This Risk Assessment and Method Statement (RAMS) provides comprehensive safety controls for the installation of solar photovoltaic arrays on commercial factory roofs and the commissioning of DC string inverters. The document addresses critical hazards including work at height, electrical risks, structural loading, and manual handling. All activities are conducted in accordance with the Work at Height Regulations 2005 (HSG33), Electricity at Work Regulations 1989, and MCS 012 installation standards. The work involves mounting PV panel rails, installing modules, DC cabling, and energising string inverters. A permit-to-work system, collective fall protection, and electrical isolation procedures (LOTO) are mandatory throughout. Only competent persons holding relevant qualifications (PASMA, IPAF, ECS Gold Card or equivalent) may undertake this work. Emergency rescue plans and first aid provisions are established before work commences.
| Identified Hazard & Harm | Initial Risk (L×S) | Mandatory Engineering, Isolation & Procedural Controls | Residual Risk |
|---|---|---|---|
| 1. Falls from height during PV panel mounting and inverter installation on factory roof (working at 8-12m above ground level) Harm: Fatal or life-changing injuries including head trauma, spinal fractures, multiple limb fractures, internal organ damage | 4 × 5 = 20 | Collective edge protection (guardrails to BS EN 13374 Class A) installed before access. Mobile scaffold towers with full guardrails and toe boards. Roof access via fixed ladder with fall arrest system. Exclusion zone 3m from roof edge enforced. Rescue plan with trained rescue team on site. Weather monitoring - no work in wind >20mph or wet conditions. Pre-use scaffold inspections (SG4:15 compliant) by competent person. | 2 × 5 = 10 |
| 2. Electric shock or arc flash from DC circuits during string wiring, testing, and inverter energisation (600-1000V DC) Harm: Electrocution causing cardiac arrest, severe burns (entry/exit wounds), arc flash burns to face and hands, permanent neurological damage | 3 × 5 = 15 | Permit-to-work and LOTO (Lock-Out Tag-Out) procedures mandatory. DC isolators locked in OFF position with personal padlocks. Voltage testing before and after work using calibrated CAT III multimeter. Insulated tools (VDE 1000V) only. Arc-rated PPE worn during energisation. Work conducted by ECS Gold Card electricians or MCS-certified installers only. Inverter manufacturer commissioning procedures followed. No live working - all connections made de-energised. Array covered during installation to prevent voltage generation. | 1 × 5 = 5 |
| 3. Structural failure or roof penetration due to inadequate load assessment or fixing failure (PV array weight 15-20 kg/m²) Harm: Catastrophic roof collapse causing multiple fatalities, serious crush injuries, falls through fragile roof materials | 3 × 5 = 15 | Structural engineer's load assessment and certification obtained pre-work. Roof survey identifying fragile materials (asbestos cement, liner panels). Load distribution calculated per BS EN 1991-1-1. Roof-rated walkways and crawl boards used. Fixings designed by structural engineer - M10 stainless steel with specified torque settings (verified with calibrated torque wrench). Penetrations sealed with approved weatherproofing systems. No storage of materials on roof - crane lift or hoist used. Fragile roof warning signs and barriers installed. | 1 × 5 = 5 |
| 4. Manual handling injuries during lifting and positioning of PV panels (20-25kg each) and inverter units (30-50kg) Harm: Acute back injuries (prolapsed discs, muscle tears), shoulder and knee injuries, chronic musculoskeletal disorders | 4 × 3 = 12 | Team lifts (minimum 2 persons per panel) mandatory. Mechanical aids used where practicable - material hoist or crane for bulk delivery to roof level. Panels stored at waist height on purpose-built racks. Lifting technique training (Manual Handling Operations Regulations 1992) provided. Task rotation to prevent repetitive strain. Inverters lifted using certified lifting slings and spreader bars. Pre-shift stretching and warm-up exercises. Maximum individual lift weight 15kg enforced. | 2 × 3 = 6 |
| 5. Adverse weather conditions (high winds, rain, ice) affecting stability of materials, slip hazards, and reduced visibility on exposed roof Harm: Falls from height due to slips, wind-blown materials causing impact injuries, hypothermia, reduced reaction times leading to accidents | 4 × 4 = 16 | Weather monitoring system with defined stop-work thresholds: wind >20mph (Beaufort Scale 5), rain causing wet surfaces, ice/frost, visibility <50m, lightning within 10 miles. Anemometer installed on roof with audible alarm. Anti-slip roof coatings or temporary grip mats applied. All materials secured immediately after placement - no loose items on roof. Work suspended during adverse conditions - safe egress plan implemented. Appropriate clothing for cold/wet conditions provided. Toolbox talks on weather-related risks conducted daily. | 2 × 4 = 8 |
Establish exclusion zone beneath work area with barriers and signage. Conduct site induction for all personnel covering emergency procedures and site-specific hazards. Erect mobile scaffold towers or install collective edge protection (guardrails, toe boards, debris netting) to BS EN 13374 Class A around entire work area perimeter. Verify scaffold inspection certificates (SG4:15) are current and displayed. Install roof access ladder with fall arrest system. Position material hoist or arrange crane lift schedule. Confirm structural engineer's load certificate is available and understood. Verify emergency rescue equipment (rescue harness, descent device) is on site with trained rescue team identified. Conduct weather check and confirm conditions within safe working parameters.
Mark out mounting rail positions per approved design drawings ensuring correct spacing and alignment. Use roof-rated walkways to access fixing positions - never walk directly on fragile roof materials. Drill pilot holes for M10 stainless steel fixings using cordless drill with depth stop. Install fixings with calibrated torque wrench to engineer's specified torque (typically 25-35 Nm) - record torque values on inspection sheet. Apply weatherproofing seals and flashing to all roof penetrations immediately. Secure mounting rails to fixings and verify level using spirit level (max 2° deviation). Conduct pull-test on sample fixings (10% minimum) to verify holding strength. Install earthing/bonding connections to rails per BS 7671 Section 712 requirements.
Cover PV panels with opaque material during installation to prevent voltage generation. Use material hoist or team lift (minimum 2 persons) to position panels on mounting rails. Align panel frames with rail clamps ensuring correct orientation (check polarity markings). Secure panels using manufacturer-specified clamps torqued to specification (typically 10-15 Nm). Maintain minimum 10mm gap between adjacent panels for thermal expansion. Verify all panels are securely fastened before removing covering material. Install cable management clips to rails. Check no damage to panel glass, frames, or junction boxes occurred during installation. Record panel serial numbers and positions on as-built drawing.
Ensure all panels remain covered. Wear arc-rated gloves (BS EN 60903 Class 00) for all DC work. Route DC cables through cable management system avoiding sharp edges and ensuring UV-rated cable used for exposed runs. Make string connections at panel junction boxes using insulated tools (VDE 1000V rated) and manufacturer-approved MC4 connectors - verify polarity before connection. Install DC isolators in accessible location with clear labelling. Route DC cables to inverter location maintaining segregation from AC circuits (minimum 300mm separation). Terminate DC cables at inverter DC input terminals per manufacturer instructions. Install surge protection devices (SPD) per BS 7671 requirements. Before uncovering panels, test insulation resistance (minimum 1MΩ at 500V DC) and verify polarity using multimeter. Label all DC cables with voltage warnings and string identification.
Mount string inverter(s) on wall or frame at manufacturer-specified height (typically 1.5-2m) using appropriate fixings for substrate. Ensure inverter location provides adequate ventilation and protection from weather. Verify AC supply is isolated and locked off (LOTO) at distribution board. Install AC isolator adjacent to inverter with clear labelling. Route AC cables in steel conduit or trunking to distribution board maintaining segregation from DC circuits. Terminate AC connections at inverter AC output terminals and AC isolator using insulated tools. Install AC circuit protection (MCB/RCBO) at distribution board per design specification. Verify earthing and bonding connections - test earth loop impedance and RCD operation. Install generation meter and export control equipment if required. Apply warning labels to inverter, isolators, and distribution board indicating dual supply hazard.
Conduct pre-energisation checks: verify all DC and AC isolators are OFF and locked. Remove panel coverings. Measure open-circuit voltage (Voc) of each string - verify within expected range (typically 600-900V DC depending on string length). Close DC isolators and verify inverter display shows DC input voltage. Close AC isolator and energise inverter per manufacturer commissioning procedure. Monitor inverter startup sequence and verify no fault codes displayed. Measure AC output voltage and current - verify within specification. Configure inverter settings (grid parameters, export limits) per DNO requirements and MCS standards. Conduct performance test over minimum 30-minute period recording power output. Complete electrical installation certificate (BS 7671) and MCS installation checklist. Provide client with operation and maintenance manual, emergency procedures, and as-built drawings. Conduct client handover briefing covering isolation procedures and emergency contacts.
In the event of a fall from height, do not move the casualty unless in immediate danger. Call 999 immediately and request ambulance with trauma capability. Administer first aid only if trained - maintain airway and monitor breathing. Activate emergency rescue plan if casualty is suspended in fall arrest harness - rescue must be effected within 15 minutes to prevent suspension trauma. For electric shock incidents, DO NOT TOUCH the casualty until power is confirmed isolated. Isolate DC and AC supplies using clearly marked emergency isolators. Call 999 and state electrical incident. If casualty is not breathing, commence CPR immediately if safe to do so. For arc flash burns, cool affected area with running water for minimum 20 minutes and cover with sterile dressing - do not remove clothing stuck to burns. First aid kit to BS 8599-1 must be located at site access point. Minimum two first aiders (FAW or EFAW qualified) must be on site during all work activities. Nearest A&E department location and route must be displayed at site entrance. All incidents and near-misses must be reported to site supervisor immediately and recorded in site accident book. RIDDOR-reportable incidents (fatalities, major injuries, over-7-day injuries) must be reported to HSE within required timeframes.
Under the Electricity at Work Regulations 1989 and MCS 012 standards, all personnel must be 'competent persons' with appropriate training and experience. Electricians performing DC and AC work must hold ECS Gold Card (or equivalent) demonstrating BS 7671:2018 18th Edition qualification. Installers should hold MCS-accredited installer certification or manufacturer-specific training for the PV equipment being installed. For work at height, operatives require PASMA (towers) or IPAF (MEWPs) certification as applicable, plus site-specific fall protection training. A designated 'appointed person' under Work at Height Regulations 2005 must supervise all work at height activities and hold relevant supervisory qualifications (e.g., SMSTS, IOSH Managing Safely). All personnel must complete site-specific induction covering emergency procedures, rescue plans, and electrical isolation protocols. Competency records and training certificates must be verified before site access is granted.
DC isolation for solar PV presents unique challenges as arrays generate voltage whenever exposed to light. The LOTO procedure must include: (1) Cover all PV panels with opaque material during installation to prevent voltage generation. (2) Open and lock all DC isolators in the OFF position using personal safety padlocks - each person working on the circuit applies their own lock. (3) Test for absence of voltage using a calibrated multimeter (CAT III 1000V rated) at the point of work - test the tester before and after to verify functionality. (4) Apply 'Danger - Electrical Work in Progress' tags to all isolation points with the name of the person working. (5) Treat all DC circuits as live until proven dead - never assume isolation. (6) Only the person who applied the lock may remove it upon completion of work. (7) Before re-energisation, verify all personnel are clear, remove covers from panels in controlled sequence, and test system functionality. This procedure must be documented in a permit-to-work system and supervised by a competent person. BS 7671:2018 Section 712 provides specific requirements for PV system isolation.
Regulation 4 of the Work at Height Regulations 2005 requires that work at height is properly planned, including emergency and rescue procedures. For commercial roof work, this means: (1) A written rescue plan must be prepared before work commences, specific to the site and work activity. (2) Rescue equipment (e.g., rescue harness, descent device, rescue lines) must be available on site and inspected before use. (3) A trained rescue team (minimum 2 persons) must be identified and present on site - they must be competent in the use of rescue equipment and have practiced rescue procedures. (4) If fall arrest systems are used, rescue must be effected within 15 minutes to prevent suspension trauma (orthostatic intolerance). (5) Emergency services (999) contact procedures must be established with site address and access routes clearly communicated. (6) All personnel must be briefed on the rescue plan during site induction. (7) Rescue equipment and procedures must be tested before work at height commences. HSE guidance HSG33 'Health and Safety in Roof Work' emphasizes that rescue planning is not optional - it is a legal requirement and must be proportionate to the risks and complexity of the work.
Competent Person & Operative Declaration: By signing below, the Site Supervisor confirms this assessment has been adapted and verified for actual site conditions, and operatives confirm they have attended the pre-start Toolbox Talk for Commercial Factory Roof Solar PV Array Mounting & DC String Inverter Commissioning and will follow the safe system of work.
| Operative / Supervisor Name | Trade / Role & CSCS No. | Signature | Date & Time |
|---|---|---|---|
| 1. (Site Supervisor): | |||
| 2. | |||
| 3. | |||
| 4. | |||
| 5. | |||
| 6. |