OPC Portland Cement, Concrete & Masonry Mortar (Alkali Burns & Silica Dust) (COSHH Template & 5x5 Risk Assessment)

This COSHH assessment addresses the significant health hazards associated with Ordinary Portland Cement (OPC), concrete and masonry mortar under COSHH 2002 (as amended). The primary hazards are severe alkali burns (pH 12-13) causing skin/eye damage (CLP H318 Eye Damage Category 1, H317 Skin Sensitisation) and respirable crystalline silica (RCS) exposure leading to silicosis and lung cancer. EH40/2005 sets the Workplace Exposure Limit (WEL) for RCS at 0.1 mg/m³ 8-hour TWA. This document mandates engineering controls including LEV systems achieving minimum 1 m/s capture velocity, wet cutting/mixing methods, enclosed batch systems, and strict hygiene protocols. Competent persons must conduct atmospheric monitoring, health surveillance (respiratory function and skin checks), and ensure all operatives complete COSHH awareness training. Emergency eyewash stations (BS EN 15154) must be within 10 metres of all mixing/application areas. Residual risk is reduced to ALARP through hierarchy of controls.

Statutory FrameworkCOSHH 2002, EH40/2005 (RCS 0.1 mg/m3), CLP (GHS05 Eye Damage H318, GHS07 Sensitiser H317)
ClassificationCLP/GHS Classification: GHS05 Corrosion (Causes serious eye damage H318 - Eye Damage Category 1; Skin Corrosion/Irritation H315 Category 2). GHS07 Health Hazard (May cause allergic skin reaction H317 - Skin Sensitisation Category 1). GHS08 (Specific Target Organ Toxicity - STOT RE H372 via inhalation of respirable crystalline silica causing silicosis and lung cancer). Signal Word: DANGER. Precautionary Statements: P280 Wear protective gloves/eye protection/face protection. P305+P351+P338 IF IN EYES: Rinse cautiously with water for several minutes, remove contact lenses if present and easy to do, continue rinsing. P310 Immediately call a POISON CENTRE/doctor. P261 Avoid breathing dust. P284 [In case of inadequate ventilation] wear respiratory protection. Contains: Calcium oxide (CaO), Calcium hydroxide (Ca(OH)₂), Crystalline silica (quartz) 10-30% by weight. Not classified as dangerous goods for transport but subject to COSHH workplace controls.
Required Plant / KitLocal Exhaust Ventilation (LEV) system with HEPA filtration (tested and examined every 14 months per COSHH Regulation 9) • Water suppression equipment (hose/spray system for wet cutting and dust suppression) • Enclosed forced-action mixer with integral LEV extraction point • Class H (HEPA) vacuum cleaner conforming to BS EN 60335-2-69 for dry cleanup • Emergency eyewash station and deluge shower conforming to BS EN 15154-1 and BS EN 15154-2
Review Cycle12 Months / Post-Incident
Instant AI Customization or Free Blank Word (.doc) Download

Need this COSHH customized with your Company Name, Site Postcode & Nearest A&E Hospital?

Dictate your site specifics on your phone in 45 seconds to auto-compile a signed PDF—or download our free blank Word (.doc) shell below.

Auto-Fill via Voice / CLP (45s)

2. 5×5 Hazard Risk Assessment Matrix (HASAWA 1974 / MHSWR 1999)

Identified Hazard & HarmInitial Risk (L×S)Mandatory Engineering, Isolation & Procedural ControlsResidual Risk
1. Respirable Crystalline Silica (RCS) inhalation during mixing, cutting, grinding or demolition of cured concrete
Harm: Silicosis (irreversible lung scarring), lung cancer, COPD, and renal disease from chronic exposure. Latency period 10-20 years. Fatal occupational lung disease.
4 × 5 = 20Engineering: LEV with min 1 m/s capture velocity at source, on-tool extraction for power tools (EN 60335-2-69 Class H), wet cutting/grinding methods, enclosed mixing systems. Administrative: Atmospheric monitoring every 6 months, health surveillance (respiratory function tests annually), RPE programme with fit testing, COSHH training. Limit duration of high-dust tasks. Hygiene: Prohibit dry sweeping - use HEPA vacuum or wet methods only. Separate welfare facilities for decontamination.3 × 3 = 9
2. Severe alkali burns to eyes from cement/mortar splash during mixing, pouring or trowelling
Harm: Irreversible corneal damage, permanent blindness (H318 Eye Damage Category 1). Alkaline pH 12-13 causes liquefactive necrosis penetrating deep into ocular tissue.
3 × 5 = 15Engineering: Enclosed batch mixing systems, splash guards on mixers, reduced drop heights when pouring. Emergency: Eyewash stations (BS EN 15154) within 10m, clearly signed. Immediate irrigation for minimum 15 minutes then urgent A&E attendance. Administrative: Permit-to-work for overhead concrete pours, exclusion zones, toolbox talks on emergency response. Mandatory eye protection at all times when handling wet cement products.2 × 4 = 8
3. Allergic contact dermatitis and chemical burns from prolonged or repeated skin contact with wet cement
Harm: Cement dermatitis (H317 skin sensitisation from hexavalent chromium Cr(VI)), painful skin ulceration, permanent sensitisation requiring career change. Chemical burns from alkalinity.
5 × 3 = 15Engineering: Automated dispensing systems, use of pre-mixed products where practicable. Substitution: Specify low-chromium cement (Cr(VI) <2 ppm per Annex XVII REACH). Administrative: Skin surveillance programme, pre-employment screening for atopic individuals, job rotation to limit exposure duration. Hygiene: Barrier creams (after-work replenishing only, not pre-work), immediate washing facilities, prohibition of cement-contaminated clothing. Mandatory chemical-resistant gloves (nitrile/neoprene) - never work barehanded.3 × 2 = 6
4. Inhalation of cement dust causing acute respiratory irritation and exacerbation of asthma
Harm: Upper respiratory tract irritation, occupational asthma, bronchitis, reduced lung function. Particular risk to pre-existing asthmatics or those with respiratory conditions.
4 × 3 = 12Engineering: LEV at bag-opening and mixing points, use of bulk silos with closed transfer systems, damping down of bagged cement before opening. Substitution: Wet-mix ready-to-use products where feasible. Administrative: Health surveillance including baseline and annual spirometry, exclusion of workers with severe asthma, RPE (minimum FFP3) during all dusty operations, limitation of manual bag handling. Housekeeping: Daily HEPA vacuuming of work areas, no compressed air blowing.2 × 3 = 6
5. Manual handling injuries from lifting 25kg cement bags and heavy mixing equipment
Harm: Musculoskeletal disorders (MSDs) - acute back strain, chronic lower back pain, shoulder and knee injuries. Exacerbated by repetitive lifting and awkward postures on construction sites.
5 × 2 = 10Engineering: Mechanical aids (sack trolleys, hoists, pallet trucks), height-adjustable work platforms, bulk delivery systems eliminating manual bag handling. Ergonomic design: Locate mixers at waist height, use smaller 10kg bags for mortar where practicable. Administrative: Manual handling training per HSE guidance, team lifting for loads >20kg, job rotation, pre-placement health screening for back problems. Limit individual to maximum 10 bags per hour with rest breaks.3 × 2 = 6

3. Step-by-Step Safe Sequence of Operations & Hold-Points

1

COSHH Risk Assessment Review and Atmospheric Monitoring

Pre-Task Preparation

Competent person (COSHH assessor) must review site-specific risk assessment and verify all control measures are in place. Check LEV system thorough examination certificate is in date (14-month intervals per Regulation 9). Conduct baseline atmospheric monitoring for RCS if not done within previous 6 months or if process has changed. Verify emergency eyewash stations are functional and within 10m of work area. Confirm all operatives hold valid COSHH awareness certificates and RPE fit-test certificates (in-date within 3 years). Issue Permit-to-Work if overhead pours or confined space work involved.

Critical Hold-Point: STOP WORK if LEV examination is out of date, atmospheric monitoring shows RCS >0.1 mg/m³ without adequate RPE, or emergency eyewash is non-functional. Work must not proceed until deficiencies are rectified and documented.
2

PPE Donning and Pre-Use Inspection

Pre-Task Preparation

Don PPE in correct sequence: 1) Waterproof coveralls (Type 6) and safety boots (S3). 2) Inspect chemical-resistant gloves for splits, degradation or contamination - discard if defective. 3) Conduct positive/negative pressure fit check on FFP3 respirator or PAPR per manufacturer instructions. 4) Don safety goggles or face shield ensuring seal around face. Supervisor to verify PPE compliance before work commences. Ensure spare gloves and respirators available on site. Wash hands before donning RPE to prevent face seal contamination.

Critical Hold-Point: MANDATORY HOLD POINT: RPE must not be worn over facial hair that interferes with seal. Failed fit check = immediate replacement of respirator. Never proceed without full PPE ensemble - alkali burns occur within seconds of skin/eye contact.
3

Controlled Cement/Mortar Mixing with Dust Suppression

Mixing and Preparation

Activate LEV system and verify airflow indicator shows adequate extraction (minimum 1 m/s at capture hood). Use enclosed forced-action mixer with integral extraction. When opening cement bags, cut below bag top to minimise dust release, or use pre-dampened method. Add cement to water (never water to cement) to reduce dust generation. Maintain wet mixing - consistency should prevent dust liberation. For mortar, use factory-batched dry-mix silos with closed transfer where available. Limit number of operatives in immediate mixing zone (2m radius). Ensure mixer is positioned to prevent splashback towards workers.

Critical Hold-Point: STOP: If visible dust cloud generated during mixing, cease operation immediately and increase water suppression or improve LEV capture. Do not add dry cement to mixer while rotating at high speed. Explosion risk if cement dust accumulates near ignition sources.
4

Concrete Pouring, Screeding and Masonry Work

Application and Handling

Maintain exclusion zone (3m) around pour area - only essential personnel with full PPE permitted. Use chutes, pumps or skips to minimise drop height and splash risk. For masonry work, keep mortar boards at waist height to reduce bending. Avoid skin contact - use trowels and tools, never hands. If skin contact occurs, immediately wash with clean water (not wet wipes alone). Take regular breaks away from exposure (10 minutes per hour minimum) in designated clean welfare area. Rotate tasks to limit individual exposure duration. Keep work area damp to suppress dust from spillages.

Critical Hold-Point: EMERGENCY PROTOCOL: Any cement/mortar splash to eyes requires IMMEDIATE continuous irrigation at eyewash station for minimum 15 minutes while calling 999. Do not delay irrigation to remove contact lenses. Arrange immediate A&E attendance - alkali burns worsen over hours even after initial irrigation.
5

Wet Cutting/Grinding of Cured Concrete with On-Tool Extraction

Cutting, Grinding and Finishing

Use only tools fitted with on-tool water suppression (wet cutting) or on-tool LEV extraction (Class H HEPA). Never dry cut or grind concrete/masonry. Verify water supply is adequate before commencing cut. For angle grinders, use shrouded disc with extraction attachment connected to Class H vacuum (BS EN 60335-2-69). Operator and any person within 5m must wear RPE (minimum FFP3, preferably PAPR for extended tasks >1 hour). Conduct task in well-ventilated area or outdoors where practicable. Monitor for visible dust - if present, stop and improve controls. Limit continuous cutting to 30-minute periods with breaks.

Critical Hold-Point: ABSOLUTE PROHIBITION: Dry cutting or grinding of concrete is forbidden due to extreme RCS exposure (can exceed WEL by 10-50 times). Disciplinary action for non-compliance. Ensure water suppression is active throughout entire cut - do not continue if water supply fails.
6

Hygiene Procedures, Waste Handling and PPE Removal

Decontamination and Waste Disposal

Before leaving work area: 1) Wet-clean tools and equipment using hose/damp cloth - never dry brush. 2) HEPA vacuum all dust from clothing while still wearing RPE. 3) Remove PPE in reverse order: goggles/face shield, gloves (turn inside-out), coveralls (roll inwards), finally remove RPE in clean area. 4) Wash hands and face thoroughly with pH-neutral soap and warm water. 5) Shower if facilities available. Dispose of contaminated PPE and waste cement in designated sealed skips - never in general waste. Launder work clothing separately from personal clothes. Do not take cement-contaminated clothing home. Clean welfare facilities daily.

Critical Hold-Point: CONTAMINATION CONTROL: Never eat, drink, smoke or use mobile phone with contaminated hands - cement ingestion causes internal chemical burns. Do not use barrier creams as substitute for gloves. Report any skin irritation, rashes or respiratory symptoms to supervisor immediately for health surveillance review.

Emergency Rescue, First Aid & Spill Protocol

EMERGENCY CONTACTS: Dial 999 for serious injuries. Report to HSE under RIDDOR if: injury results in >7 days absence, occupational disease diagnosed (silicosis, dermatitis, asthma), or dangerous occurrence. Site First Aider: [Insert name/contact]. Occupational Health: [Insert provider]. FIRST AID PROCEDURES: **Eye Contact (MOST CRITICAL):** Immediately irrigate eyes at emergency eyewash station for minimum 15 minutes with eyelids held open. Remove contact lenses if easy to do so, continue rinsing. Call 999 and arrange immediate A&E attendance - alkali burns cause progressive damage. Do NOT use neutralising agents. **Skin Contact:** Remove contaminated clothing immediately. Wash affected area with copious amounts of clean water and pH-neutral soap for at least 10 minutes. Do not use acidic neutralisers. Seek medical attention if irritation, burns or ulceration develops. **Inhalation:** Move casualty to fresh air immediately. If breathing difficulties persist, call 999. Administer oxygen if trained and available. Monitor for delayed pulmonary oedema (up to 24 hours post-exposure). **Ingestion (rare):** Do NOT induce vomiting due to corrosive nature. Rinse mouth with water. Give small sips of water if conscious. Call 999 immediately - risk of oesophageal and gastric burns. SPILLAGE: Contain with absorbent material, avoid dust generation. Use wet methods or HEPA vacuum for cleanup. Dispose as hazardous waste (EWC code 17 01 01). Ventilate area. FIRE: Cement is non-flammable but dust clouds may explode if ignition source present. Use water spray to settle dust. Wear SCBA if involved in fire.

4. UK HSE Compliance FAQs: OPC Portland Cement, Concrete & Masonry Mortar (Alkali Burns & Silica Dust)

What is the current UK Workplace Exposure Limit (WEL) for respirable crystalline silica (RCS) and how do I ensure compliance when working with concrete and cement products?

The WEL for RCS is 0.1 mg/m³ as an 8-hour time-weighted average (TWA), as specified in EH40/2005 Workplace Exposure Limits (Fourth Edition, 2020 with amendments). This is a legally binding limit under COSHH Regulation 2(1). To ensure compliance: 1) Conduct initial atmospheric monitoring by a competent occupational hygienist using personal sampling pumps and gravimetric analysis per MDHS101/2. 2) Implement engineering controls (LEV, wet methods, on-tool extraction) as primary measures - RPE is secondary control only. 3) Repeat monitoring every 6 months or when process changes. 4) If exposure exceeds 0.05 mg/m³ (50% of WEL), implement enhanced controls and health surveillance. 5) Maintain records for 40 years per COSHH Regulation 10. 6) Provide health surveillance (respiratory questionnaires, spirometry) per COSHH Regulation 11 for all workers regularly exposed. Note: RCS is also classified as IARC Group 1 carcinogen - apply hierarchy of controls rigorously and reduce exposure to as low as reasonably practicable (ALARP), not just below WEL.

Our workers are developing skin rashes and dermatitis from handling cement and mortar. What are our legal obligations under COSHH and how can we prevent occupational skin disease?

Cement dermatitis is a prescribed occupational disease (PD C23 - Chrome ulceration/dermatitis) reportable under RIDDOR. Your legal obligations: 1) Under COSHH Regulation 6, prevent exposure by substitution (use low-chromium cement with Cr(VI) <2 ppm per REACH Annex XVII restriction) or engineering controls (automated dispensing, pre-mixed products). 2) Provide suitable chemical-resistant gloves (nitrile/neoprene per BS EN ISO 374-1 Type B) - never allow barehanded work with wet cement. 3) Implement skin surveillance programme per COSHH Regulation 11 - baseline skin checks and regular monitoring by occupational health professional. 4) Provide immediate washing facilities with pH-neutral soap (not harsh detergents). 5) Train workers on early symptom recognition (itching, redness, cracking). 6) Investigate all cases and review risk assessment. Prevention measures: Specify low-chromium cement in procurement, enforce strict no-skin-contact policy, provide adequate glove supplies, ensure contaminated clothing is laundered professionally (not taken home), consider job rotation for high-exposure tasks. After-work emollient creams help restore skin barrier but are not substitute for gloves. Early reporting is critical - chronic sensitisation may be irreversible and end careers.

We need to cut and grind existing concrete structures. What are the specific UK HSE requirements for controlling RCS exposure during these high-risk activities, and is dry cutting ever permitted?

Dry cutting/grinding of concrete is effectively prohibited in the UK due to extreme RCS exposures (typically 1-5 mg/m³, 10-50 times the WEL). HSE enforcement position is clear: wet methods or on-tool extraction are mandatory. Specific requirements per HSE guidance CIS36 (rev 2019) and COSHH: 1) **Primary control:** Use wet cutting with continuous water suppression at cutting point, OR on-tool LEV extraction with Class H (HEPA) vacuum per BS EN 60335-2-69. Water flow rate must be adequate to prevent visible dust. 2) **Equipment:** Only use tools designed for dust control - shrouded blades, integrated water delivery, extraction attachments. Maintain equipment per manufacturer instructions. 3) **RPE:** Despite engineering controls, RPE is still required - minimum FFP3 (APF 20), but powered air-purifying respirator (PAPR TH3, APF 40) strongly recommended for tasks >1 hour due to high baseline exposure and comfort/compliance. 4) **Atmospheric monitoring:** Mandatory for these tasks - personal sampling to verify controls achieve <0.1 mg/m³. 5) **Health surveillance:** Enhanced respiratory surveillance (annual spirometry, chest X-ray if symptomatic) for regular concrete cutters. 6) **Training:** Operatives must hold specific training in RCS control and RPE use. Emergency dry cutting may only occur in life-safety situations (rescue operations) with highest-level RPE (SCBA) and subsequent medical monitoring. Document all cutting activities in COSHH records.

5. Operative Toolbox Talk & Competent Person Sign-Off Register

Competent Person & Operative Declaration: By signing below, the Site Supervisor confirms this assessment has been adapted and verified for actual site conditions, and operatives confirm they have attended the pre-start Toolbox Talk for OPC Portland Cement, Concrete & Masonry Mortar (Alkali Burns & Silica Dust) and will follow the safe system of work.

Operative / Supervisor Name Trade / Role & CSCS No. Signature Date & Time
1. (Site Supervisor):     
2.     
3.     
4.     
5.     
6.     