This Risk Assessment and Method Statement (RAMS) provides comprehensive safety controls for deep trench excavation operations exceeding 1.2m depth, incorporating hydraulic shoring installation and CAT/Genny buried service detection protocols. The document addresses principal hazards including trench collapse, buried service strikes, and confined space risks in accordance with CDM 2015 Regulations, HSG47 (Avoiding Danger from Underground Services), and the Health and Safety at Work etc. Act 1974. All operatives must hold relevant CSCS cards, CPCS/NPORS plant tickets, and CAT/Genny competency certification. A Temporary Works Coordinator (TWC) must approve all shoring designs to BS 5975:2008+A1:2011. Permit to Dig systems are mandatory, with service plans verified on-site before any excavation commences. Emergency rescue equipment must be immediately available, and all personnel briefed on collapse and service strike emergency procedures.
| Identified Hazard & Harm | Initial Risk (L×S) | Mandatory Engineering, Isolation & Procedural Controls | Residual Risk |
|---|---|---|---|
| 1. Trench collapse / sidewall failure Harm: Burial, crush injuries, asphyxiation, multiple fatalities. Typical trench collapse involves 1-2 tonnes per cubic metre of soil. | 4 × 5 = 20 | Competent person (SSSTS/SMSTS minimum) to assess ground conditions daily. Hydraulic shoring installed progressively as excavation deepens - no unsupported excavation >1.2m. Shoring design by TWC to BS 5975. Spoil heaps minimum 1.5m from trench edge. Excavator tracking mats used to distribute load. Trench inspected at start of each shift and after weather events. Barriers/edge protection at 2m setback. LOTO on hydraulic rams during personnel entry. | 2 × 5 = 10 |
| 2. Strike of buried electrical cables (LV/HV) Harm: Electrocution, arc flash burns, cardiac arrest, fatality. HV cables carry up to 33kV on typical distribution networks. | 3 × 5 = 15 | Permit to Dig obtained with statutory utility searches (C2, C4 plans). CAT/Genny scan by trained operative (refresher every 3 years) before any excavation. Trial holes hand-dug at 0.5m intervals in areas of uncertainty. Safe digging practices: hand tools only within 0.5m of indicated services. Insulated tools used for cable exposure. Assume all cables live unless isolated and proven dead by DNO. Emergency contact numbers displayed. Excavator fitted with RCD protection (30mA, 40ms). | 1 × 5 = 5 |
| 3. Gas main strike (LP/MP/HP) Harm: Explosion, fire, asphyxiation in confined trench, mass casualty event. Natural gas LEL 5%, UEL 15%. | 3 × 5 = 15 | Gas plans obtained from National Grid/SGN. CAT/Genny in 'Genny' mode to trace metallic gas services. Hand digging within 0.5m of indicated gas mains. Gas detector (4-gas monitor) used continuously when services suspected - calibrated monthly. Immediate evacuation if gas detected >10% LEL. Hot work prohibited within 10m of gas apparatus. Emergency gas escape number (0800 111 999) on site board. Excavation supervised at all times when near gas infrastructure. | 1 × 5 = 5 |
| 4. Oxygen deficiency / toxic gas accumulation in deep trench Harm: Asphyxiation, loss of consciousness, hydrogen sulphide poisoning (>100ppm rapidly fatal), confined space fatality. | 3 × 5 = 15 | Trenches >1.2m depth assessed for confined space entry per Confined Spaces Regulations 1997. Continuous 4-gas monitoring (O2, LEL, CO, H2S) - alarm at O2 <19.5% or >23.5%. Forced ventilation (blower/extractor) if readings abnormal. Rescue harness and tripod with winch at trench entry points >2m depth. Trained rescue team on standby - no untrained rescue attempts. Buddy system mandatory. Permit to Enter for confined space classification. Banksman maintains surface watch. | 1 × 5 = 5 |
| 5. Plant/excavator contact with personnel in trench Harm: Crushing, traumatic amputation, multiple fractures, fatality from excavator bucket or tracks. | 4 × 5 = 20 | Segregated working: no personnel in trench during excavator operation within 5m. Excavator fitted with amber flashing beacon and reversing alarm (minimum 87dB(A)). Banksman (CPCS A73) directs all plant movements near trench edge using standard signals. Exclusion zone marked with barriers. LOTO applied to excavator ignition when personnel enter trench for shoring installation. Two-way radio communication between excavator operator and trench supervisor. Daily plant pre-use checks recorded. | 1 × 5 = 5 |
Obtain and review Permit to Dig with all statutory utility searches (C2 desktop, C4 GPR where available). Conduct comprehensive CAT/Genny scan of proposed excavation area using Power, Radio, and Genny modes. Mark all detected services with colour-coded paint (red=electric, yellow=gas, blue=water, green=telecoms). Photograph marked area. Verify service plans against CAT readings - investigate all discrepancies. Establish Trial Hole locations at 0.5m intervals where services indicated. Erect barriers at 2m from proposed trench edge. Hold site briefing covering emergency procedures, service locations, and trench collapse rescue. Confirm all operatives hold valid competency cards.
Excavate trial holes by hand tools only at marked service crossing points. Dig carefully to 0.3m depth initially, then probe with insulated rod. Use vacuum excavation (suction excavator) where available for safer exposure. Expose services sufficiently to confirm type, depth, and horizontal alignment. Photograph all exposed services with depth measurement visible. Update site service plot with actual positions. Protect exposed services with timber boards or proprietary service protection. Mark exact service positions with permanent markers (spray paint + wooden stakes). Backfill trial holes only after services are fully documented and protected, or leave open if excavation is imminent.
Position excavator on stable ground with tracking mats if ground is soft. Excavate in 0.5m lifts, maintaining 1:1 batter on unsupported faces temporarily. Operator to use toothless grading bucket within 0.5m of services. Banksman to maintain continuous visual contact with operator. Stop excavation at 1.2m depth to install first lift of hydraulic shoring. Spoil to be placed minimum 1.5m from trench edge, not exceeding 1.5m height. Continuously monitor trench walls for cracking, bulging, or water ingress. Install shoring panels and hydraulic rams as per manufacturer's instructions and TWC design. Ensure waler beams are level and rams are evenly pressurized (pressure gauge readings recorded). Continue excavation and shoring in 1.0m lifts until design depth achieved.
Install hydraulic shoring in accordance with manufacturer's safe working load (SWL) and TWC design drawings. Ensure all panels are undamaged (no cracks, bent frames, or leaking rams). Connect hydraulic hoses and pressurize rams evenly - record pressure readings on inspection sheet. Install spreader bars to prevent panel bowing. Check vertical alignment with spirit level. Apply LOTO (lockout/tagout) to hydraulic pump controls before personnel entry. Competent person (SSSTS minimum + shoring training) to inspect and sign off each shoring lift before work continues below. Check daily for: ram pressure loss, panel movement, ground movement behind panels, water accumulation. Provide safe access/egress (ladder secured, extending 1m above trench edge).
Limit personnel in trench to minimum required (typically 2 maximum). Maintain continuous atmospheric monitoring with calibrated 4-gas detector - alarm settings: O2 <19.5%, LEL >10%, H2S >10ppm, CO >35ppm. Ensure forced ventilation is operating if required. Banksman to maintain surface watch at all times - no lone working in trench. Use buddy system and two-way radios. Keep trench clear of tools and materials not immediately required. Provide adequate lighting (110V or battery LED). Pump out water accumulation immediately - do not work in standing water. Excavator to remain shut down (LOTO applied) during personnel entry. Emergency rescue equipment (harness, tripod, winch) to be positioned and ready. Rotate personnel every 2 hours in deep/confined trenches.
Backfill trench in 0.3m compacted layers using approved material (Type 1 or excavated material if suitable). Compact each layer with appropriate equipment (wacker plate, trench roller). Remove shoring progressively as backfill reaches each panel level - do not remove lower panels before upper panels. Release hydraulic pressure slowly and evenly. Extract panels vertically using excavator with chains/strops - check SWL of lifting gear. Personnel to remain outside trench during shoring removal. Inspect extracted shoring components for damage before storage. Continue backfill to formation level, ensuring adequate compaction for reinstatement. Reinstate surface to specification (tarmac, concrete, or topsoil). Remove barriers and signage only when area is safe for normal access.
**EMERGENCY CONTACTS:** Display prominently on site: Emergency Services 999, National Gas Emergency 0800 111 999, Electricity Network Emergency (DNO-specific, e.g., UK Power Networks 0800 31 63 105), Water Authority Emergency, Principal Contractor Site Manager, Appointed First Aider(s). **TRENCH COLLAPSE:** Immediately call 999 and request Fire & Rescue Service Urban Search and Rescue (USAR) team. Do NOT attempt untrained rescue - secondary collapse risk is extreme. Keep all personnel away from trench edge. Appoint person to direct emergency services to exact location. If casualty is partially visible and conscious, provide reassurance but do not pull or move. Preserve scene for HSE investigation. **BURIED SERVICE STRIKE - ELECTRICAL:** Assume cable is live HV. Evacuate all personnel to minimum 25m. Call 999 and DNO emergency number immediately. Do not touch casualty if still in contact with source. If casualty is clear, administer CPR if trained and safe to do so. Isolate excavator and cordon area. **GAS ESCAPE:** Evacuate to minimum 50m upwind. Call 999 and National Gas Emergency 0800 111 999. Eliminate all ignition sources - no mobile phones, vehicles, or smoking in hazard zone. Do not operate electrical switches. Evacuate nearby buildings if gas concentration significant. **CONFINED SPACE / OXYGEN DEFICIENCY:** Do not enter trench to rescue - call 999 immediately. Use rescue equipment (tripod/winch) if casualty is harnessed. Administer oxygen if trained and equipment available. Begin CPR if casualty is recovered and not breathing. **FIRST AID:** Minimum two First Aiders on site with HSE-approved First Aid at Work certificates (3-day course). First aid kit to BS 8599-1:2019 located in site cabin. Nearest A&E department identified in site induction. Accident book (BI 510) maintained for all injuries. RIDDOR-reportable incidents (>7 day injury, major injury, dangerous occurrence) to be reported to HSE within required timescales.
Under CDM 2015 Regulation 22 (Excavations), every excavation must be supported or battered back to a safe angle to prevent collapse. For excavations exceeding 1.2m depth, or where ground conditions are uncertain, a formal temporary works design to BS 5975:2008+A1:2011 is required. A Temporary Works Coordinator (TWC) must be appointed for all Category 2 and 3 temporary works (which includes most shored excavations). The TWC is responsible for: checking design assumptions match site conditions, issuing permits to load, and inspecting installations. The Principal Contractor must ensure the TWC is competent (typically holding TWf qualification) and that all shoring operatives are trained in the specific system being used. Hydraulic shoring must have current thorough examination certificates (typically 6-monthly) and be used strictly within manufacturer's safe working load limits.
HSG47 establishes the 'PAS 128 Specification for Underground Utility Detection' as best practice. Compliance requires: (1) Obtain service plans from all utility owners (C2 level minimum); (2) Conduct CAT/Genny survey by trained operative (competency refresher every 3 years recommended); (3) Use multiple detection modes - Power (detects live cables), Radio (detects re-radiated signals), and Genny (actively traces conductive services); (4) Mark all detected services and photograph; (5) Excavate trial holes to verify service positions before main excavation. CRITICAL LIMITATIONS: CAT/Genny cannot detect non-metallic services (plastic gas/water pipes, fibre optic cables), cannot determine voltage of electrical cables, and has reduced effectiveness in congested utility areas or near reinforced concrete. Ground Penetrating Radar (GPR) provides additional detection capability but still requires verification by trial holes. Always hand-dig within 0.5m of indicated services and treat all cables as live HV until proven otherwise.
A trench is legally a confined space if it is 'a place which is substantially enclosed and where serious injury can occur from hazardous substances or conditions within the space or nearby'. Depth alone does not define confined space status - the assessment must consider: (1) Oxygen deficiency risk (e.g., displacement by heavier gases, biological oxygen consumption in organic soils); (2) Toxic gas accumulation (H2S from sewers/organic decay, CO from nearby plant exhaust, methane from landfill/peat); (3) Difficulty of rescue. Trenches >2m depth in contaminated ground, near sewers, or in waterlogged conditions typically meet confined space criteria. Additional controls required: Permit to Enter system, continuous 4-gas atmospheric monitoring (O2, LEL, H2S, CO), emergency rescue equipment (tripod, winch, harnesses), trained rescue team on standby, forced ventilation if atmosphere is not safe, and no lone working. Note: The Regulations require avoidance of confined space entry if reasonably practicable (e.g., by using remote methods), and if entry is unavoidable, a safe system of work must be implemented and emergency arrangements must be in place BEFORE entry.
Competent Person & Operative Declaration: By signing below, the Site Supervisor confirms this assessment has been adapted and verified for actual site conditions, and operatives confirm they have attended the pre-start Toolbox Talk for Deep Trench Excavation, Hydraulic Shoring & CAT/Genny Buried Service Avoidance and will follow the safe system of work.
| Operative / Supervisor Name | Trade / Role & CSCS No. | Signature | Date & Time |
|---|---|---|---|
| 1. (Site Supervisor): | |||
| 2. | |||
| 3. | |||
| 4. | |||
| 5. | |||
| 6. |