This Risk Assessment and Method Statement (RAMS) provides a comprehensive safe system of work for the inspection, maintenance, and replacement of hoist ropes and conductor busbars on overhead travelling gantry cranes. The document addresses the principal hazards associated with working at height, electrical isolation, mechanical entrapment, and suspended loads in accordance with LOLER 1998, PUWER 1998, Electricity at Work Regulations 1989, and BS 7121. All work must be conducted by competent persons holding relevant qualifications (e.g., CPCS A62 Appointed Person, IPAF/PASMA for access equipment). A Permit to Work system incorporating Lock-Off/Tag-Out (LOTO) procedures is mandatory. Pre-start briefings, exclusion zones, and emergency rescue arrangements must be established before commencement. This RAMS is valid for planned preventative maintenance and must be reviewed for non-routine or emergency repairs.
| Identified Hazard & Harm | Initial Risk (L×S) | Mandatory Engineering, Isolation & Procedural Controls | Residual Risk |
|---|---|---|---|
| 1. Electrocution from contact with live conductor busbars (typically 415V 3-phase supply) Harm: Fatal electric shock, severe burns, cardiac arrest, secondary injuries from falls following shock | 4 × 5 = 20 | Implement full electrical isolation using LOTO procedures per Electricity at Work Regulations 1989. Isolate at main distribution board, lock isolator in OFF position with personal safety locks (one per person), display danger tags. Verify dead using calibrated voltage detector and proving unit (GS38 compliant). Test all phases and neutral to earth. Discharge any capacitance. Issue Permit to Work. Only competent/authorized electrical persons to perform isolation. Maintain exclusion zone until proven dead. | 2 × 5 = 10 |
| 2. Falls from height during access to crane bridge, hoist mechanism, or conductor rail systems (typically 6-20m above ground) Harm: Fatal or life-changing injuries including spinal damage, head trauma, multiple fractures | 4 × 5 = 20 | Use certified MEWP (BS EN 280) or fixed access platforms with full edge protection as primary access method. Where harness work required, implement Work at Height Regulations 2005 hierarchy: anchor points certified to BS EN 795, full body harness (BS EN 361), twin-lanyard system with shock absorber (BS EN 355). Rescue plan in place with trained personnel and equipment. Pre-use inspection of all access equipment. Exclusion zone below work area with barriers and signage. Weather monitoring - cease work in winds >12m/s or adverse conditions. | 2 × 4 = 8 |
| 3. Mechanical entrapment/crushing from unexpected crane movement or hoist drum rotation during maintenance Harm: Crushing injuries to hands/limbs, traumatic amputation, entanglement in wire rope leading to fatal injuries | 3 × 5 = 15 | Full mechanical isolation per PUWER Regulation 19: isolate all crane drives (hoist, traverse, long travel), apply mechanical brakes, insert locking pins/blocks where fitted. LOTO on all motor isolators. Display 'Men Working on Crane' signs at all control stations and access points. Remove pendant controls and lock in supervisor's possession. Establish 10m exclusion zone around crane footprint with physical barriers. Appoint dedicated banksman/safety watch. Communication protocol (radio/visual) maintained throughout. Test isolation effectiveness before work commences. | 1 × 5 = 5 |
| 4. Wire rope failure during inspection/replacement causing uncontrolled load drop or whiplash effect Harm: Fatal crushing injuries from falling loads, severe lacerations from wire rope whiplash, multiple casualties in work area | 3 × 5 = 15 | Ensure hook is fully lowered and load removed before commencing rope work. Support hoist mechanism using secondary lifting equipment or blocking where rope tension release required. Inspect rope condition per BS 7121 and LOLER before disturbance - reject if >5% wire breaks visible. Use proper rope handling techniques - never stand in bight or potential recoil path. Controlled cutting using appropriate tools with rope secured both sides. New ropes must have manufacturer certificates and be correctly spooled per BS ISO 4309. Load test new installation per LOLER before return to service. Competent person (CP) supervision mandatory. | 1 × 4 = 4 |
| 5. Manual handling injuries during rope/component removal and installation (wire ropes typically 20-50kg per section, busbar sections 10-30kg) Harm: Musculoskeletal disorders, acute back injuries, herniated discs, trapped fingers/crush injuries during lifting | 4 × 3 = 12 | Conduct task-specific manual handling assessment per Manual Handling Operations Regulations 1992. Use mechanical aids (chain blocks, rope pullers, trolleys) for all lifts >25kg or awkward geometry. Team lifts (minimum 2 persons) for components >15kg with clear communication protocol. Ensure clear access routes and staging areas. Use proper lifting technique training - bend knees, straight back, secure grip. Provide anti-fatigue matting on platforms. Rotate personnel on repetitive tasks. Pre-shift stretching and warm-up exercises. Adequate rest breaks per task duration. | 2 × 2 = 4 |
Conduct toolbox talk covering scope of work, hazards, emergency procedures, and communication protocols. Confirm all personnel are competent and medically fit for work at height. Issue Permit to Work. Authorized Electrical Person (AEP) to isolate crane electrical supply at main distribution board, apply personal LOTO locks (one per operative), display danger tags. Verify dead on all conductor busbar phases using calibrated voltage detector and proving unit (GS38). Mechanical isolation: isolate all motor drives, apply brakes, insert locking pins. Display 'Men Working on Crane' signs at all control stations. Remove and secure pendant controls. Establish 10m exclusion zone with barriers and signage.
Position and stabilize MEWP on level, load-bearing ground. Conduct pre-use inspection per manufacturer requirements. Establish anchor points and attach fall arrest systems if required. Access crane bridge using MEWP or fixed access platform. Conduct visual inspection of hoist rope per BS 7121 criteria: check for wire breaks, corrosion, kinking, bird-caging, diameter reduction, rope end terminations. Inspect conductor busbars for damage, tracking, carbon buildup, loose connections. Photograph defects for records. Measure rope diameter at multiple points using calibrated gauges. Document findings on inspection checklist. Confirm scope of work matches planned activities.
For lubrication: Clean rope using approved wire rope cleaner and lint-free cloths. Apply manufacturer-approved rope lubricant using brush or spray, working into rope lay. For replacement: Ensure hook is fully lowered and unloaded. Support hoist drum and mechanism if tension release required. Secure rope both sides of cut point. Cut old rope using proper wire rope cutters. Remove rope from drum and reeving system, noting reeving pattern (photograph for reference). Install new rope per manufacturer specifications and BS ISO 4309 - correct spooling direction, fleet angle, and termination method. Secure rope ends using approved terminations (swaged sockets, spelter sockets, or wedge sockets with certificates). Tension rope per manufacturer settings. Conduct pre-commissioning checks: rope seating, termination security, reeving correctness.
Re-verify electrical isolation before touching busbars - test with voltage detector and proving unit. Inspect busbar system: check conductor bars for damage, tracking, overheating marks; inspect collector shoes/brushes for wear (replace if <30% material remaining); check spring tension on collectors; inspect insulation and support brackets. Clean busbars using approved electrical contact cleaner and lint-free cloths - remove carbon deposits and contamination. Replace worn collector shoes using correct grade (copper or carbon as specified). Torque fixings to manufacturer specification using calibrated torque wrench. Check alignment and clearances - maintain minimum 10mm clearance to earthed metalwork. Inspect cable connections to busbar system - check for tightness, signs of overheating, insulation damage. Megger test insulation resistance (minimum 1MΩ at 500V DC) and document results.
Conduct final visual inspection of all work areas - ensure no tools or materials left on crane. Verify all fixings torqued and secured. Check rope reeving and terminations. Remove all temporary supports and blocking. Clear exclusion zone of personnel except essential test crew. Remove LOTO locks in reverse order (each person removes own lock only). Restore electrical supply under supervision of AEP. Conduct functional tests with no load: inch hoist up/down, check for unusual noise or vibration, verify limit switches operate correctly, test emergency stop functions. If new rope fitted or major work completed, conduct LOLER load test per BS 7121: apply 125% of SWL for 10 minutes, inspect rope and terminations under load, lower load and re-inspect. Document all test results. Update crane logbook and LOLER examination records. Photograph completed work.
Conduct post-work inspection with operations supervisor - demonstrate crane functionality and review work completed. Hand over updated documentation: LOLER test certificates, rope certificates, torque records, insulation test results, photographic evidence. Update crane maintenance log and asset management system. Close Permit to Work - obtain signatures from all parties. Remove all barriers and signage. Conduct debrief with work team - discuss any issues, near-misses, or lessons learned. Complete RAMS sign-off sheet. File all documentation per company document control procedures (minimum 10-year retention for LOLER records). Schedule next inspection per LOLER examination scheme (typically 6-12 months). Inform crane operators of any operational limitations or running-in requirements (e.g., new rope may require reduced loads for first 50 cycles).
In the event of an emergency, immediately activate the site emergency alarm and call 999 (specify location, nature of incident, and number of casualties). For electrical shock incidents: do not touch the casualty until confirmed isolated from electrical source; use insulated equipment to break contact if safe to do so; commence CPR immediately if casualty is not breathing; treat for burns and shock. For falls from height: do not move casualty unless in immediate danger; maintain spinal alignment; treat for shock; monitor breathing and circulation; activate suspension trauma rescue protocol if casualty is suspended in harness (rescue within 15 minutes critical). For crushing injuries: do not remove trapped limbs until medical assistance arrives (risk of crush syndrome); control bleeding; treat for shock; keep casualty warm. First aid provision: minimum two First Aiders on site holding valid HSE-approved certificates; first aid kit to BS 8599-1 readily accessible; defibrillator (AED) available within 3 minutes' access; rescue equipment for work at height including casualty lowering device and trained rescue team. Emergency rescue plan must be briefed and rehearsed before work commences. Nearest A&E department location and route to be confirmed at pre-start briefing. All incidents, including near-misses, must be reported under RIDDOR 2013 where applicable and investigated per company procedures.
Under LOLER 1998 Regulation 9, overhead travelling cranes used for lifting persons or loads must undergo thorough examination by a competent person at intervals specified in an examination scheme (typically 6-12 months, or in accordance with manufacturer recommendations). The examination must be conducted by someone with sufficient practical and theoretical knowledge and experience (usually holding CFTS qualification or equivalent). Between statutory examinations, routine maintenance and inspections can be performed by competent maintenance personnel who have received specific training on the equipment, but any work affecting safety-critical components (hoist ropes, brakes, limit switches, load-bearing structures) must be documented and may trigger the need for an interim thorough examination before return to service. Regulation 10 requires that defects identified during examination or maintenance that could cause danger must be reported to the HSE and relevant parties, and the equipment must not be used until remedied. All examination and maintenance records must be retained for a minimum of 10 years (or until the next two examinations are completed, whichever is longer).
Wire rope discard criteria are specified in BS 7121 Part 1 and BS ISO 4309. A hoist rope must be immediately removed from service if any of the following conditions are present: (1) More than 5% of total wires broken in one rope lay length, or more than 10% broken in any running length of 30 times the rope diameter; (2) Reduction in rope diameter exceeding 10% of nominal diameter due to wear or corrosion; (3) Visible core protrusion or distortion of rope structure (bird-caging, kinking, crushing); (4) Heat damage or electric arc damage; (5) Severe corrosion causing pitting or loss of metallic area; (6) Rope end termination showing signs of slippage, damage, or wire breaks at the termination; (7) Any condition that in the opinion of the competent person could affect safe operation. Additionally, ropes should be replaced based on manufacturer recommendations (often expressed as a maximum number of operating cycles or years in service). The decision to discard must be made by a competent person with knowledge of rope inspection techniques, and the inspection must be documented with findings recorded in the crane logbook. When in doubt, the rope should be replaced - the cost of replacement is insignificant compared to the consequences of rope failure.
The Electricity at Work Regulations 1989 Regulation 4(3) requires that electrical equipment must be made dead before work commences, unless it is unreasonable in all circumstances for it to be dead or it is reasonable for work to be done live (which would require specific justification and additional precautions - not applicable for routine maintenance). The isolation procedure must follow HSE Guidance Note GS38 and industry best practice: (1) Identify the correct point of isolation (usually the main crane supply isolator at the distribution board); (2) Isolate all sources of supply and secure the isolation using Lock-Off/Tag-Out (LOTO) - each person working on the system must apply their own personal safety lock; (3) Verify the equipment is dead using a proprietary voltage detector that complies with GS38 (fused leads, insulated probes, appropriate voltage rating); (4) Prove the voltage detector is functioning correctly before and after testing using a proving unit or known live source; (5) Test between all phases and between each phase and earth/neutral; (6) Where stored energy could be present (capacitors), discharge and earth the conductors; (7) Post warning notices at the point of isolation. The isolation must remain in place throughout the work, and only the person who applied each lock may remove it. Re-energization must only occur after all personnel are clear, all locks removed, and insulation resistance testing confirms system integrity (minimum 1MΩ at 500V DC for low voltage systems). This work must be supervised by an Authorized Electrical Person with appropriate competence.
Competent Person & Operative Declaration: By signing below, the Site Supervisor confirms this assessment has been adapted and verified for actual site conditions, and operatives confirm they have attended the pre-start Toolbox Talk for Overhead Travelling Gantry Crane Hoist Rope & Conductor Busbar Maintenance and will follow the safe system of work.
| Operative / Supervisor Name | Trade / Role & CSCS No. | Signature | Date & Time |
|---|---|---|---|
| 1. (Site Supervisor): | |||
| 2. | |||
| 3. | |||
| 4. | |||
| 5. | |||
| 6. |