SafeSequence › UK Safety Template Library › Branded Plant & Tool RAMS › Wacker Neuson DPU 6555 Reversible Vibratory Plate Compactor
Reference UK RAMS Example • Branded Plant & Tool RAMS

Wacker Neuson DPU 6555 Reversible Vibratory Plate Compactor (RAMS Template & 5x5 Risk Assessment)

Under CDM 2015 Regulation 13, PUWER 1998 Regulation 4, HSG150, Control of Vibration at Work Regulations 2005, Control of Noise at Work Regulations 2005, and BS EN 500, employers must ensure the Wacker Neuson DPU 6555 reversible vibratory plate compactor is operated only by competent persons following manufacturer's instructions, with mandatory vibration exposure monitoring (EAV 2.5 m/s² A(8), ELV 5.0 m/s² A(8)), hearing protection where noise exceeds 85 dB(A), pre-start mechanical isolation for maintenance, and documented daily pre-use inspections to reduce compaction-related injury risk from High (15-20) to Low (3-4) through engineered controls and permit-to-work systems.

Statutory FrameworkCDM 2015, PUWER 1998, HSG150 Health & Safety in Construction, Control of Vibration at Work Regulations 2005, Control of Noise at Work Regulations 2005, BS EN 500 Mobile Road Construction Machinery
ClassificationThe Wacker Neuson DPU 6555 is a diesel-powered reversible vibratory plate compactor. Diesel fuel is classified under GHS as Flammable Liquid Category 3 (H226), Acute Toxicity Category 4 (H332), Carcinogenicity Category 2 (H351), and Aspiration Hazard Category 1 (H304). Operators must store diesel in approved containers, refuel outdoors or in well-ventilated areas with engine off and cool, and have spill kits available. Hydraulic oil (ISO VG 46) may cause skin irritation; use nitrile gloves conforming to BS EN 374-1:2016 during servicing. Exhaust emissions contain carbon monoxide and particulates; ensure adequate ventilation in confined or semi-enclosed spaces.
Required Plant / KitWacker Neuson DPU 6555 reversible vibratory plate compactor (85 kg operating weight, 550 mm plate width) • Diesel fuel in approved 5-litre metal safety can conforming to BS EN 13094 • Anti-vibration gloves conforming to BS EN ISO 10819:2013 • Calibrated vibration dosimeter for daily exposure monitoring (A(8) measurement) • Spill kit containing absorbent granules, disposal bags, and PPE for fuel/hydraulic fluid incidents
Site Sign-Off StatusRequires Competent Person Verification
Instant AI Customization or Free Blank Word (.doc) Download

Need this RAMS customized with your Company Name, Site Postcode & Nearest A&E Hospital?

Dictate your site specifics on your phone in 45 seconds to auto-compile a signed PDF—or download our free blank Word (.doc) shell below.

Auto-Fill via Voice / CLP (45s)

1. Mandatory Personal Protective Equipment (BS EN Standards)

BS EN ISO 10819:2013
Anti-vibration gloves
Mandatory to reduce hand-arm vibration transmission from handlebar controls; DPU 6555 generates vibration levels requiring exposure time management per Control of Vibration at Work Regulations 2005
BS EN ISO 20345:2011 S3 SRC
Safety footwear with metatarsal protection and vibration-damping sole
Protects against crushing from 85 kg machine movement, slips on compacted/loose surfaces, and reduces whole-body vibration transmission through feet
BS EN 352-1:2020 (muffs) or BS EN 352-2:2020 (plugs)
Class 5 ear defenders or moulded earplugs
DPU 6555 sound power level exceeds 105 dB(A); mandatory hearing protection required under Control of Noise at Work Regulations 2005 to prevent noise-induced hearing loss
BS EN ISO 20471:2013 Class 2 or 3
High-visibility vest or jacket
Ensures operator visibility on construction sites with mobile plant and vehicle movements as required by CDM 2015 and HSG150 guidance

2. 5×5 Hazard Risk Assessment Matrix (HASAWA 1974 / MHSWR 1999)

Identified Hazard & HarmInitial Risk (L×S)Mandatory Engineering, Isolation & Procedural ControlsResidual Risk
1. Hand-arm vibration syndrome (HAVS) from prolonged handlebar contact
Harm: Permanent vascular and neurological damage to fingers, hands, and arms; loss of manual dexterity; Raynaud's phenomenon (vibration white finger)
4 × 4 = 16Implement job rotation to limit individual exposure to maximum 2 hours per day on DPU 6555. Use anti-vibration gloves conforming to BS EN ISO 10819:2013. Maintain equipment to manufacturer's specification (check engine mounts, eccentric weights, handlebar bushings weekly). Conduct daily vibration exposure monitoring using calibrated dosimeter. Maintain health surveillance records per HSE L140 guidance. Ensure handlebar height adjusted to operator to minimise grip force. Provide warm rest facilities and encourage regular breaks (10 minutes per hour).3 × 2 = 6
2. Noise-induced hearing loss from diesel engine and vibratory mechanism
Harm: Permanent threshold shift, tinnitus, irreversible sensorineural hearing damage requiring hearing aids
5 × 3 = 15Enforce mandatory hearing protection (Class 5 ear defenders BS EN 352-1:2020 or moulded plugs BS EN 352-2:2020) in designated hearing protection zones. Conduct baseline and periodic audiometric testing per Control of Noise at Work Regulations 2005. Maintain silencer and exhaust system integrity; replace damaged components immediately. Establish 5-metre exclusion zone around operating compactor. Rotate operators to limit daily noise exposure below 85 dB(A) LEP,d. Provide acoustic enclosures for refuelling/maintenance areas. Record daily noise exposure in site diary.3 × 2 = 6
3. Crushing injuries from uncontrolled machine movement or rollover on slopes
Harm: Fractures, amputations, fatal crushing of feet, legs, or torso; entrapment under 85 kg machine
3 × 5 = 15Restrict operation to maximum 25° gradient per manufacturer's specification. Conduct pre-start ground assessment for stability, underground voids, and edge proximity. Establish 2-metre exclusion zone with barriers/signage. Fit emergency stop lanyard to operator's wrist. Never operate on slopes perpendicular to gradient (always work up/down slope). Provide banksman for operations within 3 metres of excavations or drops. Ensure operator trained to Certificate of Competence (CSCS/CPCS category). Inspect base plate and guide handle daily for cracks/damage. Never leave machine unattended on slopes; always park on level ground with engine off.2 × 3 = 6
4. Fire or explosion from diesel fuel during refuelling or maintenance
Harm: Severe burns, respiratory injury from smoke inhalation, explosion causing multiple casualties and property damage
2 × 5 = 10Refuel only outdoors or in designated well-ventilated areas with engine switched off and cooled for minimum 5 minutes. Use bonded/grounded fuel containers conforming to BS EN 13094. Prohibit smoking, naked flames, and hot work within 10 metres of refuelling zone. Provide 9 kg CO₂ or dry powder fire extinguisher (BS EN 3 rated 34A 233B C) within 5 metres. Inspect fuel lines, tank cap seal, and connections daily for leaks. Store diesel in locked COSHH cabinet away from ignition sources. Provide spill kit and train operators in emergency fuel spill procedures. Ensure static bonding during bulk fuel transfer.1 × 4 = 4
5. Entanglement or contact with rotating eccentric weights during maintenance
Harm: Degloving injuries, fractures, amputations of fingers/hands; fatal head injuries from uncontrolled rotation
2 × 5 = 10Implement Lockout/Tagout (LOTO) procedure per PUWER Regulation 19 before any maintenance: (1) Switch off engine and remove ignition key, (2) Disconnect spark plug lead and secure away from plug, (3) Attach personal danger tag 'DO NOT START – Maintenance in Progress', (4) Wait 5 minutes for all moving parts to stop. Only competent/authorised persons (manufacturer-trained) may access eccentric chamber. Use barrier guards (conforming to BS EN ISO 14120:2015) during inspection. Provide torque wrench calibrated to manufacturer's specification for reassembly. Conduct two-person verification before re-energisation. Maintain maintenance log with LOTO sign-off records.1 × 3 = 3

3. Step-by-Step Safe Sequence of Operations & Hold-Points

1

Conduct pre-start checks and establish safe working zone

Pre-Operation Inspection and Site Preparation

Verify operator holds valid CSCS/CPCS competence card for compaction equipment. Complete daily pre-use inspection checklist: check engine oil level, hydraulic fluid, fuel level, air filter condition, base plate for cracks/wear, handlebar security, emergency stop function, and belt tension. Inspect work area for underground services using CAT/Genny scanner and consult utility drawings. Mark exclusion zone with barriers/cones at 2-metre radius. Confirm ground gradient does not exceed 25°. Check weather conditions; do not operate in heavy rain (slip hazard) or high winds affecting stability. Ensure spill kit, fire extinguisher, and first aid kit positioned within 10 metres. Obtain Permit to Work if required by site rules.

Critical Hold-Point: HOLD POINT: Do not proceed until underground services located and marked, operator competence verified, and exclusion zone established. Striking buried cables or pipes can cause electrocution, explosion, or flooding.
2

Start engine and verify control functionality

Start-Up and Operational Readiness

Don all mandatory PPE: anti-vibration gloves (BS EN ISO 10819:2013), safety boots (S3 SRC), hearing protection (Class 5), and high-visibility vest (Class 2/3). Attach emergency stop lanyard to wrist. Position machine on level ground. Open fuel valve, set choke (if cold start), and pull recoil starter or use electric start. Allow engine to warm for 2 minutes at idle. Test forward/reverse lever operation without load. Check vibration engagement/disengagement by lifting base plate slightly and activating exciter. Listen for abnormal noises (grinding, knocking) indicating mechanical fault. Verify throttle response and emergency stop function. If any defect identified, isolate machine with danger tag and report to supervisor immediately.

Critical Hold-Point: HOLD POINT: Never bypass or disable emergency stop mechanism. Test emergency stop function before commencing work. Faulty controls can result in uncontrolled machine movement and crushing injuries.
3

Perform systematic compaction in controlled passes

Compaction Operations

Begin compaction at lowest point of area, working uphill where gradients exist. Engage vibration only when base plate in contact with material; never vibrate on hard surfaces (concrete/tarmac) as this damages plate and increases vibration transmission. Maintain steady walking pace (approximately 10-15 metres/minute). Overlap each pass by 50-100 mm to ensure uniform compaction. Keep both hands on handlebar with relaxed grip; do not grip tightly as this increases vibration transmission. For direction changes, disengage vibration, stop forward motion, engage reverse lever, then re-engage vibration. Maintain awareness of exclusion zone; stop immediately if any person enters 2-metre radius. Take 10-minute rest break every hour to minimise vibration exposure. Monitor vibration dosimeter and cease operation if approaching EAV (2.5 m/s² A(8)).

Critical Hold-Point: CRITICAL: Never operate within 3 metres of excavation edges, manholes, or drops without banksman guidance. Machine can destabilise edge material causing collapse and burial. Never walk backwards while operating; always maintain forward visibility.
4

Safely refuel machine following hot work controls

Refuelling

Move machine to designated refuelling area (outdoors or well-ventilated space). Switch off engine and remove ignition key. Allow engine and exhaust to cool for minimum 5 minutes; touch test exhaust guard to confirm cool. Establish 10-metre no-smoking/no-ignition zone with signage. Position 9 kg fire extinguisher within 5 metres. Use bonded fuel container conforming to BS EN 13094. Wipe fuel cap area clean to prevent contamination. Slowly open fuel cap to release pressure. Use funnel to prevent spillage. Fill to 80% capacity (allow expansion space). Replace cap and tighten securely. Wipe any spillage immediately with absorbent cloth; dispose in metal waste bin. If major spill occurs (>1 litre), deploy spill kit, contain with absorbent booms, and notify site manager. Do not restart engine until all fuel vapour dissipated.

Critical Hold-Point: HOLD POINT: Never refuel with engine running or hot. Diesel vapour ignition can cause flash fire and severe burns. Always have fire extinguisher immediately accessible during refuelling operations.
5

Safely shut down and secure machine

Shutdown and Securing

Move machine to designated parking area on level, stable ground away from traffic routes and excavations. Disengage vibration mechanism. Allow engine to idle for 1 minute to cool. Switch off engine using ignition key (not emergency stop unless emergency). Close fuel valve to prevent leakage. Remove ignition key and store securely. Inspect base plate, handlebar, and engine compartment for damage, leaks, or loose components. Record any defects in plant logbook and attach 'DO NOT USE' tag if unsafe. Clean base plate of compacted material using scraper (never hands). Check for fuel or hydraulic leaks underneath machine. Ensure machine cannot roll by positioning on level ground or using chocks if on slight gradient. Complete daily inspection sheet and vibration exposure record. Report operational hours to plant manager for service scheduling.

Critical Hold-Point: CRITICAL: Never leave machine unattended with engine running. Always remove ignition key to prevent unauthorised use. Unsecured plant is a major cause of site accidents and unauthorised operation injuries.
6

Perform scheduled maintenance under LOTO protocol

Maintenance and Inspection

Maintenance must only be performed by competent, manufacturer-trained personnel. Implement full Lockout/Tagout: (1) Park on level ground and switch off engine, (2) Remove ignition key and attach personal danger tag 'MAINTENANCE IN PROGRESS – DO NOT START', (3) Disconnect spark plug lead and secure away from plug, (4) Wait 5 minutes for all components to stop and cool, (5) Dissipate stored energy by manually rotating belt (with guards removed) to confirm no residual motion. Consult manufacturer's service manual for torque specifications and service intervals. Check/replace air filter every 50 hours, engine oil every 100 hours, hydraulic oil annually. Inspect eccentric weights for wear and secure mounting bolts to specified torque. Check belt tension and condition; replace if cracked or frayed. Inspect base plate wear bars; replace when worn to 50% original thickness. Lubricate handlebar pivot points with specified grease. Before re-energisation, conduct two-person verification: first person confirms all guards replaced and tools removed; second person independently verifies before reconnecting spark plug and removing LOTO tag. Test run machine without load before returning to service.

Critical Hold-Point: HOLD POINT: Never perform maintenance without full LOTO isolation. Accidental start-up during maintenance has caused multiple fatalities in UK construction. All guards must be replaced before re-energisation; never operate with missing guards.

Emergency Rescue, First Aid & Spill Protocol

**Emergency Shutdown:** In the event of operator injury, machine malfunction, or imminent danger, immediately activate the emergency stop button/lanyard. If emergency stop fails, turn ignition key to OFF position and close fuel valve. Evacuate all personnel from 5-metre radius and establish cordon. Do not attempt to restart until fault investigated by competent person. **Fire Emergency:** If fire occurs, activate emergency stop and evacuate immediately. Only tackle small fires (<0.5 m²) using CO₂ or dry powder extinguisher if safe to do so. For fuel fires, do not use water. Call 999 and request Fire & Rescue Service. Evacuate to assembly point and account for all personnel. For clothing fires, use drop-and-roll technique or fire blanket. **Injury Response:** For crushing injuries, do not move casualty unless in immediate danger. Call 999 and request ambulance, stating "construction site crushing injury." Apply direct pressure to bleeding wounds with sterile dressings. For suspected fractures, immobilise limb and keep casualty warm. For vibration-related symptoms (numbness, tingling, blanching of fingers), cease work immediately and report to occupational health. For noise exposure incidents (sudden hearing loss, severe tinnitus), seek immediate medical attention and report under RIDDOR if likely to result in permanent threshold shift. **Fuel Spill:** For spills <5 litres, use spill kit absorbent granules to contain and absorb. Dispose of contaminated materials as hazardous waste (EWC code 15 02 02). For spills >5 litres, evacuate area, eliminate ignition sources, and call Environment Agency Incident Hotline (0800 807060). Prevent entry to drains or watercourses using absorbent booms. For skin contact with diesel, wash immediately with soap and water for 15 minutes; seek medical advice if irritation persists. **RIDDOR Reporting:** Report the following to HSE within required timescales: fatalities and specified injuries (immediately), over-7-day injuries (within 15 days), occupational diseases including HAVS or noise-induced hearing loss (upon diagnosis), dangerous occurrences including uncontrolled machine movement causing injury risk. Maintain accident book (BI 510) and preserve evidence/machine for investigation.

4. UK HSE Compliance FAQs: Wacker Neuson DPU 6555 Reversible Vibratory Plate Compactor

How long can my lads operate the Wacker Neuson DPU 6555 before they hit the daily vibration exposure limit under the 2005 Regs?

Under the Control of Vibration at Work Regulations 2005, the Exposure Action Value (EAV) is 2.5 m/s² A(8) and Exposure Limit Value (ELV) is 5.0 m/s² A(8). The DPU 6555 typically generates hand-arm vibration of approximately 3.5-4.5 m/s² depending on material and maintenance condition. At 4.0 m/s² vibration magnitude, operators reach the EAV after approximately 2 hours of trigger time and the ELV after approximately 1 hour. You must implement job rotation to limit individual exposure to maximum 2 hours per day, use anti-vibration gloves (BS EN ISO 10819:2013), maintain equipment to manufacturer's specification, and conduct daily vibration monitoring with a calibrated dosimeter. Keep exposure records for each operator and arrange health surveillance (tier 3-4) for anyone regularly exceeding EAV. Remember, it's 'trigger time' (actual handlebar contact) not total shift time that counts toward exposure.

Do we need a CPCS card specifically for the DPU 6555 or will a general plant ticket cover us for insurance and CDM compliance?

For CDM 2015 and PUWER 1998 compliance, operators must be competent, which means appropriate training, knowledge, and experience for the specific equipment. The CPCS category A73 (Ride-on Roller under 1 tonne and Pedestrian Roller) or CSCS Plant Operator card with compaction equipment endorsement is the recognised UK competence standard for vibratory plate compactors like the DPU 6555. A 'general plant ticket' is insufficient. Additionally, operators should receive manufacturer-specific familiarisation training on the DPU 6555's controls (particularly the reversible mechanism), emergency stop procedures, and maintenance requirements. Your employer's/public liability insurance may be invalidated if an incident occurs and the operator cannot demonstrate appropriate competence certification. As Principal Contractor or equipment hirer, you must verify and record operator competence before allowing operation, and this verification must be available for HSE inspection. For agency or subcontractor operatives, obtain copies of certification before they start work and maintain in your CDM site file.

What's the actual legal requirement for maintenance records on hired plant like this compactor – can HSE prosecute us if we don't have the service history?

Yes, HSE can and does prosecute for inadequate plant maintenance records. Under PUWER 1998 Regulation 5, you must ensure work equipment is maintained in efficient working order and good repair, and under Regulation 6, you must ensure equipment is inspected at suitable intervals and records kept. When you hire the Wacker Neuson DPU 6555, you must obtain and verify the service/maintenance history from the hire company, including records of statutory inspections, vibration emission testing, and any repairs. You must then maintain daily pre-use inspection records (completed by operator), weekly documented checks (by competent person), and records of any defects and remedial actions. These records must be available for HSE inspection and retained for minimum 2 years (longer if health surveillance triggered). If an incident occurs and you cannot demonstrate the equipment was properly maintained, you face prosecution under Section 2 or 3 of HSWA 1974 with unlimited fines and potential director disqualification. The hire company remains responsible for thorough examination and statutory maintenance, but you as the user are responsible for daily checks and ensuring the equipment remains safe throughout the hire period. Always obtain a LOLER/PUWER inspection certificate dated within the last 6 months before accepting hired plant onto your site.

5. Operative Toolbox Talk & Competent Person Sign-Off Register

Competent Person & Operative Declaration: By signing below, the Site Supervisor confirms this assessment has been adapted and verified for actual site conditions, and operatives confirm they have attended the pre-start Toolbox Talk for Wacker Neuson DPU 6555 Reversible Vibratory Plate Compactor and will follow the safe system of work.

Operative / Supervisor Name Trade / Role & CSCS No. Signature Date & Time
1. (Site Supervisor):     
2.     
3.     
4.     
5.     
6.     