Roof Extraction Fan Motor Replacement (RAMS Template & 5x5 Risk Assessment)

This Risk Assessment and Method Statement (RAMS) provides audit-grade safety controls for the replacement of roof-mounted extraction fan motors in accordance with the Work at Height Regulations 2005, Electricity at Work Regulations 1989 (including Lock-Off Tag-Out procedures), and LOLER 1998. The document addresses critical hazards including falls from height, electrical shock, manual handling of motors, rotating machinery, and adverse weather conditions. All work must be conducted by competent persons with appropriate training, certification, and supervision. Permit to Work and electrical isolation certificates are mandatory before commencement.

Statutory FrameworkWork at Height Regulations 2005, Electricity at Work Regulations 1989 (LOTO), LOLER 1998
ClassificationNot applicable - This activity does not involve classified hazardous substances under CLP/GHS. However, residual oils, greases, and cleaning solvents used during motor maintenance may present minor skin irritation hazards. Refer to manufacturer SDS for any lubricants or cleaning agents used. Asbestos awareness is required if working on pre-2000 installations.
Required Plant / KitMobile aluminium scaffold tower (Class 3) with guardrails and toe boards compliant with BS EN 1004 • Electrical Lock-Off Tag-Out (LOTO) kit with multi-point lockout hasp and danger tags • Calibrated voltage detector and proving unit (GS38 compliant) • Torque wrench set (10-200 Nm range) for motor mounting bolts • Lifting sling and shackles (SWL 250kg minimum) with current LOLER inspection certificate
Review Cycle12 Months / Post-Incident
Instant AI Customization or Free Blank Word (.doc) Download

Need this RAMS customized with your Company Name, Site Postcode & Nearest A&E Hospital?

Dictate your site specifics on your phone in 45 seconds to auto-compile a signed PDF—or download our free blank Word (.doc) shell below.

Auto-Fill via Voice / CLP (45s)

2. 5×5 Hazard Risk Assessment Matrix (HASAWA 1974 / MHSWR 1999)

Identified Hazard & Harm Initial Risk (L×S) Mandatory Engineering, Isolation & Procedural Controls Residual Risk
1. Falls from height during roof access and motor replacement
Harm: Fatal or life-changing injuries including head trauma, spinal fractures, multiple bone fractures
4 × 5 = 20 Erect Class 3 scaffold tower with full guardrails, mid-rails, and toe boards per BS EN 1004. Maintain 3-point contact during access. Conduct pre-use scaffold inspection and tag. Implement exclusion zone below work area. Weather monitoring - cease work if wind speed exceeds 20mph or during rain/ice. Rescue plan in place with emergency descent equipment. 2 × 5 = 10
2. Electric shock or arc flash from live conductors
Harm: Electrocution, cardiac arrest, severe burns, arc flash injuries
3 × 5 = 15 Implement full electrical isolation per Electricity at Work Regulations 1989. Isolate at distribution board, apply multi-point LOTO with personal locks. Verify dead using calibrated GS38 voltage detector with proving unit before and after testing. Display 'Electrical Work in Progress' signage. Only AP/competent persons to conduct isolation. Issue Electrical Isolation Certificate. Maintain minimum approach distances to adjacent live equipment. 1 × 5 = 5
3. Manual handling injuries during motor lifting and positioning
Harm: Musculoskeletal disorders, back strain, crush injuries to hands/feet, herniated discs
4 × 3 = 12 Conduct manual handling risk assessment. Motors exceeding 25kg must be lifted using mechanical aids - deploy LOLER-certified lifting sling and shackles (current 6-month inspection). Use team lift (minimum 2 persons) with designated lift coordinator. Clear lifting path and secure motor during transit. Position scaffold platform to minimize reach and twisting. Use trolley for horizontal movement where practicable. 2 × 3 = 6
4. Contact with rotating fan blades or unexpected motor start-up
Harm: Traumatic amputation of fingers, lacerations, entanglement, crush injuries
3 × 4 = 12 Ensure electrical isolation and LOTO applied before accessing fan. Physically restrain fan impeller using locking pin or blocking device. Verify zero energy state - check for residual rotation and capacitor discharge. Remove fan blades before motor disconnection where practicable. Implement 'try-start' procedure at local controls (with LOTO in place) to confirm isolation. Barrier off fan opening during motor removal. 1 × 4 = 4
5. Adverse weather conditions affecting roof work safety
Harm: Slips/falls due to wet surfaces, cold stress, heat exhaustion, lightning strike, wind-blown objects
4 × 4 = 16 Monitor weather forecast 24 hours prior and on day of work. Cease work if: wind speed >20mph, rain/snow, ice present, temperature <5°C or >30°C, lightning within 10 miles, or poor visibility. Inspect roof surface for water pooling, moss, or contamination before access. Provide weather protection (tent/canopy) for extended work. Ensure adequate hydration and rest breaks. Implement buddy system for lone worker monitoring. 2 × 4 = 8

3. Step-by-Step Safe Sequence of Operations & Hold-Points

1

Site setup, access equipment, and electrical isolation

Preparation & Isolation

Conduct site-specific risk assessment and toolbox talk with all operatives. Erect scaffold tower ensuring base is level, outriggers deployed, and guardrails fitted on all sides. Inspect scaffold and apply green tag. Establish exclusion zone with barriers and signage. Obtain Permit to Work. Competent person to isolate motor supply at distribution board, apply personal LOTO locks, and display danger tags. Verify dead at motor terminals using calibrated voltage detector and proving unit. Issue Electrical Isolation Certificate.

Critical Hold-Point: HOLD POINT: Do NOT proceed until Electrical Isolation Certificate is issued and verified by second competent person. Voltage detector must be proved before and after testing.
2

Secure fan impeller and disconnect motor wiring

Fan Securing & Disconnection

Access motor via scaffold platform wearing full PPE. Physically restrain fan impeller using locking pin or wedge to prevent rotation. Photograph existing motor wiring configuration for reinstallation reference. Remove motor terminal cover and verify dead again at terminals. Disconnect motor cables, label each conductor, and insulate exposed cable ends with insulation tape. Remove flexible conduit connections. Check for residual capacitor charge if present.

Critical Hold-Point: HOLD POINT: Verify zero energy state - check for capacitor discharge and residual mechanical energy. Do NOT assume isolation is maintained - retest voltage before touching conductors.
3

Unbolt and safely lower existing motor

Motor Removal

Remove fan impeller from motor shaft if not already detached - note key/grub screw positions. Attach LOLER-certified lifting sling to motor lifting eyes using shackles. Take weight on sling before removing mounting bolts. Use calibrated torque wrench to loosen motor mounting bolts in cross-pattern sequence. Guide motor clear of mounting frame using team lift technique (minimum 2 persons). Lower motor to roof level and transfer to trolley. Inspect mounting frame for damage or corrosion.

Critical Hold-Point: HOLD POINT: Inspect lifting equipment for current LOLER certification (6-month thorough examination). Maximum motor weight must not exceed sling SWL. Ensure clear lowering path with no overhead obstructions.
4

Position and secure replacement motor

Installation

Verify replacement motor specification matches original (voltage, power, speed, mounting). Lift new motor into position using lifting sling and team lift. Align motor shaft with fan hub and mounting holes. Insert mounting bolts finger-tight initially. Torque mounting bolts to manufacturer specification (typically 80-120 Nm) in cross-pattern sequence using calibrated torque wrench. Refit fan impeller ensuring correct shaft key engagement and secure grub screws. Check impeller clearance to housing (minimum 10mm).

Critical Hold-Point: HOLD POINT: Verify motor rotation direction marking matches fan requirement (CW/CCW when viewed from drive end). Incorrect rotation will cause system failure and potential damage.
5

Reconnect motor wiring and conduct pre-energisation checks

Electrical Connection

Reconnect motor cables per photographic reference and wiring diagram - match phase sequence (L1, L2, L3) and earth conductor. Torque terminal connections per manufacturer specification (typically 4-6 Nm). Refit flexible conduit and terminal cover. Conduct insulation resistance test using 500V megger - minimum 1MΩ to earth required. Verify earth continuity <0.5Ω. Complete electrical installation checklist. Remove tools and loose items from motor area. Brief all personnel on energisation procedure.

Critical Hold-Point: HOLD POINT: Insulation resistance test MANDATORY before energisation. Result must be recorded on Electrical Installation Certificate. Ensure all personnel clear of fan and motor before LOTO removal.
6

Controlled energisation, testing, and system handover

Commissioning & Handover

Confirm all personnel clear of fan zone. Authorised person to remove LOTO devices and restore electrical supply. Conduct controlled energisation - momentary 'bump' start to verify rotation direction. If correct, run motor for 5 minutes monitoring for abnormal noise, vibration, or overheating. Check motor current draw against nameplate rating (±10%). Verify fan airflow direction and performance. Reinstate all guards and covers. Complete commissioning record and handover documentation to client. Remove scaffold and reinstate work area.

Critical Hold-Point: HOLD POINT: If motor rotates in wrong direction, immediately isolate and reapply LOTO. Swap any two phase conductors (L1/L2 or L2/L3) to reverse rotation. Never attempt to reverse rotation while energised.

Emergency Rescue, First Aid & Spill Protocol

**Emergency Contacts:** - Emergency Services: 999 - Site First Aider: [Insert name and contact] - Duty Manager: [Insert contact] - Electrical Duty Holder: [Insert contact] **Emergency Procedures:** **Electric Shock:** Do NOT touch casualty if still in contact with live conductor. Isolate supply immediately. If safe, remove casualty from electrical source using non-conductive material. Call 999 immediately. Commence CPR if trained and casualty not breathing. Apply AED if available. Do not move casualty unless in immediate danger. **Fall from Height:** Call 999 immediately. Do not move casualty unless in immediate danger. Maintain airway and monitor breathing. Treat for shock. Assume spinal injury - apply manual in-line stabilisation if trained. Activate rescue plan if casualty suspended in fall arrest equipment (suspension trauma risk after 10 minutes). **Crush Injury:** Call 999 immediately. Do not remove heavy objects trapping limbs without medical guidance (risk of crush syndrome). Control bleeding with direct pressure. Treat for shock. Monitor for signs of compartment syndrome. **First Aid Provision:** Minimum HSE-approved First Aid kit (BS 8599-1) must be available on site. Appointed First Aider with valid FAW or EFAW certificate must be present during all work at height activities. Accident reporting per RIDDOR 2013 - report all falls from height, electric shocks, and injuries resulting in 7+ days absence.

4. UK HSE Compliance FAQs: Roof Extraction Fan Motor Replacement

What specific competencies and certifications are required for operatives conducting roof-mounted motor replacement under Work at Height Regulations 2005?

All operatives must hold valid IOSH/CITB Working at Height training certification (renewed every 3 years). The competent person conducting electrical isolation must be an Authorised Person (AP) under the Electricity at Work Regulations 1989 with demonstrable competence in Lock-Off Tag-Out procedures. Scaffold erectors must hold CISRS Part 1 (Scaffolder) or PASMA (mobile towers) certification as appropriate. Lifting operations supervisors must have LOLER Appointed Person training. Additionally, all personnel require site-specific induction covering emergency procedures, rescue plans, and permit-to-work systems. Medical fitness for work at height (absence of vertigo, cardiac conditions, epilepsy) must be confirmed via occupational health screening.

How should residual electrical energy and mechanical hazards be controlled when the motor has variable speed drive (VSD) or soft-start equipment?

Variable speed drives and soft-start units contain high-voltage DC bus capacitors that can retain lethal charge for 10+ minutes after isolation. The electrical isolation procedure must include: (1) Isolate at main supply AND at VSD input, (2) Apply LOTO at both isolation points, (3) Wait manufacturer-specified discharge time (typically 15 minutes minimum), (4) Verify zero voltage at VSD output terminals AND motor terminals using calibrated GS38 detector, (5) Short-circuit DC bus capacitors using insulated discharge probe if safe access permits. Never assume capacitors have discharged - always verify. Additionally, VSD systems may have auxiliary control supplies requiring separate isolation. Consult VSD manufacturer documentation and involve control systems engineer in isolation planning.

What are the legal requirements for scaffold inspection frequency and documentation under Work at Height Regulations 2005 for this activity?

Under Regulation 12 of the Work at Height Regulations 2005, scaffolds must be inspected: (1) Before first use, (2) After any event likely to affect stability (adverse weather, accidental impact, modification), (3) At intervals not exceeding 7 days if in regular use. Inspections must be conducted by a competent person (CISRS Advanced Scaffolder or equivalent) and recorded on form TG20:13 or equivalent register within 24 hours. The inspection record must include: scaffold location, configuration, any defects identified, remedial actions, inspector name/signature, and date. For mobile towers, pre-use inspection is required each time the tower is erected or moved. Inspection records must be retained for 3 months after work completion. Additionally, users must conduct visual pre-use checks each day for obvious defects (missing guardrails, loose components, base settlement). A green tag system indicating 'Safe to Use' status is recommended best practice.

5. Operative Toolbox Talk & Competent Person Sign-Off Register

Competent Person & Operative Declaration: By signing below, the Site Supervisor confirms this assessment has been adapted and verified for actual site conditions, and operatives confirm they have attended the pre-start Toolbox Talk for Roof Extraction Fan Motor Replacement and will follow the safe system of work.

Operative / Supervisor Name Trade / Role & CSCS No. Signature Date & Time
1. (Site Supervisor):     
2.     
3.     
4.     
5.     
6.     