This Standard Operating Procedure (SOP) establishes mandatory safety protocols for HGV loading bay operations including dock leveller deployment, vehicle wheel chocking, and saloon-lock engagement. Designed for logistics and dispatch operations, this procedure ensures compliance with HSG136 Workplace Transport Safety, PUWER 1998 (Provision and Use of Work Equipment Regulations), and LOLER 1998 (Lifting Operations and Lifting Equipment Regulations). The protocol addresses critical hazards including vehicle roll-away, dock leveller collapse, pedestrian-vehicle interface risks, and crush injuries. All personnel must be trained and competent in loading bay operations, vehicle restraint systems, and emergency procedures. This SOP mandates a permit-to-load system with documented pre-operational checks, positive vehicle restraint, and segregated pedestrian routes. Risk assessments demonstrate reduction from high-risk initial scenarios (15-20 risk scores) to tolerable residual levels (3-6) through engineered controls, administrative procedures, and mandatory PPE.
| Identified Hazard & Harm | Initial Risk (L×S) | Mandatory Engineering, Isolation & Procedural Controls | Residual Risk |
|---|---|---|---|
| 1. Vehicle roll-away or premature departure during loading/unloading Harm: Crushing of personnel between vehicle and dock, dock leveller collapse, fall from height (4m), multiple fatalities | 4 × 5 = 20 | Engineered saloon-lock vehicle restraint system with interlock preventing dock leveller operation until engaged. Dual wheel chocks (front and rear) applied before trailer doors opened. Traffic light system with red-lock preventing vehicle movement. Permit-to-load system with driver handbrake confirmation and key isolation where practicable. Audible alarm if vehicle moves with leveller deployed. | 2 × 3 = 6 |
| 2. Dock leveller mechanical failure or collapse under load Harm: Fall of FLT and operator into pit (2.5m), crush injuries, equipment damage, fatality | 3 × 5 = 15 | LOLER-compliant 6-monthly thorough examination by competent person with certification. Daily pre-use visual inspection checklist (hydraulic leaks, lip condition, deck integrity). Safe Working Load (SWL) clearly marked and enforced (typically 10,000kg). Interlocked control preventing operation if safety barriers not closed. Maintenance LOTO procedure for all hydraulic isolation. Defect reporting system with immediate withdrawal from service. | 1 × 4 = 4 |
| 3. Pedestrian-vehicle collision in loading bay approach zone Harm: Crushing, multiple traumatic injuries, fatality from HGV manoeuvring | 4 × 5 = 20 | Segregated pedestrian walkways with physical barriers (Armco or bollards to HSG136 standards). Designated banksman with high-visibility clothing and two-way radio communication. Exclusion zone marked with hatched yellow lines - no pedestrian access during vehicle movements. Convex mirrors at blind corners. Speed limit 5mph enforced in loading yard. Audible reversing alarms on all vehicles. | 2 × 2 = 4 |
| 4. Crush injuries from dock leveller lip or moving components Harm: Amputation of fingers/hands, severe crush injuries to feet, fractures | 3 × 4 = 12 | Guarded control panel with two-handed operation or hold-to-run controls. Automatic lip extension with no manual handling requirement. Emergency stop buttons at 3-metre intervals around dock perimeter. Interlocked safety gates preventing access to pit during operation. Warning signage and flashing beacons during leveller movement. Maintenance LOTO with hydraulic pressure isolation and mechanical props. | 1 × 3 = 3 |
| 5. Trailer instability or landing leg collapse during loading Harm: Trailer tipping causing load shift, crushing of personnel, FLT rollover, multiple serious injuries | 3 × 4 = 12 | Pre-loading inspection of trailer condition including landing legs, suspension, and load distribution. Maximum FLT load and travel speed restrictions inside trailers (4mph, no sudden braking). Load distribution plan ensuring weight over axles not front-heavy. Prohibition on loading uncoupled trailers unless landing legs inspected and rated. Banksman monitoring trailer stability throughout operation. Emergency evacuation procedure if trailer movement detected. | 2 × 2 = 4 |
Conduct pre-operational inspection of dock leveller using daily checklist (hydraulic fluid levels, lip condition, deck surface, control functionality, emergency stop operation). Verify LOLER certification is current (check displayed certificate). Ensure loading bay is clear of obstructions, pedestrians evacuated from exclusion zone, and traffic light system set to RED. Prepare permit-to-load documentation with vehicle registration, load details, and authorised personnel signatures. Confirm FLT operator and banksman are briefed and in position.
Banksman guides HGV driver using agreed hand signals or two-way radio communication. Direct vehicle to approach dock at walking pace (maximum 5mph) ensuring central alignment with dock opening. Position vehicle so trailer rear is 150-300mm from dock bumpers. Instruct driver to apply parking brake and switch off engine. Verify trailer height is compatible with dock leveller range (typically ±400mm). Confirm vehicle is level and landing legs deployed if uncoupled unit.
Apply heavy-duty wheel chocks to both rear wheels of trailer (front and rear of each wheel - total 4 chocks minimum). Ensure chocks are tight against tyres with no gaps. Engage saloon-lock vehicle restraint system by activating control - verify mechanical hook engages with trailer ICC bar and green indicator light illuminates. Test restraint by gentle forward vehicle movement (driver applies slight throttle) - vehicle must not move. Document restraint engagement on permit-to-load. Only after positive confirmation, change traffic light to AMBER (preparation phase).
Ensure all personnel are clear of dock leveller pit and moving components. Close any safety gates or barriers. Activate dock leveller control using two-handed or hold-to-run operation. Leveller deck will rise and lip will automatically extend onto trailer bed. Verify lip is fully seated on trailer deck with minimum 150mm overlap and no gaps. Check deck is level and stable. Confirm hydraulic system holds pressure with no visible leaks. Change traffic light to GREEN indicating loading/unloading may commence. Open trailer doors using safe manual handling techniques.
FLT operator proceeds onto dock leveller and into trailer at controlled speed (maximum 4mph). Observe load capacity limits (dock leveller SWL and trailer floor rating). Maintain smooth acceleration/deceleration to prevent trailer movement or leveller stress. Banksman maintains visual contact and monitors vehicle restraint indicators throughout operation. Conduct loading/unloading systematically ensuring load distribution per plan. Prohibit pedestrian access to loading bay during FLT movements. Monitor for any trailer movement, unusual noises, or hydraulic issues.
Once loading/unloading complete, ensure all personnel and FLT have exited trailer and are clear of dock leveller. Close and secure trailer doors. Change traffic light to RED. Retract dock leveller using control - lip will fold and deck will lower to stored position. Disengage saloon-lock vehicle restraint and verify red indicator light shows. Remove all four wheel chocks and store safely. Complete permit-to-load documentation with finish time and any observations. Banksman guides driver for safe departure, ensuring pedestrian exclusion zone is maintained. Reset loading bay for next operation.
EMERGENCY PROCEDURES: In the event of vehicle roll-away or premature departure, activate emergency stop buttons immediately and sound general alarm. Evacuate all personnel from loading bay area using designated escape routes. Do not attempt to stop moving vehicle. If personnel are trapped between vehicle and dock, call 999 immediately requesting Fire & Rescue Service with heavy lifting equipment. For dock leveller collapse or FLT fall into pit, isolate hydraulic power using emergency isolation switch (red lockable isolator on main panel), call 999, and deploy trained first aiders. Do not enter pit until confirmed safe by competent person. For crush injuries, do not move casualty unless immediate danger exists - maintain airway and control bleeding while awaiting paramedics. FIRST AID: Designated first aiders must be available during all loading bay operations (minimum First Aid at Work certificate to HSE standards). First aid room located [SITE SPECIFIC] with spinal board and trauma kit. All incidents must be reported via RIDDOR if result in 7+ days absence or specified injuries (fractures, amputations, crushing). Accident book (BI 510) to be completed within 24 hours. EQUIPMENT FAILURE: If dock leveller fails in deployed position, use mechanical props (stored in loading bay office) to support deck before any maintenance. Implement LOTO procedure isolating hydraulic and electrical supplies. Cordon off area with barriers and warning signage. Contact authorised LOLER engineer for inspection before return to service. Vehicle restraint system failure requires immediate withdrawal from use and engineering assessment - use alternative loading bay or manual chocking with additional controls.
Under LOLER 1998 Regulation 9, dock levellers are classified as lifting equipment and require thorough examination by a 'competent person' at intervals not exceeding 6 months. The competent person must have sufficient training, experience, and knowledge (typically a qualified engineer from an accredited inspection body). Examinations must identify whether equipment can continue in safe operation and detect deterioration. A written report must be provided within 28 days, and copies retained for inspection by HSE. In addition to 6-monthly LOLER inspections, PUWER 1998 Regulation 6 requires daily pre-use checks by trained operators and maintenance per manufacturer's schedule. Failure to maintain valid LOLER certification renders the equipment illegal to use and creates director-level liability under Section 37 HSWA 1974.
While HSG136 acknowledges various restraint methods, UK HSE guidance emphasises the hierarchy of controls favouring engineered solutions with redundancy for high-consequence scenarios. Loading bay operations present multiple fatality risks (fall from height, crushing, vehicle rollover) warranting defence-in-depth. Saloon-locks can fail due to ICC bar corrosion, incorrect engagement, or driver error. Wheel chocks provide independent mechanical backup but can slip on wet surfaces or with worn tyres. Dual restraint creates redundancy so single-point failure does not result in catastrophic incident. This approach aligns with CDM 2015 principles of designing out risk and HSG136 paragraph 127 recommendation for 'positive vehicle restraint' in high-risk scenarios. Risk assessment demonstrates dual restraint reduces likelihood from 4 to 2 on 5x5 matrix - a critical reduction for potential fatality scenarios. Many insurers now mandate dual restraint as condition of liability cover for loading bay operations.
HSG136 Section 5 establishes that banksmanship is a safety-critical role requiring formal training and demonstrated competence. Banksmen must complete accredited training (e.g., RTITB, ITSSAR, or in-house programmes meeting HSE standards) covering vehicle characteristics, hand signals, communication protocols, and emergency procedures. Competence assessment must be documented with refresher training every 3-5 years. Under PUWER Regulation 8 and Management of Health & Safety at Work Regulations 1999 Regulation 13, employers must ensure only trained, competent persons direct vehicle movements. The banksman has legal authority to stop operations if unsafe conditions develop - drivers must comply per company transport policy. High-visibility clothing (BS EN ISO 20471 Class 2 minimum) is mandatory. Banksmen must maintain clear sightlines, never position themselves in vehicle path, and use agreed communication methods (radio preferred over hand signals in noisy environments). Failure to provide competent banksmanship has resulted in HSE prosecutions with fines exceeding £500,000 under sentencing guidelines for corporate manslaughter where fatalities occur.
Competent Person & Operative Declaration: By signing below, the Site Supervisor confirms this assessment has been adapted and verified for actual site conditions, and operatives confirm they have attended the pre-start Toolbox Talk for HGV Loading Bay Dock Leveller Operation, Wheel Chocking & Saloon-Lock Protocol and will follow the safe system of work.
| Operative / Supervisor Name | Trade / Role & CSCS No. | Signature | Date & Time |
|---|---|---|---|
| 1. (Site Supervisor): | |||
| 2. | |||
| 3. | |||
| 4. | |||
| 5. | |||
| 6. |