Labour8 hrs£52.00£416.00

1. Mandatory Personal Protective Equipment (BS EN Standards)

BS EN 374-1:2016 Type B, AQL ≤1.5
Nitrile chemical-resistant gloves (coil cleaner handling, refrigerant contact)
Protect against alkaline/acidic coil detergents (pH 2–12) and refrigerant skin contact (frostbite risk from liquid phase).
BS EN 166:2001 Class 1 Optical, Frame F
Safety spectacles with side shields (splash/particle protection)
Mandatory during coil cleaning (chemical splash) and filter removal (dust/fibres); TR19 hygiene sampling requires eye protection.
BS EN ISO 20345:2011 S3 SRC
Safety boots with midsole protection and slip-resistant sole
Protect against dropped cylinders (10 kg refrigerant), wet AHU plenums (slip hazard), and penetration from metal fixings.
BS EN 149:2001+A1:2009 FFP2 (94% filtration)
FFP2 disposable respirator (valve optional)
Required when removing heavily contaminated filters (bioaerosols, Legionella risk per HSG274) or working in dusty AHU plenums.

2. 5×5 Hazard Risk Assessment Matrix (HASAWA 1974 / CDM 2015)

Identified Hazard & HarmInitial Risk (L×S)Mandatory Engineering, Isolation & Procedural ControlsResidual Risk
1. Refrigerant exposure (R32, R410A) – inhalation, asphyxiation in confined AHU plant rooms, or frostbite from liquid contact
Harm: Asphyxiation (oxygen displacement <19.5%), cardiac sensitisation (high concentrations), cold burns (liquid refrigerant −51°C)
4 × 4 = 16F-Gas Cat I certified engineer only; pre-work O₂ monitoring (<19.5% stop work); forced ventilation (10 ACH min.); wear nitrile gloves (BS EN 374); refrigerant recovery before opening system; emergency eyewash station within 10 m.2 × 2 = 4
2. Electrical shock from live AHU fan motors, control panels, or VSD drives (230/400 V 3-ph)
Harm: Electrocution (fatal), severe burns, arc flash injury
5 × 5 = 25PUWER 1998 Reg 19 LOTO: isolate at local isolator & main distribution board; fit MCB lockout devices & personal padlock; affix 'Danger: Men Working' tag; prove dead with calibrated voltage tester (GS38); permit-to-work for >400 V; AP (Authorised Person) supervision.1 × 3 = 3
3. Working at height – accessing rooftop AHU, changing filters on elevated plenums (2–4 m)
Harm: Fall from height causing fractures, head injury, or fatality
4 × 5 = 20Use mobile scaffold tower (BS EN 1004:2020, PASMA-trained erector, weekly inspection); guardrails on all open sides; 3:1 base:height ratio; toe boards; alternatively, podium step with handrails; no ladders for prolonged work; edge protection on roofs (collective measures per Work at Height Regs 2005).2 × 3 = 6
4. Rotating machinery entanglement – AHU fan impellers, belt drives, motor couplings during inspection/cleaning
Harm: Crush injury to hands/fingers, amputation, entanglement of clothing/hair
3 × 5 = 15LOTO isolation (see Hazard 2) before opening AHU access doors; verify fan stationary (visual + try-to-turn test); remove watches/jewellery; secure long hair; replace all guarding (BS EN ISO 14120) before re-energising; two-person rule for confined AHU plenums.1 × 4 = 4
5. Legionella bacteria exposure from AHU cooling coils, humidifiers, or condensate trays (bioaerosol inhalation)
Harm: Legionnaires' disease (pneumonia, 10% fatality), Pontiac fever (flu-like illness)
3 × 4 = 12HSG274 Part 2 compliance: quarterly TR19 hygiene swabs (ATP <500 RLU pass); biocide dosing of humidifiers; drain & clean condensate trays; coil disinfection (quaternary ammonium or chlorine dioxide, 10 min contact); wear FFP2 respirator during cleaning; Legionella risk assessment reviewed annually by competent person (e.g. Legionella Control Association cert).2 × 2 = 4

3. Step-by-Step Safe Sequence of Operations & Hold-Points

1

Site induction, permit-to-work issue, and PUWER LOTO electrical isolation

Pre-Start & Isolation

Attend client site induction; confirm AHU location, refrigerant type (nameplate check), and SFG20 task scope. Obtain permit-to-work from Authorised Person (AP). Isolate AHU at local isolator and main distribution board; fit MCB lockout devices and personal padlock; affix 'Danger: Men Working' tag with name/date. Prove dead at fan motor terminals and control panel using calibrated voltage tester (GS38). Test emergency stop functionality. Erect mobile scaffold tower (if required) with PASMA inspection record; check guardrails, toe boards, and 3:1 stability ratio.

Critical Hold-Point: ⚠ STOP: Do NOT open AHU access doors until electrical isolation is proven dead and LOTO padlock is in place. Failure to isolate can result in fatal electrocution or entanglement with live rotating fans.
2

Open AHU, conduct TR19 hygiene assessment, and photograph pre-work condition

Access & Initial Inspection

Don FFP2 respirator and safety spectacles. Open AHU access panels (fan, filter, coil sections). Visually inspect for standing water in condensate trays, visible mould/biofilm on coils, and filter loading. Take TR19 hygiene swabs from cooling coil surface and condensate tray; record ATP readings (target <500 RLU). Photograph filter condition, coil fouling, and any corrosion. Check fan impeller for debris/damage and belt tension (if belt-driven). Record findings on SFG20 task sheet.

Critical Hold-Point: ⚠ STOP: If ATP reading >1000 RLU or visible Legionella risk (stagnant water, heavy biofilm), escalate to Legionella competent person before proceeding. Do not disturb contaminated surfaces without enhanced RPE (FFP3 or powered).
3

Replace filters, clean cooling coils with approved biocide, and drain condensate trays

Filter & Coil Maintenance

Remove and bag used filters (EWC 15 01 02 waste code); dispose per site waste management plan. Fit new MERV 8 filters (check airflow direction arrow). Spray cooling coils with approved coil cleaner (pH-neutral or mild alkaline; consult SDS); allow 10 min contact time. Rinse with low-pressure water (avoid fin damage). Apply biocide (quaternary ammonium or chlorine dioxide, 200 ppm) to coils and condensate tray; leave 10 min contact. Drain and flush condensate trays; check trap seal (U-bend water level). Wipe fan impeller blades with damp cloth.

Critical Hold-Point: ⚠ STOP: Wear nitrile gloves (BS EN 374) and eye protection when handling coil cleaners. Ensure adequate ventilation (10 ACH) to prevent chemical vapour build-up. Never mix alkaline and acidic cleaners (exothermic reaction risk).
4

F-Gas certified engineer: leak test, pressure/temperature checks, top-up if required

Refrigerant System Check

Connect calibrated digital manifold gauges to service ports (low/high side). Record suction/discharge pressures and temperatures. Calculate superheat (suction temp − evaporator saturation temp; target 8–12°C) and subcooling (condenser saturation temp − liquid line temp; target 5–7°C). Perform electronic leak detection (heated diode or infrared sensor, 5 g/yr sensitivity per F-Gas Regs). If leak detected, mark location, recover refrigerant, repair, pressure test (nitrogen 1.1× design pressure, 24 hr hold), vacuum to 500 microns, recharge to nameplate weight (±2%). Record refrigerant type, GWP, quantity added, and cylinder batch number in site F-Gas log.

Critical Hold-Point: ⚠ STOP: Only F-Gas Cat I certified engineers may handle refrigerants. Never vent refrigerant to atmosphere (illegal under F-Gas Regs; £200k fine). Use recovery unit for all refrigerant removal. Ensure O₂ monitor alarmed if working in plant room <100 m³.
5

Refit all guarding, remove tools, and conduct pre-start safety inspection

Re-Assembly & Pre-Energisation Checks

Refit all AHU access panels and secure with original fasteners. Verify all tools and cleaning materials removed from AHU interior (tool count check). Confirm fan impeller rotates freely by hand (no obstruction). Check belt tension and alignment (if applicable). Inspect motor bearings for noise/play. Verify condensate drain trap seal. Replace any damaged insulation or gaskets. Complete SFG20 task sheet with filter type/date, ATP results, refrigerant pressures, and any defects. Photograph completed work.

Critical Hold-Point: ⚠ STOP: Do NOT re-energise until all access panels are secured and tool count verified. Loose tools left inside AHU can cause catastrophic fan failure, projectile hazards, or fire (motor overload).
6

Remove LOTO, restore power, commission AHU, and hand back to client with certification

Re-Energisation & Commissioning

Remove personal padlock and LOTO devices (only the person who fitted them may remove). Restore power at distribution board and local isolator. Start AHU in manual mode; listen for abnormal noise (bearing wear, belt squeal). Check fan rotation direction (compare to nameplate arrow). Measure supply air temperature and velocity (anemometer at grille). Verify BMS communication and setpoint control. Run for 15 min; re-check refrigerant pressures under load. Issue SFG20 certificate of completion, TR19 hygiene report, and F-Gas service record to client. Update asset register and schedule next service (per SFG20 frequency, typically 6–12 months).

Critical Hold-Point: ⚠ STOP: If abnormal noise, vibration, or tripping occurs on start-up, isolate immediately and investigate. Do not leave site until AHU is running stably and client/FM representative has signed off. Ensure permit-to-work is closed out with AP.

Emergency Rescue, First Aid & Spill Protocol

**Emergency Contact:** Dial 999 (ambulance/fire). Site Emergency Assembly Point: [Insert location]. **Refrigerant Exposure:** Move casualty to fresh air immediately; if unconscious, place in recovery position and administer O₂ if trained. For liquid refrigerant contact (frostbite), irrigate affected skin/eyes with lukewarm water (15 min); do NOT rub. Seek medical attention. **Electrical Shock:** Do NOT touch casualty if still in contact with live conductor; isolate power first. If casualty not breathing, commence CPR (30 compressions:2 breaths) and deploy AED. Call 999. Treat burns with cool running water (20 min). **Fall from Height:** Do not move casualty if spinal injury suspected; call 999 and keep warm. Control bleeding with direct pressure. **Chemical Splash (Coil Cleaner):** Irrigate eyes/skin with eyewash station or running water (15 min). Remove contaminated clothing. Consult SDS for specific first aid (e.g. alkaline burns may require medical attention). **Legionella Suspected Exposure:** If flu-like symptoms develop within 2–10 days post-work (fever, cough, shortness of breath), seek urgent medical attention and inform GP of potential Legionella exposure; early antibiotic treatment is critical. **First Aid:** Minimum 1× First Aid at Work (FAW) trained person on site; first aid kit to BS 8599-1. Accident reporting: RIDDOR notification required for >7-day absence, major injury, or dangerous occurrence (HSE online F2508 within 15 days).

4. UK Commercial, HSE & PQQ Compliance FAQs: HVAC, Air Conditioning & AHU Maintenance Quotation & Priced BoQ Template UK

5. Operative Toolbox Talk & Competent Person Sign-Off Register

Operative / Supervisor Name Trade / Role & CSCS No. Signature Date & Time
1. (Site Supervisor):     
2.     
3.     
4.     

Price the Job & Automate UK Safety Compliance with SafeSequence®

Need a priced commercial quote or site-specific compliance pack instead of a static template? Explore the live SafeSequence® UK studios hosted in AWS London (eu-west-2):

Voice-to-Quote & 1-Click RAMS Dictate your job scope to compile a priced UK Trade BoQ, auto-fill your blank .docx letterhead & unlock the matching 5×5 RAMS for £0 extra. PCI Tender-to-RAMS Studio Upload 300-page Principal Contractor PCI PDFs for [Page X] cited RAMS & PAS 91 answers. Voice RAMS & CLP COSHH Dictate site tasks or scan chemical tins to generate UK 5×5 RAMS & Reg 6 COSHH PDFs. Enterprise Admin Command Hub Unlock custom logo branding, saved company rate cards, Visual Video SOPs, 6S OPLs & CAPAs.

Related UK Quote, Tender & Safety Templates