This Risk Assessment and Method Statement (RAMS) provides comprehensive safety controls for the replacement of tension springs and motors on industrial roller shutter doors. The work involves significant stored energy hazards, work at height, and mechanical handling risks. All activities must comply with PUWER 1998, Work at Height Regulations 2005, and Supply of Machinery (Safety) Regulations 2008. Only competent, trained personnel shall undertake this work following Lock-Off Tag-Out (LOTO) procedures. The document establishes a safe system of work incorporating isolation, controlled energy release, and fall protection measures to reduce risks to an acceptable level.
| Identified Hazard & Harm | Initial Risk (L×S) | Mandatory Engineering, Isolation & Procedural Controls | Residual Risk |
|---|---|---|---|
| 1. Uncontrolled release of stored energy from tension springs Harm: Catastrophic spring recoil causing severe crush injuries, amputations, or fatality. Historical incidents include facial trauma and chest injuries. |
4 × 5 = 20 | Implement manufacturer-specific spring winding procedure. Use only approved winding bars (never screwdrivers or improvised tools). Apply LOTO to electrical supply. Install temporary restraints/clamps before tension release. Two-person operation mandatory. Mark spring tension positions. Controlled, incremental release of tension (quarter-turn maximum per step). Exclusion zone of 3 metres minimum. | 2 × 4 = 8 |
| 2. Work at height - falls from mobile tower scaffold Harm: Falls from height (typically 2.5-4 metres) resulting in major injuries including fractures, spinal injuries, or fatality. |
3 × 5 = 15 | Erect Class 3 mobile tower scaffold by competent person. Inspect before use and every 7 days (record in site diary). Ensure 3:1 height-to-base ratio maintained. Fit guardrails, mid-rails, and toe boards to all working platforms. Lock all castors before work commences. Maintain three points of contact. No overreaching - reposition tower as required. Secure tools using lanyards. Exclude unauthorised persons from work area. | 2 × 4 = 8 |
| 3. Electrical shock from motor and control circuits Harm: Electric shock causing cardiac arrest, burns, or secondary fall injuries. 230V/400V three-phase supplies typical. |
3 × 5 = 15 | Isolate electrical supply at distribution board using LOTO procedure. Affix 'Danger - Men Working' tags. Verify dead using proprietary voltage tester (prove-test-prove sequence). Short circuit and earth if >400V. Only competent electricians to disconnect/reconnect motor. Insulated tools used throughout. Test emergency stop functionality before re-energisation. Issue Permit to Work for live testing if unavoidable. | 1 × 5 = 5 |
| 4. Manual handling of heavy components (motors 15-30kg, door curtains) Harm: Musculoskeletal injuries including back strain, herniated discs, shoulder injuries, and trapped fingers. |
4 × 3 = 12 | Conduct task-specific manual handling assessment. Use mechanical aids (hoist/pulley system) for motors >15kg. Two-person lift mandatory for awkward loads. Maintain clear access routes. Position materials at waist height where practicable. Use correct lifting technique (bend knees, straight back, load close to body). Take rest breaks. Rotate personnel on repetitive tasks. Provide hand-holds on components. | 2 × 2 = 4 |
| 5. Entanglement or crushing in moving door mechanism during testing Harm: Severe crush injuries to hands, arms, or body. Entanglement in chains, cables, or rotating shafts causing traumatic amputations. |
3 × 5 = 15 | Maintain exclusion zone during all testing phases. Reinstate all manufacturer guards before energisation. Conduct initial tests in 'inching' mode using hold-to-run controls only. Station observer with access to emergency stop. Never place hands/body in shear points or pinch zones. Test emergency stop function before full operational test. Ensure all personnel clear before each test cycle. Conduct final witnessed commissioning test with client representative. | 1 × 4 = 4 |
Conduct site-specific toolbox talk covering hazards, emergency procedures, and roles. Erect barriers and signage to establish 3-metre exclusion zone. Verify mobile tower scaffold inspection (within 7 days) and erect to manufacturer instructions. Identify electrical isolation point and implement LOTO procedure - affix personal locks and 'Danger - Men Working' tags. Verify dead using voltage tester (prove-test-prove). Notify building occupants of door out-of-service status. Position fire extinguisher (CO2 type) within 5 metres.
Manually lower door to fully closed position (or safe working position if damaged). Install mechanical restraints/locking pins through door guides to prevent movement. Mark existing spring tension positions using paint pen or tape (count turns from neutral). Photograph spring configuration for reference. Measure and record spring dimensions and part numbers. Disconnect motor drive chain/coupling using appropriate tools. Support door weight using temporary props if required.
Insert manufacturer-approved winding bars (matched pair) into spring winding cones. Ensure bars are fully engaged (minimum 75mm insertion). With two operatives, release locking grub screws while maintaining bar control. Release tension incrementally - maximum quarter-turn per step. Maintain firm grip and controlled movement. Never allow bars to spin freely. Continue until all tension released and springs are in neutral position. Remove winding bars only when tension fully released. Clear exclusion zone of all non-essential personnel during this phase.
Disconnect motor electrical connections (already isolated). Remove motor mounting bolts and carefully lower motor using two-person lift or mechanical hoist. Remove spring retaining hardware and carefully extract old springs. Inspect shaft, bearings, and mounting points for wear or damage - report defects. Clean and lubricate shaft and bearings per manufacturer specification. Install new springs ensuring correct orientation and seating. Fit new motor to mounting bracket, align coupling/chain drive, and torque bolts to specification (record values). Reconnect motor wiring per circuit diagram - verify phase rotation if three-phase supply.
Insert winding bars into spring cones. Apply tension incrementally (quarter-turn steps) to manufacturer-specified number of turns (typically marked or documented). Secure locking grub screws at each full turn. Use torque wrench to tighten grub screws to specification. Test door balance by releasing mechanical restraints and manually lifting door to mid-position - door should remain stationary (balanced). Adjust tension if required (±quarter turn). Reconnect motor drive chain/coupling and adjust tension per specification. Verify all fasteners torqued and locking devices fitted.
Reinstate all guards and safety devices. Remove LOTO devices and restore electrical supply (controlled re-energisation). Test emergency stop function - must halt door immediately. Conduct initial test in 'inching' mode - verify correct direction of travel. Test limit switches (fully open and fully closed positions). Conduct full operational cycle test with observer stationed at emergency stop. Test safety edge/photocell operation (if fitted). Verify door closes smoothly without jerking or binding. Complete commissioning checklist and obtain client signature. Provide operation/maintenance instructions. Remove barriers and signage. Clear site of all tools and waste materials.
In the event of spring recoil injury or fall from height, immediately activate emergency procedures. Call 999 and request ambulance, providing precise location and nature of injuries. Administer first aid only if trained - do NOT move casualties with suspected spinal injuries. For electric shock, do NOT touch casualty until confirmed dead - use non-conductive item to break contact if safe to do so. Isolate power and commence CPR if trained and casualty not breathing. For crush injuries, control bleeding using direct pressure and elevate if possible. Preserve accident scene for HSE investigation if RIDDOR-reportable (fatality, major injury, or over-7-day injury). First aid kit (HSE compliant) must be available on site. Nearest A&E department location and route must be briefed during toolbox talk. Report all incidents to site supervisor immediately and complete accident book entry. For entrapment in door mechanism, use emergency stop or electrical isolation - do NOT attempt manual release if person trapped.
Operatives must be competent persons as defined by PUWER Regulation 9, demonstrated through manufacturer-specific training on the particular door system being serviced. This should include certification in spring tensioning procedures, LOTO implementation, and emergency procedures. Additionally, IPAF or PASMA certification is required for tower scaffold use (Work at Height Regulations 2005), and electrical work must be undertaken by persons holding relevant qualifications (e.g., City & Guilds 2391 inspection/testing or equivalent). A documented competency matrix should be maintained showing training records, refresher dates, and authorisations. Operatives should have minimum 12 months supervised experience before working independently on high-energy spring systems.
All replacement motors and safety-critical components must bear CE/UKCA marking and be supplied with a Declaration of Conformity demonstrating compliance with essential health and safety requirements. The replacement motor must be suitable for the specific application (duty cycle, torque rating, environmental conditions) and compatible with existing safety systems (emergency stops, safety edges, limit switches). Manufacturers' installation instructions must be followed precisely, and any modifications to the door system must not compromise the original safety integrity. Upon completion, updated technical documentation should be provided to the client including wiring diagrams, maintenance schedules, and residual risk information. If the replacement significantly alters the door's safety characteristics, a new risk assessment and potentially a new Declaration of Conformity may be required.
Under RIDDOR 2013, the responsible person must report to HSE any work-related fatality, specified major injury (including fractures, amputations, crush injuries, or injuries from electric shock), over-7-day incapacitation, or dangerous occurrence (such as uncontrolled spring release even without injury). Reports must be made within timescales specified (immediately for fatalities, 15 days for over-7-day injuries). The accident scene must be preserved until HSE authorises disturbance. HSE investigation may follow, potentially leading to Improvement Notices (requiring specific actions within timescales), Prohibition Notices (immediate work stoppage), or prosecution under HSWA 1974 Sections 2/3 with unlimited fines and potential imprisonment for directors under gross negligence. Common enforcement focuses include inadequate LOTO procedures, use of improvised tools, lack of competent supervision, and failure to follow manufacturer instructions. Maintain comprehensive records of risk assessments, training, equipment inspections, and method statements as evidence of compliance.
Competent Person & Operative Declaration: By signing below, the Site Supervisor confirms this assessment has been adapted and verified for actual site conditions, and operatives confirm they have attended the pre-start Toolbox Talk for Industrial Roller Shutter Door Tension Spring & Motor Replacement and will follow the safe system of work.
| Operative / Supervisor Name | Trade / Role & CSCS No. | Signature | Date & Time |
|---|---|---|---|
| 1. (Site Supervisor): | |||
| 2. | |||
| 3. | |||
| 4. | |||
| 5. | |||
| 6. |