Under COSHH Regulations 2002 and CLP Regulation, Hilti HIT-RE 500 V4 and HIT-HY 200 injectable epoxy/hybrid resin anchors are classified as corrosive (GHS05 H314), skin sensitisers (GHS07 H317), and present respiratory/environmental hazards (GHS08, GHS09). Employers must implement hierarchy of controls including local exhaust ventilation, isolation of work areas, and mandatory respiratory protection to reduce dermal contact and inhalation exposure risks from uncontrolled 4×4 (16) to controlled 2×2 (4) or lower.

Statutory FrameworkCOSHH Regulations 2002, CLP Regulation (GHS05 Corrosive H314, GHS07 Sensitiser H317, GHS08, GHS09)
ClassificationCLP Regulation (EC) No 1272/2008: GHS05 Corrosion (H314 Causes severe skin burns and eye damage), GHS07 Health Hazard (H317 May cause allergic skin reaction), GHS08 Health Hazard (H334 May cause allergy or asthma symptoms or breathing difficulties if inhaled; H335 May cause respiratory irritation), GHS09 Environmental Hazard (H411 Toxic to aquatic life with long lasting effects). Contains epoxy resin components (bisphenol-A-epichlorohydrin), amines, and reactive diluents. UN classification not typically assigned for cartridge-packaged construction chemicals but components may fall under UN 3082 (environmentally hazardous) or UN 2735 (amines, liquid, corrosive).
Required Plant / KitHilti HIT-RE 500 V4 or HIT-HY 200 resin cartridge system with static mixer • Hilti dispensing tool (manual or pneumatic) compatible with 330ml or 500ml cartridges • Rotary hammer drill with appropriate diameter masonry drill bits (SDS-Plus or SDS-Max) • Blow-out pump or compressed air line with moisture trap for hole cleaning • Wire brush (diameter-matched to drilled hole) for mechanical hole preparation
Site Sign-Off StatusRequires Competent Person Verification
Instant AI Customization or Free Blank Word (.doc) Download

Need this COSHH customized with your Company Name, Site Postcode & Nearest A&E Hospital?

Dictate your site specifics on your phone in 45 seconds to auto-compile a signed PDF—or download our free blank Word (.doc) shell below.

Auto-Fill via Voice / CLP (45s)

1. Mandatory Personal Protective Equipment (BS EN Standards)

BS EN ISO 374-1:2016/A1:2018 Type B (KPT), BS EN 420:2003+A1:2009
Nitrile chemical-resistant gloves (minimum 0.4mm thickness, breakthrough time >480 minutes for epoxy resins)
Mandatory protection against corrosive epoxy/amine components (H314) and prevention of allergic skin sensitisation (H317). Latex gloves are inadequate due to permeation.
BS EN 140:1999 (half-mask), BS EN 136:1998 (full-face), BS EN 14387:2004+A1:2008 (A2 gas filter), BS EN 143:2021 (P3 particulate filter)
Full-face respirator with combined A2-P3 filters or half-mask with A2-P3 filters (if full-face not required for eye protection)
Protection against amine vapours and aerosol mists during dispensing and curing (H334, H335). A2 filter for organic vapours <0.5% vol, P3 for fine particulate/aerosol.
BS EN 166:2001 (Frame marking: 3 for liquid splash, 4 for coarse dust; Lens marking: 1 optical class)
Safety goggles or full-face shield with indirect ventilation
Essential protection against accidental resin splash causing severe eye burns (H314). Indirect ventilation prevents vapour ingress while allowing airflow.
BS EN ISO 13982-1:2004+A1:2010 (Type 5 particulate), BS EN 13034:2005+A1:2009 (Type 6 liquid splash), BS EN ISO 20345:2011 S3 (safety footwear)
Chemical-resistant coveralls (Type 5/6) and safety boots with chemical-resistant soles
Prevention of skin contact with corrosive resin (H314) and sensitising agents (H317). S3 footwear provides penetration resistance and chemical sole protection.

2. 5×5 Hazard Risk Assessment Matrix (HASAWA 1974 / MHSWR 1999)

Identified Hazard & HarmInitial Risk (L×S)Mandatory Engineering, Isolation & Procedural ControlsResidual Risk
1. Skin and eye contact with uncured epoxy/hybrid resin causing severe chemical burns (H314) and allergic sensitisation (H317)
Harm: Severe skin burns, permanent eye damage, allergic contact dermatitis, long-term sensitisation requiring permanent exclusion from epoxy work
4 × 4 = 16Eliminate manual handling where possible using automated dispensing. Isolate work area with barriers and signage. Provide local exhaust ventilation (LEV) at point of application (minimum 0.5 m/s capture velocity). Enforce double-gloving protocol (inner nitrile + outer disposable). Provide immediate access to eyewash station (BS EN 15154-2:2006) within 10 seconds travel. Implement permit-to-work for confined spaces. Pre-work skin checks and health surveillance per HSE COSHH essentials.2 × 2 = 4
2. Inhalation of amine vapours and aerosol mist during dispensing causing respiratory sensitisation (H334) and irritation (H335)
Harm: Occupational asthma, chronic obstructive pulmonary disease (COPD), acute respiratory distress, long-term lung function impairment
4 × 4 = 16Mandatory use of on-tool extraction (Hilti TE-DRS dust removal system or equivalent) achieving >95% capture efficiency. Install fixed LEV system with HEPA filtration where >10 anchors installed per shift. Enforce respiratory protection zone with RPE mandatory signage. Conduct atmospheric monitoring (amine vapour <0.1 ppm TWA). Implement work rotation to limit exposure duration. Health surveillance including baseline and annual spirometry. Restrict access to trained, medically cleared operatives only.2 × 2 = 4
3. Exothermic reaction during curing generating heat and accelerated vapour release in confined or poorly ventilated spaces
Harm: Thermal burns to skin, intensified vapour exposure exceeding WEL, fire risk if flammable materials nearby
3 × 4 = 12Prohibit use in confined spaces (as defined by Confined Spaces Regulations 1997) without forced mechanical ventilation achieving minimum 6 air changes per hour. Monitor temperature of large-volume installations (>500ml) using infrared thermometer. Maintain minimum 3-metre exclusion zone during curing phase (first 30 minutes). Remove all ignition sources and flammable materials from work area. Use only in ambient temperatures 5°C to 30°C per manufacturer's datasheet. Provide thermal imaging camera for large installations to detect hotspots.2 × 3 = 6
4. Environmental contamination from resin spillage or waste disposal affecting aquatic ecosystems (H411)
Harm: Prosecution under Environmental Protection Act 1990, watercourse pollution, harm to aquatic life, costly remediation and fines up to £50,000
3 × 3 = 9Implement spill containment protocol: provide spill kit with absorbent granules (vermiculite/sand), non-reactive scoops, and hazardous waste bags within 5 metres of work area. Prohibit washing of contaminated tools or PPE into drainage systems. Segregate all waste (empty cartridges, contaminated absorbents, used PPE) into UN-approved hazardous waste containers (UN 3082 classification). Arrange collection by licensed waste carrier (Environment Agency registration verified). Maintain waste transfer notes for 2 years. Conduct pre-work drain isolation and bunding for external/basement work near watercourses.2 × 2 = 4
5. Cartridge pressurisation failure or improper dispensing tool use causing violent resin ejection and operator exposure
Harm: High-velocity resin spray to face/eyes causing H314 burns, uncontrolled environmental release, equipment damage
3 × 4 = 12Inspect all cartridges for damage, bulging, or expiry date before use—reject any defects. Verify dispensing tool compatibility with cartridge type (HIT-RE 500 V4 vs HIT-HY 200 have different viscosities). Conduct pre-shift function test of dispensing tool trigger and pressure release. Always point nozzle away from body and face during priming. Purge first 50mm of mixed resin onto disposable surface to verify correct mixing ratio (observe colour uniformity). Lock-off and depressurise tool before cartridge changes. Provide tool-specific training and competency assessment (record in training matrix).2 × 2 = 4

3. Step-by-Step Safe Sequence of Operations & Hold-Points

1

Site setup, hazard identification, and control verification

Preparation and Risk Assessment

Conduct site-specific COSHH assessment and review Safety Data Sheets (SDS) for Hilti HIT-RE 500 V4 or HIT-HY 200. Verify cartridge batch number, expiry date, and storage conditions (5°C–25°C). Establish 3-metre exclusion zone with barrier tape and 'Hazardous Chemicals in Use' signage. Confirm LEV system operational (measure face velocity ≥0.5 m/s) or on-tool extraction connected. Check eyewash station functional and within 10 seconds access. Issue permit-to-work if confined space or overhead work. Verify all operatives hold valid COSHH training (refreshed annually) and medical clearance for respiratory sensitisers. Inspect all PPE for damage and correct EN standards.

Critical Hold-Point: STOP: Do not proceed if respiratory protection (A2-P3 filters) is unavailable, expired, or face-fit test not completed within last 3 years. Amine vapour exposure without RPE can cause irreversible occupational asthma (H334).
2

Correct PPE sequence and fit verification

PPE Donning and Pre-Work Checks

Don PPE in correct sequence: (1) chemical-resistant coveralls (Type 5/6), (2) safety boots (S3), (3) inner nitrile gloves, (4) half-mask or full-face respirator with A2-P3 filters (conduct positive/negative pressure seal check), (5) safety goggles if using half-mask, (6) outer disposable gloves. Verify glove integrity by inflating and checking for leaks. Confirm respirator straps are snug but not over-tightened. Buddy-check all PPE with second operative. Retrieve spill kit and position within arm's reach. Confirm mobile phone or radio available for emergency communication. Record PPE issue in site diary or permit.

Critical Hold-Point: STOP: Facial hair (including stubble >1mm) prevents effective respirator seal and invalidates protection. Clean-shaven policy is mandatory for tight-fitting RPE per HSE guidance.
3

Drill hole to specification and achieve cleanliness standard

Hole Preparation and Cleaning

Drill hole to specified diameter and depth per structural engineer's design (typically 10–30mm diameter, embedment depth per Hilti design software). Use rotary percussion mode only—do not use hammer-only mode. Activate on-tool dust extraction during drilling. Blow out hole using compressed air (maximum 6 bar pressure) or blow-out pump, directing debris away from face and body. Brush hole interior using wire brush (3 complete in-out cycles, rotating brush). Repeat blow-out process. Inspect hole for cleanliness—no visible dust, moisture, or oil contamination. For critical applications (e.g., structural steel connections), verify hole cleanliness using white tissue test—tissue must remain clean after insertion.

Critical Hold-Point: HOLD POINT: Contaminated holes (dust, water, oil, formwork release agents) will cause bond failure and structural collapse risk. Reject any hole showing moisture or oil staining—re-drill or use alternative fixing method.
4

Controlled resin injection and anchor insertion within working time

Resin Dispensing and Anchor Installation

Load cartridge into dispensing tool ensuring correct orientation (check arrow on cartridge). Attach static mixer nozzle and secure with quarter-turn lock. Point nozzle away from body and dispense first 50mm onto disposable surface to verify uniform colour mixing (HIT-RE 500 V4: grey; HIT-HY 200: off-white). Insert nozzle to back of hole and dispense resin while slowly withdrawing to fill 2/3 of hole depth—avoid air pockets. Immediately insert anchor rod/rebar with slow twisting motion until resin exudes from hole. Do not disturb anchor during gel time (HIT-RE 500 V4: ~8 minutes at 20°C; HIT-HY 200: ~5 minutes). Mark anchor with chalk and note installation time. Clean excess resin from substrate using absorbent cloth (dispose as hazardous waste). Depressurise dispensing tool and remove cartridge if work paused >5 minutes.

Critical Hold-Point: STOP: Working time is temperature-dependent and reduces by 50% for every 10°C rise. At 30°C, HIT-HY 200 working time is <3 minutes. Exceeding working time results in incomplete bond and structural failure—discard and re-install.
5

Protect installation during cure and monitor vapour levels

Curing and Exclusion Zone Maintenance

Maintain 3-metre exclusion zone during full cure time (HIT-RE 500 V4: 24 hours at 20°C; HIT-HY 200: 3 hours at 20°C for service temperature <50°C). Post 'Curing in Progress—No Entry' signage. Continue LEV operation for minimum 30 minutes post-installation to extract residual vapours. For multiple installations (>10 anchors), conduct atmospheric monitoring using direct-reading amine detector—cease work if levels exceed 0.1 ppm TWA. Prohibit grinding, cutting, or loading of anchors before full cure time. Record installation details: cartridge batch, ambient temperature, cure start time, and expected load time. Inspect for resin bleed-out or anchor movement—report any anomalies to site supervisor immediately.

Critical Hold-Point: HOLD POINT: Loading anchors before full cure time causes creep failure and progressive structural collapse. Verify cure time using manufacturer's temperature-adjusted tables—do not rely on 'touch-dry' assessment.
6

Safe removal of PPE and compliant hazardous waste handling

Decontamination and Waste Disposal

Before removing PPE, decontaminate outer gloves using damp cloth (water only—no solvents). Remove outer gloves and dispose into hazardous waste bag. Remove goggles/face shield and place in designated cleaning area. Carefully doff respirator by lifting bottom strap over head first, then top strap—avoid touching filter surfaces. Remove coveralls by rolling outwards (contaminated side inwards) and dispose as hazardous waste. Remove inner gloves last using glove-in-glove technique. Wash hands and forearms with soap and water for minimum 60 seconds—do not use solvents or abrasive cleaners. Segregate waste: (1) empty cartridges and mixers in UN 3082 container, (2) contaminated PPE/absorbents in separate hazardous waste bag, (3) reusable tools in decontamination area. Complete waste transfer note and store for 2 years. Conduct post-work skin inspection for redness or irritation—report to occupational health if present.

Critical Hold-Point: STOP: Never dispose of resin waste, contaminated PPE, or washwater into standard waste bins or drainage systems. Environmental offences under EPA 1990 carry unlimited fines and potential imprisonment for serious pollution incidents.

Emergency Rescue, First Aid & Spill Protocol

**SKIN CONTACT (H314 Corrosive):** Immediately remove contaminated clothing and PPE. Flush affected area with copious running water for minimum 15 minutes—do not use neutralising agents. Seek medical attention immediately, bringing SDS. Monitor for delayed allergic reaction (H317) over following 48 hours. **EYE CONTACT (H314):** Irrigate eyes with eyewash station or running water for minimum 15 minutes, holding eyelids open. Remove contact lenses if present and easy to do. Seek immediate emergency medical attention—risk of permanent corneal damage. **INHALATION (H334, H335):** Move casualty to fresh air immediately. If breathing is difficult, administer oxygen if trained and available. If respiratory distress or wheezing occurs, call 999 and inform of potential occupational asthma (H334). Do not re-expose operative—refer to occupational health. **INGESTION (unlikely):** Do NOT induce vomiting due to corrosive nature. Rinse mouth with water. Give small amounts of water to drink if conscious. Seek immediate medical attention. **SPILLAGE:** Evacuate area and establish 5-metre cordon. Wear full PPE including RPE. Absorb liquid with vermiculite/sand—do not use sawdust (exothermic reaction risk). Scoop into UN-approved hazardous waste container. Ventilate area for minimum 30 minutes. Do not wash into drains. Report spills >5 litres to Environment Agency Incident Hotline: 0800 807060. **FIRE:** Resin is not classified as flammable but will burn, releasing toxic fumes (nitrogen oxides, carbon monoxide). Use water spray, foam, or CO₂. Wear SCBA in enclosed spaces. Cool containers with water spray to prevent pressure build-up.

4. UK HSE Compliance FAQs: Hilti HIT-RE 500 V4 & HIT-HY 200 Injectable Epoxy/Hybrid Resin Anchor

Do I need the same respiratory protection for both Hilti HIT-RE 500 V4 and HIT-HY 200, or can I just use dust masks for small jobs?

No, dust masks (FFP2/FFP3) are inadequate for both products. Both HIT-RE 500 V4 (epoxy) and HIT-HY 200 (hybrid) contain amine hardeners that emit vapours classified H334 (respiratory sensitiser) and H335 (respiratory irritant). You must use a half-mask or full-face respirator with combined A2-P3 filters per BS EN 140/136 regardless of job size. The A2 filter captures organic amine vapours, while P3 captures aerosol mists. Even a single exposure without RPE can trigger lifelong occupational asthma. There is no 'safe' short-duration exposure—COSHH Regulations 2002 require elimination or control of sensitiser exposure to the lowest practicable level, which mandates RPE for all resin anchor work.

What's the actual difference in cure times between HIT-RE 500 V4 and HIT-HY 200, and can I speed it up with a heat gun to get the job finished quicker?

At 20°C, HIT-RE 500 V4 (pure epoxy) requires 24 hours to achieve full structural cure for normal service loads, while HIT-HY 200 (hybrid) cures in approximately 3 hours for service temperatures below 50°C and 24 hours for higher temperatures or seismic applications. Never use artificial heat (heat guns, torches) to accelerate curing—this causes uneven polymerisation, internal stresses, and voids that compromise bond strength and can lead to catastrophic anchor failure under load. The only compliant method to reduce cure time is to use HIT-HY 200 in appropriate temperature conditions (15°C–25°C optimum) or plan work sequences to allow proper cure time. Structural engineers design anchor capacities based on manufacturer's certified cure schedules—deviating from these invalidates design calculations and breaches CDM Regulations 2015.

If I get a bit of resin on my hands but wash it off straight away, do I still need to report it, or is that just creating paperwork for a minor incident?

Yes, you must report all skin contact incidents immediately to your supervisor and record in the accident book, even if washed off quickly. Here's why: (1) Hilti resins are classified H314 (corrosive) and can cause chemical burns that may not be immediately apparent—symptoms can develop over 24–48 hours. (2) They are also H317 (skin sensitisers)—a single exposure can trigger allergic sensitisation, meaning future contact causes severe dermatitis requiring permanent exclusion from all epoxy work. (3) Under COSHH Regulations 2002 and RIDDOR 2013, skin contact with corrosive/sensitising substances must be recorded for health surveillance and may be reportable if results in 7+ days absence or medical treatment. (4) Early reporting enables occupational health monitoring and may protect your legal rights if long-term sensitisation develops. This isn't 'just paperwork'—it's a regulatory requirement and protects your health and livelihood.

5. Operative Toolbox Talk & Competent Person Sign-Off Register

Competent Person & Operative Declaration: By signing below, the Site Supervisor confirms this assessment has been adapted and verified for actual site conditions, and operatives confirm they have attended the pre-start Toolbox Talk for Hilti HIT-RE 500 V4 & HIT-HY 200 Injectable Epoxy/Hybrid Resin Anchor and will follow the safe system of work.

Operative / Supervisor Name Trade / Role & CSCS No. Signature Date & Time
1. (Site Supervisor):     
2.     
3.     
4.     