Pre-Construction Information (PCI) Pack Example & Subcontractor RAMS Guide (TENDER Template & 5x5 Risk Assessment)

Under CDM 2015 Regulation 4 (Client duties) and Regulation 12 (Principal Designer duties), clients must ensure Pre-Construction Information (PCI) is prepared and provided to all designers and contractors before construction commences, containing proportionate information about the site, existing structures, and significant health and safety risks. The PCI must enable competent contractors to plan, manage, and monitor construction work safely, reducing residual risk to ALARP (As Low As Reasonably Practicable) in accordance with HASAWA 1974 Section 3 and HSG150 guidance. This document provides a comprehensive PCI Pack example with subcontractor RAMS integration templates, demonstrating how principal contractors and principal designers discharge their statutory duties through structured information exchange, hazard identification, and control measure specification. The PCI must be proportionate, relevant, and sufficient to enable proper planning and resource allocation, forming the foundation for Construction Phase Plans and site-specific Risk Assessments and Method Statements (RAMS).

Statutory FrameworkCDM 2015 Regulation 4 & Regulation 12, HASAWA 1974, HSG150
ClassificationNot applicable – this is a procedural/documentation template for CDM 2015 compliance. However, PCI Packs must identify any hazardous substances present on site (asbestos, contaminated land, existing chemical stores) with reference to COSHH 2002 and CLP Regulation (EC) 1272/2008. Where hazardous materials are identified, GHS pictograms and Safety Data Sheets must be referenced in [Page 12-15] of the PCI Pack under "Existing Site Hazards and Contamination".
Required Plant / KitPCI Pack template (digital PDF/Word format compliant with CDM 2015 Appendix 2 and HSG150 Appendix 3) • Site survey equipment (laser distance measurers, moisture meters, asbestos sampling kits for intrusive surveys) • Document management system (ISO 19650-compliant BIM/CDE platform for PCI distribution and version control) • Risk assessment software (5x5 matrix calculator with ALARP demonstration and residual risk tracking) • PAS 91 Pre-Qualification Questionnaire template (Construction Line Gold/SSIP-aligned for subcontractor vetting)
Site Sign-Off StatusRequires Competent Person Verification
Bid-Winning PCI Tender Studio or Instant Voice Customization

Bidding a Contract or Need This TENDER Customized for Your Site?

Drop your client's Pre-Construction Information (PCI) PDF into our Tender Studio to generate a page-cited 5×5 RAMS & PQQ pack—or download our free blank Word (.doc) shell below.

Upload Client PCI / PQQ PDF (30s)

1. Mandatory Personal Protective Equipment (BS EN Standards)

BS EN ISO 20345:2011 S3 SRC
Safety footwear with steel toecap and midsole protection
Mandatory for all site visits during PCI survey phase to protect against crush injuries, penetration hazards, and slips on uneven/contaminated ground as identified in [Page 8] Site Access and Ground Conditions
BS EN ISO 20471:2013 Class 2 or 3
High-visibility vest or jacket (Class 2 minimum for site surveys)
Required during all site reconnaissance and PCI data-gathering activities to ensure visibility to plant operators and existing site occupants, particularly in operational environments or near highways
BS EN 397:2012+A1:2012
Safety helmet with chin strap for overhead hazard zones
Compulsory when surveying existing structures, multi-storey buildings, or areas with overhead services identified in [Page 10] Existing Structures and Overhead Hazards section of PCI
BS EN 388:2016 Level 4 cut resistance (minimum 2X42C)
Cut-resistant gloves for handling sharp materials during surveys
Essential when inspecting existing structures with sharp edges, broken glass, or metal protrusions during intrusive PCI surveys and asbestos sampling activities

2. 5×5 Hazard Risk Assessment Matrix (HASAWA 1974 / CDM 2015)

Identified Hazard & HarmInitial Risk (L×S)Mandatory Engineering, Isolation & Procedural ControlsResidual Risk
1. Inadequate or incomplete Pre-Construction Information leading to unidentified site hazards
Harm: Contractors commence work without knowledge of asbestos, underground services, structural instability, or contaminated land, resulting in fatal incidents, HSE enforcement (Improvement/Prohibition Notices), and CDM 2015 Regulation 4/12 prosecution
4 × 5 = 20Principal Designer must collate PCI from client, surveys (asbestos R&D, topographical, geotechnical, utility searches), and existing H&S files per CDM 2015 Reg 12(2). PCI must be issued to all tenderers at [Page 1-3] Executive Summary with clear hazard register. Use HSG150 Appendix 3 checklist to verify completeness. Client to provide written confirmation of information accuracy per Reg 4(5). Residual risk: contractors receive comprehensive, verified PCI enabling informed RAMS preparation.2 × 3 = 6
2. Subcontractor RAMS incompatible with Principal Contractor's Construction Phase Plan
Harm: Conflicting work methods, inadequate segregation, simultaneous operations causing struck-by incidents, falls from height, or plant/pedestrian interface collisions; HSE investigation under CDM 2015 Reg 13 and Reg 15
5 × 4 = 20Principal Contractor must issue PCI Pack [Page 18-22] containing site rules, permit systems, exclusion zones, and RAMS submission template aligned to Construction Phase Plan. Implement 3-stage RAMS review: (1) Pre-start desktop review against PCI, (2) Pre-construction meeting with method statement walk-through, (3) On-site verification before work commences. Reject non-compliant RAMS with written feedback. Residual risk: all subcontractor activities coordinated and compatible with site-wide controls.2 × 2 = 4
3. Failure to identify existing asbestos or hazardous materials in PCI
Harm: Disturbance of ACMs during demolition/refurbishment causing asbestos fibre release, mesothelioma, lung cancer, asbestosis; HSE prosecution under Control of Asbestos Regulations 2012 Reg 4 and CDM 2015 Reg 4(4)
3 × 5 = 15Client must commission UKAS-accredited asbestos R&D survey (HSG264 Type 3 refurbishment/demolition survey) before PCI issue. Survey results and asbestos register must be included at [Page 12-14] of PCI with clear location plans and condition assessments. Licensed asbestos removal must be completed pre-construction or method statements must include HSE notification (14 days) and licensed contractor appointment. Residual risk: all ACMs identified, removed, or managed with licensed controls.2 × 3 = 6
4. Inadequate site access and egress information in PCI causing vehicle/plant collisions
Harm: Delivery vehicles, mobile plant, and site traffic collide with pedestrians, existing structures, or overhead lines due to insufficient access route specifications; fatalities and serious crush injuries
4 × 5 = 20PCI [Page 7-9] must include scaled site plan showing access routes, turning circles, weight restrictions, overhead line heights (with PAS 128 utility survey), and pedestrian segregation. Specify delivery times, banksman requirements, and exclusion zones. Principal Contractor to issue site traffic management plan (STMP) based on PCI data, with segregated routes, speed limits (10mph max), and marshalling points. Residual risk: all vehicle movements planned with engineered segregation and competent supervision.2 × 3 = 6
5. Insufficient information on existing services (electric, gas, water, telecoms) leading to strikes
Harm: Excavation or drilling strikes live electric cables (11kV or 415V), gas mains, or water pipes causing electrocution, explosion, flooding, and service disruption; fatalities and HSE prosecution under CDM 2015 and Electricity at Work Regulations 1989
4 × 5 = 20Client must commission PAS 128 Type B utility survey (electromagnetic detection and GPR) and provide statutory undertaker plans (C2, C4 searches) in PCI [Page 15-17]. All services must be marked on site plans with depth, voltage/pressure, and isolation points. Specify Cable Avoidance Tool (CAT) and Genny use, trial holes, and permit-to-dig system. Principal Contractor to implement LOTO (Lock-Out/Tag-Out) for any service isolation. Residual risk: all services located, marked, and isolated before intrusive works.2 × 2 = 4

3. Step-by-Step Safe Sequence of Operations & Hold-Points

1

Commission surveys, collate existing information, and draft PCI Pack per CDM 2015 Reg 4 & 12

Pre-Tender: Client and Principal Designer PCI Preparation

Client appoints Principal Designer (competent per CDM 2015 Reg 8) who commissions: asbestos R&D survey (HSG264), topographical survey, geotechnical investigation, PAS 128 utility survey, structural condition survey, and contaminated land assessment. Collate existing H&S File, planning conditions, environmental permits, and party wall agreements. Principal Designer drafts PCI Pack using HSG150 Appendix 3 template, including [Page 1-3] Executive Summary, [Page 4-6] Site Description and Constraints, [Page 7-9] Access and Logistics, [Page 10-11] Existing Structures, [Page 12-15] Hazardous Materials, [Page 16-17] Services, [Page 18-22] Site Rules and RAMS Requirements. Client reviews and signs PCI accuracy declaration per Reg 4(5).

Critical Hold-Point: HOLD POINT: PCI must not be issued to tenderers until Client has reviewed and confirmed accuracy in writing. Incomplete or inaccurate PCI breaches CDM 2015 Reg 4(4) and exposes Client to prosecution if contractors are misled about site hazards.
2

Issue PCI Pack to all tendering Principal Contractors and manage RFI process

Tender Stage: PCI Distribution and Tenderer Queries

Principal Designer issues PCI Pack (PDF and native CAD/BIM files) via secure portal to all tendering Principal Contractors minimum 4 weeks before tender return. Include covering letter stating PCI is issued under CDM 2015 Reg 12(5) and tenderers must allow for all identified hazards in pricing. Establish RFI (Request for Information) log for tenderer queries about PCI content. Principal Designer responds to RFIs within 5 working days and issues clarifications to all tenderers to maintain competitive parity. Record all RFIs and responses in PCI amendment log [Page 23].

Critical Hold-Point: CRITICAL: All tenderers must receive identical PCI and clarifications. Selective disclosure of hazard information breaches procurement fairness and CDM 2015 transparency requirements, and may invalidate tender process.
3

Evaluate tenderer competence using PAS 91 criteria and review outline RAMS submissions

Tender Evaluation: Subcontractor PQQ and RAMS Assessment

Principal Contractor (tenderer) completes PAS 91 Pre-Qualification Questionnaire demonstrating: CHAS/Construction Line Gold/SSIP membership, employer's liability insurance (£10m minimum), H&S policy, competence evidence (CSCS cards, SMSTS/SSSTS, plant operator certificates), and previous project references. Submit outline RAMS for high-risk activities identified in PCI [Page 18-20] including: asbestos removal, working at height >2m, excavations >1.2m depth, lifting operations, and work near live services. Client and Principal Designer score tenders using quality/price matrix (60/40 weighting) with mandatory pass/fail on H&S competence.

Critical Hold-Point: HOLD POINT: Do not appoint Principal Contractor who fails to demonstrate competence per CDM 2015 Reg 8 or submits inadequate outline RAMS. Client retains liability under Reg 4(1) for appointing incompetent duty holders.
4

Appointed Principal Contractor develops Construction Phase Plan using PCI as foundation

Pre-Construction: Principal Contractor Construction Phase Plan Development

Appointed Principal Contractor receives updated PCI (incorporating tender clarifications) and develops Construction Phase Plan per CDM 2015 Reg 15. Plan must reference PCI [Page numbers] and expand on: site-specific risk assessments, method statements for all work packages, site rules, permit systems (hot works, confined space, excavation, lifting), emergency procedures, welfare facilities, induction content, and subcontractor coordination procedures. Submit draft Construction Phase Plan to Principal Designer for review minimum 4 weeks before construction start. Principal Designer verifies plan addresses all PCI hazards and is proportionate to project scale/complexity.

Critical Hold-Point: HOLD POINT: Construction work must not commence until Principal Contractor has prepared Construction Phase Plan and Principal Designer has confirmed it adequately addresses PCI hazards per CDM 2015 Reg 15(4). Client must not allow construction start without this confirmation.
5

Subcontractors submit detailed RAMS aligned to PCI and Construction Phase Plan for approval

Pre-Construction: Subcontractor RAMS Submission and Approval

Each subcontractor submits task-specific RAMS minimum 2 weeks before work package start, using template provided in PCI [Page 21-22]. RAMS must include: scope of work, hazard identification (cross-referenced to PCI hazards), 5x5 risk assessment with initial and residual scores, control measures (hierarchy: elimination, substitution, engineering, administrative, PPE), competence requirements, plant/equipment specifications, emergency procedures, and environmental controls. Principal Contractor reviews RAMS using 3-stage process: (1) Desktop review against Construction Phase Plan, (2) Pre-start meeting with subcontractor supervision, (3) On-site verification walk-through. Approve, reject, or request revisions within 5 working days.

Critical Hold-Point: CRITICAL: No subcontractor work activity may commence without approved, site-specific RAMS. Principal Contractor must verify RAMS compliance on-site before work starts and stop work immediately if actual methods deviate from approved RAMS.
6

Monitor PCI accuracy, update for design changes, and compile H&S File for handover

Construction: PCI Review, Update, and H&S File Handover

Principal Designer monitors PCI accuracy throughout construction and issues revisions if new hazards emerge (e.g., unexpected asbestos, uncharted services, ground conditions). Principal Contractor notifies Principal Designer of any PCI inaccuracies within 24 hours. At practical completion, Principal Designer compiles H&S File per CDM 2015 Reg 12(6) containing: as-built drawings, asset maintenance requirements, residual hazards (e.g., fragile roofs, confined spaces), operation and maintenance manuals, and records of installed safety systems. Client receives H&S File and PCI archive for future projects. Principal Designer retains PCI and H&S File records for minimum 6 years (limitation period for CDM prosecution).

Critical Hold-Point: HOLD POINT: Client must not take possession of completed structure without receiving H&S File from Principal Designer. Failure to provide H&S File breaches CDM 2015 Reg 12(6) and leaves Client unable to manage ongoing H&S risks during occupation and future maintenance.

Emergency Rescue, First Aid & Spill Protocol

In the event of an incident arising from inadequate PCI or RAMS failure: (1) Stop all work immediately and secure the area – Principal Contractor to implement emergency procedures per Construction Phase Plan [Page 35-37]; (2) Administer first aid if injuries occur – minimum 1 appointed person per 50 workers (HSE guidance), with first aid room for sites >150 workers; (3) Contact emergency services (999) for serious injuries, electrocution, asbestos exposure, or service strikes – provide site address, access route from PCI [Page 7], and nature of incident; (4) Notify HSE under RIDDOR 2013 within 10 days for >7-day injuries, within 15 days for occupational disease (e.g., asbestos exposure), and immediately for fatalities, major injuries, or dangerous occurrences; (5) Preserve incident scene for HSE investigation – do not disturb evidence unless necessary to prevent further harm; (6) Principal Contractor to conduct immediate investigation, review RAMS and PCI adequacy, and issue safety alert to all subcontractors; (7) Principal Designer to review whether PCI omission or inaccuracy contributed to incident and update PCI/H&S File accordingly; (8) Client to review competence of duty holders and consider CDM 2015 compliance audit. All incidents must be recorded in site accident book and reported in monthly H&S statistics. For asbestos disturbance, implement emergency procedures per HSG264: evacuate area, seal with polythene, engage licensed asbestos contractor for clearance testing, and notify HSE if >10 minutes uncontrolled exposure.

4. UK HSE & PQQ Compliance FAQs: Pre-Construction Information (PCI) Pack Example & Subcontractor RAMS Guide

5. Operative Toolbox Talk & Competent Person Sign-Off Register

Operative / Supervisor Name Trade / Role & CSCS No. Signature Date & Time
1. (Site Supervisor):     
2.     
3.     
4.     