This Risk Assessment and Method Statement (RAMS) provides comprehensive safety controls for the replacement of high-bay LED lighting fixtures in warehouse environments using Mobile Elevating Work Platforms (MEWP/scissor lifts). The document addresses key hazards including working at height, electrical isolation, manual handling, and MEWP operation. All activities must comply with the Work at Height Regulations 2005, LOLER 1998, and Electricity at Work Regulations 1989. Only competent, IPAF-trained operatives with valid electrical qualifications (e.g., City & Guilds 2391) may undertake this work. A Permit to Work system must be implemented, and all electrical circuits must be isolated, locked-off, and tested dead before commencement. Emergency rescue procedures must be in place, and ground-level exclusion zones maintained throughout operations.
| Identified Hazard & Harm | Initial Risk (L×S) | Mandatory Engineering, Isolation & Procedural Controls | Residual Risk |
|---|---|---|---|
| 1. Falls from height during MEWP operation Harm: Fatal or life-changing injuries including spinal damage, head trauma, multiple fractures from falls of 6-12 metres |
4 × 5 = 20 | Only IPAF-trained operatives (3a/3b) to operate MEWP. Pre-use checks mandatory. Guardrails maintained at all times - no leaning out or overreaching. Harness NOT required in fully enclosed scissor lift platform per HSE guidance. Ground-level exclusion zone (3m radius) with barriers and signage. Emergency lowering procedures briefed. Firm, level ground confirmed before positioning. | 2 × 5 = 10 |
| 2. Electric shock or electrocution from live circuits Harm: Fatal electric shock, cardiac arrest, severe burns, or permanent neurological damage from contact with 230V/400V circuits |
3 × 5 = 15 | Permit to Work system enforced. Electrical isolation at distribution board by competent person (BS 7671). LOTO applied with personal locks - test before touch protocol. Voltage detection with GS38-compliant proving unit on all conductors. Insulated VDE tools used throughout. Circuits proven dead and re-tested after any break. No live working permitted. Authorised Person (Electricity) to supervise isolation and restoration. | 1 × 5 = 5 |
| 3. Manual handling injuries during fixture removal/installation Harm: Musculoskeletal disorders, back strain, shoulder injuries, trapped fingers from handling fixtures weighing 8-15kg at awkward heights |
4 × 3 = 12 | Two-person lift mandatory for fixtures >10kg. Mechanical aids (tool lanyards, lifting slings) used where practicable. Fixtures lowered to platform before ground transfer - no throwing. Kinetic lifting techniques briefed. Work rotation to prevent fatigue. Platform height adjusted to maintain neutral posture. Pre-task stretching encouraged. Adequate rest breaks scheduled. | 2 × 3 = 6 |
| 4. MEWP collision or overturn Harm: Crushing injuries, entrapment, platform overturn causing multiple casualties, structural damage to racking or building fabric |
3 × 4 = 12 | Site survey completed identifying overhead/side obstructions. Exclusion zone enforced - no pedestrian/FLT access during operations. Banksman deployed for complex manoeuvres. Outriggers fully extended and load capacity verified. Ground conditions assessed (load bearing >100kN/m²). Proximity to racking maintained (>0.5m clearance). Speed restricted to walking pace. Emergency stop tested pre-use. Wind speed monitored (<12.5 m/s limit for outdoor work). | 1 × 4 = 4 |
| 5. Inadequate lighting causing trips, falls, or errors Harm: Slips, trips, falls on warehouse floor, incorrect wiring connections, failure to identify live conductors leading to secondary incidents |
3 × 3 = 9 | Temporary LED task lighting (110V) deployed at work area and platform level (minimum 500 lux). Work scheduled during daylight hours where possible. Phased replacement strategy maintains minimum 50% operational lighting in zone. Torch/headlamp (hands-free) available for close inspection. Housekeeping maintained - cables secured, trip hazards removed. High-visibility clothing worn by all personnel. Work suspended if lighting falls below safe levels. | 1 × 3 = 3 |
Conduct site-specific risk assessment and toolbox talk with all operatives. Issue Permit to Work and confirm emergency procedures. Establish exclusion zone with barriers, cones, and warning signage. Authorised Person (Electricity) to isolate relevant lighting circuits at distribution board, apply LOTO devices with personal padlocks, and affix danger tags. Verify isolation using calibrated voltage detector (GS38) and prove unit functionality before and after testing. Confirm short-circuit earthing applied where required. Communicate isolation to site management and log in permit register.
Inspect MEWP for current LOLER certificate (within 6 months) and daily pre-use checklist (hydraulics, controls, guardrails, emergency lowering, outriggers). Verify IPAF operator cards are valid and category-appropriate (3a/3b). Position MEWP on firm, level ground beneath first lighting fixture, ensuring adequate clearance from racking, overhead obstructions, and structural steelwork. Deploy outriggers fully and confirm stability. Test emergency stop and descent functions. Confirm ground-level banksman is in position with two-way radio communication.
Operator and assistant (maximum 2 persons unless platform SWL permits otherwise) board platform with tools and replacement LED fixture. Elevate slowly to working height (typically 6-12m), maintaining awareness of overhead clearances. Position platform to allow comfortable access to fixture without overreaching (maximum 0.5m reach from platform edge). Ensure all tools are tethered with lanyards to prevent dropped objects. Deploy temporary task lighting on platform. Confirm stable position before commencing fixture removal. Maintain communication with ground-level banksman throughout.
Re-verify circuit is dead using voltage detector at fixture terminals before touching conductors. Photograph existing wiring configuration for reference. Using insulated VDE tools, disconnect supply cables from fixture terminal block, ensuring conductors are identified (L, N, E). Remove fixture mounting bolts/clips using appropriate tools. Two-person lift to lower fixture to platform deck - do not throw or drop. Inspect mounting bracket for damage or corrosion. Place removed fixture in designated container on platform, ensuring it cannot roll or fall. Cap or isolate exposed conductors temporarily with connector blocks.
Inspect new LED fixture for damage and verify correct specification (voltage, IP rating, lumen output). Two-person lift to position fixture onto mounting bracket, ensuring secure mechanical fixing before releasing. Connect supply cables to fixture terminals following manufacturer's instructions and wiring diagram - verify correct polarity (Brown=L, Blue=N, Green/Yellow=E). Ensure all connections are tight and conductors fully inserted into terminals. Verify earth continuity if required by installation standards. Secure cable glands and ensure no strain on connections. Double-check all fixings are tight and fixture is mechanically secure.
Lower MEWP to ground level and clear all personnel and equipment from exclusion zone. Authorised Person (Electricity) to remove LOTO devices (only their own locks), remove short-circuit earths, and restore power at distribution board following permit closure procedure. Conduct functional test of installed fixtures - verify illumination, check for flickering or abnormal operation. Inspect for signs of overheating or loose connections. Complete installation certificate and update asset register. Remove barriers and signage. Dispose of old fixtures via WEEE-compliant waste route. Close out Permit to Work and conduct post-task debrief.
In the event of a fall from height, do NOT move the casualty unless in immediate danger. Call 999 immediately and request ambulance with spinal injury capability. Administer first aid only if trained (check responsiveness, breathing, circulation). If MEWP becomes stuck at height, use emergency lowering controls (ground or platform-mounted) as per manufacturer's instructions - do NOT attempt rescue without training. For electric shock, do NOT touch casualty until power is confirmed isolated. Switch off at source, call 999, and commence CPR if trained and casualty is not breathing. All incidents must be reported immediately to site management and logged in accident book. RIDDOR-reportable injuries (>7 days incapacity, specified injuries, dangerous occurrences) must be reported to HSE within required timeframes. First aid provision: Minimum HSE-appointed First Aider on site with stocked first aid kit (BS 8599-1). Nearest A&E location and route to be briefed in toolbox talk. Emergency contact numbers displayed at site entrance and on permit.
No - HSE guidance (INDG405) confirms that harnesses are NOT required when working from a fully enclosed scissor lift (MEWP Category 3) with intact guardrails, as the platform itself provides collective fall protection. Harnesses should only be used if specifically required by the manufacturer's instructions or if guardrails must be removed (which should be avoided). Incorrect harness use can create additional hazards including suspension trauma. The focus must be on maintaining guardrails and preventing overreaching.
Operatives must hold valid IPAF certification (Category 3a for scissor lifts, 3b if boom access required), which must be renewed every 5 years. Electrical work must be undertaken by competent persons holding appropriate qualifications such as City & Guilds 2391 (Inspection & Testing), 18th Edition BS 7671, or equivalent, with demonstrable experience in commercial installations. The Authorised Person (Electricity) responsible for isolation must be appointed in writing by the duty holder and deemed competent under the Electricity at Work Regulations 1989. LOLER requires that MEWP thorough examinations are conducted by competent persons (typically accredited engineers) every 6 months.
The Work at Height Regulations require a hierarchy: avoid work at height where possible, use collective protection (e.g., MEWP platforms with guardrails rather than ladders), then personal protection (harnesses) as last resort. For high-bay lighting, work at height cannot be avoided, so we use scissor lifts (collective protection) rather than ladders or tower scaffolds. The MEWP provides a stable, guarded platform eliminating individual fall risk. We avoid working from the top of stepladders or using makeshift access. Emergency rescue plans are in place, and all work is planned, supervised, and conducted by competent persons. This approach aligns with HSE guidance INDG401 and demonstrates compliance with Regulation 6 (hierarchy) and Regulation 4 (work planning).
Competent Person & Operative Declaration: By signing below, the Site Supervisor confirms this assessment has been adapted and verified for actual site conditions, and operatives confirm they have attended the pre-start Toolbox Talk for High-Bay Warehouse LED Lighting Replacement via Scissor Lift (MEWP) and will follow the safe system of work.
| Operative / Supervisor Name | Trade / Role & CSCS No. | Signature | Date & Time |
|---|---|---|---|
| 1. (Site Supervisor): | |||
| 2. | |||
| 3. | |||
| 4. | |||
| 5. | |||
| 6. |