Industrial Roofing, Cladding & Gutter Repairs Quote, BoQ & 5x5 RAMS Template UK

Under the Work at Height Regulations 2005 (Reg. 4–6), CDM 2015 (Reg. 13), HSG33 (Health & Safety in Roof Work), and ACR[M]001 (Avoiding Danger from Fragile Roofs), every industrial roofing, cladding, and gutter repair must be planned by a competent person, use collective fall protection (edge protection, guardrails, safety nets) in preference to personal fall arrest, and reduce residual fall-from-height risk to ≤6 (5×5 matrix). This audit-grade UK commercial quote, Bill of Quantities (BoQ), and 5×5 Risk Assessment & Method Statement (RAMS) template integrates 2026 UK trade rates (Materials, Plant, Labour in £ GBP), CIS Domestic Reverse Charge VAT treatment (VATA 1994 s.55A), and pre-staged safe systems of work. Once a Client Purchase Order is locked, the contractor automatically unlocks the pre-staged 5×5 RAMS, ensuring full CDM Principal Contractor compliance, BS EN-certified PPE (fall arrest harness EN 361, safety helmet EN 397, work-at-height footwear EN ISO 20345 S3), and documented permit-to-work for fragile roof access. Suitable for main contractors, roofing specialists, facilities managers, and CDM Principal Designers tendering industrial roof repairs, re-cladding, or gutter replacement across the UK.

Statutory FrameworkWork at Height Regulations 2005, ACR[M]001 Fragile Roofs, HSG33, CDM 2015, CIS Reverse Charge
ClassificationNot applicable—this is a construction work-at-height activity. However, sealants, mastics, and bitumen-based roof coatings may carry GHS07 (irritant) or GHS08 (respiratory sensitiser) pictograms. Consult manufacturer Safety Data Sheets (SDS) for each roofing compound. Ensure adequate ventilation and respiratory protection (FFP3 / BS EN 149:2001+A1:2009) when applying solvent-based coatings or hot bitumen in confined roof valleys.
Required Plant / KitMobile Elevated Work Platform (MEWP) / Cherry Picker – 3.5 t GVW, 12 m working height, LOLER-inspected, operator IPAF-certified • Aluminium scaffold tower (BS EN 1004:2004) with guardrails, toe-boards, and outriggers for edge protection • Personal Fall Arrest System (PFAS): full-body harness (EN 361), twin-leg lanyard with shock absorber (EN 355), anchor sling (EN 795 Class B) • Cordless impact driver (18 V Li-ion) and socket set for cladding fixings, plus torque wrench for structural bolts • Roof ladder with ridge hook (BS 1129) and crawling boards for fragile roof access, plus roof safety anchor points (EN 795 Class A2)
1-Click RAMS HandoverQuote + 5×5 RAMS Supported
Price This Job & Unlock the Matching 5×5 RAMS in 1 Click

Need a Priced Quote or Custom QUOTE for Your Site?

Dictate your job scope in our Voice-to-Quote Studio to generate a watermarked UK Trade BoQ preview (and unlock the matching 5×5 RAMS for £0 extra when the PO lands)—or download our free blank Word (.doc) shell below.

Price This Job + RAMS (Free Preview)

Benchmark 2026 UK Trade Bill of Quantities (BoQ) & Rate Card Schedule

Need to price this scope for a client buyer? Dictate your scope in the SafeSequence Voice-to-Quote Studio to compile a custom BoQ, auto-fill your blank .docx letterhead, and unlock the matching 5×5 RAMS below at £0 extra credit cost when the PO lands.

Code Trade Item & Specification Category Qty / Unit Unit Rate Net Total
M-RFC-001Trapezoidal steel roof cladding sheets, 0.7 mm pre-coated Colorcoat HPS200 Ultra, 6.0 m × 1.0 m cover width, inc. fixings, flashings, and 10% waste allowanceMaterials85 m²£42.50£3,612.50
M-GUT-002Aluminium box gutter sections (mill finish, 150 mm × 100 mm), inc. end caps, unions, brackets, and silicone sealant; compliant with BS EN 612Materials22 linear m£38.00£836.00
P-MEWP-003Mobile Elevated Work Platform (MEWP) hire – 12 m working height, 3.5 t GVW, LOLER-inspected, delivered, operated by IPAF-certified operative, 5-day hirePlant1 week£875.00£875.00
L-ROF-004JIB-graded Industrial Roofer / Cladding Operative (Gold Card), CSCS, IPAF 3a/3b, Work at Height trained, inc. travel, supervision, and tool-time; standard 39-hour weekLabour80 hours£28.50£2,280.00

1. Mandatory Personal Protective Equipment (BS EN Standards)

BS EN 361:2002
Full-body fall arrest harness with dorsal & sternal D-rings, adjustable leg & chest straps
Mandatory personal fall protection when working >2 m height and collective measures (guardrails, nets) are not reasonably practicable; must be inspected every 6 months per LOLER 1998.
BS EN 397:2012+A1:2012
Safety helmet (industrial, vented, 6-point textile cradle, chin strap)
Protects against falling objects (tools, fixings, cladding offcuts) and head impact on roof trusses; mandatory on all CDM 2015 construction sites.
BS EN ISO 20345:2011 S3 SRC
Safety footwear (S3 work boots): steel toe-cap, midsole penetration resistance, water-resistant leather, cleated sole
Prevents puncture injuries from roof fixings, provides slip resistance on wet cladding (SRC rating), and protects against falling materials.
BS EN 388:2016+A1:2018 (4X42C)
Cut-resistant gloves (Level C blade cut, abrasion Level 4, tear Level 4)
Protects hands from sharp metal edges, cladding swarf, and gutter burrs during handling and installation; essential for manual handling of steel sheets.

2. 5×5 Hazard Risk Assessment Matrix (HASAWA 1974 / CDM 2015)

Identified Hazard & HarmInitial Risk (L×S)Mandatory Engineering, Isolation & Procedural ControlsResidual Risk
1. Fall from height (>2 m) through fragile roof lights, unprotected roof edges, or during MEWP operation
Harm: Fatal or life-changing injuries: spinal fracture, traumatic brain injury, multiple fractures, permanent disability
4 × 5 = 20• Appoint competent person (SSSTS/SMSTS) to plan work per Work at Height Regs 2005 Reg. 4–6. • Erect collective edge protection (guardrails, toe-boards) to all open edges per BS EN 13374 Class A. • Cover or barrier-off all fragile roof lights; use roof ladders & crawling boards (BS 1129) to distribute load. • MEWP operator must hold valid IPAF 3a/3b; daily pre-use checks per LOLER 1998. • All operatives wear full-body harness (EN 361) + twin-leg lanyard (EN 355) attached to EN 795 Class A2 anchor. • Rescue plan in place; rescue equipment (descent device, stretcher) on-site. • Weather monitoring: cease work if wind >10 m/s or rain makes surfaces slippery.2 × 5 = 10
2. Manual handling of heavy/awkward cladding sheets (6 m × 1 m, ~18 kg each) causing musculoskeletal injury
Harm: Back strain, shoulder injury, trapped fingers, lacerations from sharp edges
4 × 3 = 12• Conduct Manual Handling Risk Assessment per Manual Handling Operations Regulations 1992. • Use mechanical aids: MEWP platform, material hoist, or crane for lifting sheets to roof level. • Two-person lift for all sheets >15 kg; team briefing on safe grip points and communication signals. • Pre-cut sheets to manageable lengths where possible; store vertically in A-frame racks. • Wear cut-resistant gloves (EN 388:2016 Level C) to prevent hand injuries. • Provide lifting training and toolbox talk on kinetic handling techniques.2 × 3 = 6
3. Adverse weather: high winds, rain, ice, or lightning during exposed roof work
Harm: Loss of balance, slips, wind-blown materials striking operatives, lightning strike
3 × 4 = 12• Monitor Met Office forecasts daily; cease work if wind speed >10 m/s (Beaufort Scale 5) or gusts >15 m/s. • Stop work immediately if lightning detected within 10 miles (use lightning detection app). • Do not work on wet, icy, or snow-covered roofs; apply anti-slip grit or defer until dry. • Secure all loose materials (sheets, tools) with lanyards or weighted bags to prevent wind-lift. • Provide high-visibility waterproof clothing (EN ISO 20471 Class 3) and thermal layers in cold weather. • Establish safe refuge area at ground level; communicate weather hold via two-way radio.2 × 4 = 8
4. Contact with live overhead power lines or buried services during MEWP positioning or drilling
Harm: Electrocution (fatal), arc flash burns, explosion if gas main struck
2 × 5 = 10• Obtain up-to-date utility plans (electricity, gas, water, telecoms) from asset owners (UKPN, Cadent, etc.). • Use Cable Avoidance Tool (CAT) and Signal Generator (Genny) to locate buried services; mark with spray paint. • Maintain minimum 3 m exclusion zone from overhead lines; if <3 m, arrange isolation or goal-post barriers with DNO. • MEWP boom must never approach within 3 m of live conductors; appoint trained banksman. • Permit-to-Work for any drilling or penetration; hand-dig trial holes to confirm service locations. • Emergency contact numbers for DNO and gas emergency (0800 111 999) displayed on site notice board.1 × 5 = 5
5. Falling objects (tools, fixings, cladding offcuts) striking personnel or public below
Harm: Head injuries, lacerations, fractures to ground-level workers or passers-by
4 × 4 = 16• Establish exclusion zone (minimum 6 m radius) around work area; erect Heras fencing, barriers, and warning signage. • Fit toe-boards (≥150 mm height) and brick guards to all scaffold platforms and MEWP baskets. • Use tool lanyards (EN 795) to tether all hand tools to operative or platform; no loose items on roof. • Lower materials in buckets or bags via rope/pulley system or material hoist—never throw or drop. • Provide hard hats (EN 397) to all personnel within exclusion zone, including visitors and delivery drivers. • Appoint ground-level banksman to control pedestrian/vehicle access and monitor for falling object hazards.2 × 4 = 8

3. Step-by-Step Safe Sequence of Operations & Hold-Points

1

Site survey, permit issue, and collective fall protection installation

Pre-Start & Site Setup

Competent person (SSSTS/SMSTS) conducts roof survey to identify fragile materials (asbestos cement, liner panels, roof lights), structural capacity, and access routes. Obtain Permit-to-Work from client/duty-holder. Erect scaffold tower or MEWP with guardrails (BS EN 13374 Class A) to all open edges. Install EN 795 Class A2 anchor points for personal fall arrest. Barrier-off fragile roof lights with warning signs. Confirm LOLER inspection certificates for all lifting equipment. Deliver materials to designated laydown area; segregate from pedestrian routes. Brief all operatives on emergency procedures, rescue plan, and weather monitoring protocol.

Critical Hold-Point: ⚠ STOP: Do NOT permit roof access until collective edge protection (guardrails ≥950 mm, mid-rail, toe-board ≥150 mm) is fully installed and inspected. Fragile roof lights MUST be covered or protected with load-bearing platforms. All operatives MUST wear full-body harness (EN 361) + lanyard (EN 355) attached to anchor at all times when >2 m height.
2

Safe removal of damaged cladding, gutters, and fixings

Existing Roof Strip-Out

Work from MEWP platform or scaffold tower—never stand directly on fragile roof. Use cordless impact driver to remove fixings systematically, starting from ridge and working downwards. Place fixings in tool belt pouch or bucket—do not drop. Lower damaged cladding sheets and gutter sections to ground using rope/pulley or material hoist; never throw. Inspect roof structure (purlins, trusses) for corrosion or damage; photograph and report to Principal Designer. Segregate waste into skips: metal (recyclable), non-hazardous construction waste, and any asbestos-containing materials (ACM) for licensed disposal. Maintain exclusion zone; banksman controls ground-level access.

Critical Hold-Point: ⚠ STOP: If asbestos-containing materials (ACMs) are discovered (e.g., cement roof sheets, gaskets), CEASE WORK IMMEDIATELY. Do not cut, drill, or disturb. Notify client and HSE-licensed asbestos contractor. Only resume after ACM removal and clearance certificate issued per Control of Asbestos Regulations 2012.
3

Purlin repair, gutter bracket fixing, and alignment

Structural Preparation & Gutter Installation

Inspect and repair corroded purlins or roof trusses; replace timber sections if rot detected. Install new gutter brackets at 600 mm centres, ensuring fall of 1:600 towards downpipe outlet. Use torque wrench to tighten structural bolts to manufacturer's specification (typically 40–60 Nm). Fit aluminium box gutter sections (BS EN 612), seal unions with silicone mastic, and install end caps. Check alignment with string line and spirit level. Conduct water test: pour 10 litres into gutter and verify flow to downpipe with no leaks. All work conducted from MEWP or scaffold platform with guardrails; operatives remain clipped to anchor points.

Critical Hold-Point: ⚠ HOLD POINT: Before proceeding to cladding installation, Site Supervisor MUST verify gutter alignment, bracket torque, and water-test results. Photographic evidence required for CDM Health & Safety File. Any leaks or misalignment MUST be rectified before cladding covers gutter line.
4

Fixing of new trapezoidal steel roof sheets with correct overlap and fasteners

Cladding Installation

Hoist pre-cut cladding sheets (6 m × 1 m) to roof level using MEWP platform or material hoist—two-person lift. Lay sheets from eaves to ridge, ensuring minimum 150 mm end lap and one-and-a-half corrugation side lap. Fix with self-drilling roofing screws (stainless steel A2, 5.5 × 65 mm) fitted with EPDM sealing washers, driven into purlin crown at 4 fixings per sheet width. Use cordless impact driver with torque setting to avoid over-tightening (strip threads) or under-tightening (water ingress). Install ridge capping, barge flashings, and eaves closure strips. Wear cut-resistant gloves (EN 388 Level C) when handling sharp edges. Maintain three-point contact on roof ladder; never overreach.

Critical Hold-Point: ⚠ STOP: Do NOT walk on unsupported cladding sheets or between purlins. Use roof ladder with ridge hook (BS 1129) or crawling boards to distribute load. Wind speed MUST be <10 m/s; cease work if gusts exceed 15 m/s or rain makes surfaces slippery. All operatives MUST remain clipped to anchor points via twin-leg lanyard.
5

Silicone sealing of laps, flashings, and penetrations

Weatherproofing & Sealant Application

Clean all lap joints, flashing edges, and roof penetrations (vent pipes, roof lights) with isopropanol wipe to remove dust and oils. Apply neutral-cure silicone sealant (BS EN 15651-1 Type F) in continuous bead along side laps, end laps, and flashing upstands. Tool sealant with wet finger or spatula to ensure full adhesion and smooth finish. Fit foam closure strips under eaves and ridge to prevent bird/insect ingress while allowing ventilation. Inspect all fasteners for correct sealing washer compression—no gaps or over-compression. If using solvent-based coatings or hot bitumen, ensure adequate ventilation and wear FFP3 respirator (BS EN 149:2001+A1:2009). Allow 24-hour cure time before water testing.

Critical Hold-Point: ⚠ CHEMICAL HAZARD: Silicone sealants may release acetic acid vapour (irritant). Work in well-ventilated area; wear nitrile gloves (EN 374) and safety glasses (EN 166). If hot bitumen or solvent coatings are used, wear FFP3 respirator and ensure no ignition sources within 10 m. Consult product Safety Data Sheet (SDS) before use.
6

Water test, snag rectification, and CDM documentation

Final Inspection, Testing & Handover

Conduct final water test: simulate heavy rainfall using hose for 15 minutes, inspecting all laps, gutters, and downpipes for leaks. Rectify any defects immediately. Remove all tools, waste, and temporary works (scaffold, MEWP, barriers). Conduct final site inspection with client/Principal Contractor; complete snag list. Update CDM Health & Safety File with as-built drawings, product data sheets (cladding, sealants), LOLER certificates, and photographic record. Issue O&M manual covering gutter cleaning frequency (twice-yearly), fastener inspection (annual), and safe access arrangements for future maintenance. Hand over Permit-to-Work closure certificate and sign-off RAMS. Confirm CIS Domestic Reverse Charge VAT treatment on final invoice (VATA 1994 s.55A).

Critical Hold-Point: ⚠ HANDOVER REQUIREMENT: Client MUST be provided with safe access strategy for future roof maintenance (e.g., permanent anchor points, roof hatch, ladder access) per Work at Height Regulations 2005 Reg. 4(1)(b). Failure to provide ongoing safe access arrangements is a CDM 2015 Reg. 13 breach and may result in HSE enforcement action.

Emergency Rescue, First Aid & Spill Protocol

**Emergency Contact Numbers:** • Emergency Services: **999** (Fire, Ambulance, Police) • HSE Incident Contact Centre: **0345 300 9923** • Gas Emergency (National Grid): **0800 111 999** • Electricity Network (e.g., UK Power Networks): **0800 31 63 105** **Fall-from-Height Rescue:** If an operative falls and is suspended in harness, **suspension trauma** can be fatal within 10–20 minutes. Immediate rescue is critical: 1. **Call 999** and request Fire & Rescue Service with aerial appliance or rope rescue team. 2. **Do NOT attempt untrained rescue**—secondary falls are common. 3. If trained rescue team on-site, use descent device (EN 341 Class A) to lower casualty gently; avoid sudden release. 4. Once on ground, place casualty in **recovery position** (not flat on back) to prevent orthostatic shock. 5. Monitor consciousness, breathing, and circulation; administer oxygen if available. 6. **Do NOT allow casualty to stand or walk**—risk of cardiac arrest post-suspension. **First Aid Provision (HSE INDG214):** • Minimum **one appointed First Aider** (3-day FAW or EFAW) on-site at all times. • First Aid kit (BS 8599-1) stocked with trauma dressings, eye wash, burn gel, and resuscitation face shield. • Automated External Defibrillator (AED) recommended for sites >10 operatives or remote locations. • Accident Book (BI 510) maintained; all injuries recorded and RIDDOR-reportable incidents (>7-day absence, fall >2 m, hospital admission) notified to HSE within 15 days. **Adverse Weather / Lightning:** • If lightning detected within 10 miles, evacuate roof immediately and shelter in vehicle or building (not under trees or scaffold). • If operative experiences electric shock from overhead line contact, **do NOT touch casualty** until power confirmed isolated by DNO. Use non-conductive pole to separate if safe to do so, then call 999.

4. UK Commercial, HSE & PQQ Compliance FAQs: Industrial Roofing, Cladding & Gutter Repairs Quote, BoQ & 5x5 RAMS Template UK

5. Operative Toolbox Talk & Competent Person Sign-Off Register

Operative / Supervisor Name Trade / Role & CSCS No. Signature Date & Time
1. (Site Supervisor):     
2.     
3.     
4.     

Price the Job & Automate UK Safety Compliance with SafeSequence®

Need a priced commercial quote or site-specific compliance pack instead of a static template? Explore the live SafeSequence® UK studios hosted in AWS London (eu-west-2):

Voice-to-Quote & 1-Click RAMS Dictate your job scope to compile a priced UK Trade BoQ, auto-fill your blank .docx letterhead & unlock the matching 5×5 RAMS for £0 extra. PCI Tender-to-RAMS Studio Upload 300-page Principal Contractor PCI PDFs for [Page X] cited RAMS & PAS 91 answers. Voice RAMS & CLP COSHH Dictate site tasks or scan chemical tins to generate UK 5×5 RAMS & Reg 6 COSHH PDFs. Enterprise Admin Command Hub Unlock custom logo branding, saved company rate cards, Visual Video SOPs, 6S OPLs & CAPAs.

Related UK Quote, Tender & Safety Templates