SafeSequence › UK Safety Template Library › Electrical › Commercial 22kW/50kW EV Charging Bollard Trenching & 3-Phase Termination
Verified UK RAMS Standard • Electrical

Commercial 22kW/50kW EV Charging Bollard Trenching & 3-Phase Termination (RAMS Template & 5x5 Risk Assessment)

This Risk Assessment and Method Statement (RAMS) covers the installation of commercial electric vehicle charging bollards rated at 22kW/50kW, including ground excavation, cable trenching, ducting installation, and 3-phase electrical termination. All works shall comply with the Electricity at Work Regulations 1989, BS 7671:2018+A2:2022 Section 722 (EV charging installations), IET Code of Practice for Electric Vehicle Charging Equipment Installation (4th Edition), and CDM Regulations 2015. Works involve excavation to 600-800mm depth, installation of SWA armoured cable in approved ducting, earthing and bonding to TN-S/TN-C-S systems, and final commissioning with insulation resistance and earth loop impedance testing. Only competent persons holding relevant electrical qualifications (18th Edition, EV charging competency) shall undertake live electrical work. Permit-to-Work and isolation procedures are mandatory. All excavations require CAT & Genny scanning, utility drawings review, and trial holes where services are suspected.

Statutory FrameworkElectricity at Work Regulations 1989, BS 7671 Section 722, IET Code of Practice for EV Charging
ClassificationNot applicable - no hazardous substances requiring UN/GHS classification are used in this electrical installation activity. However, cable lubricants and cleaning solvents shall have Safety Data Sheets available on site. Any bitumen or cold-lay surfacing materials used for reinstatement must comply with COSHH requirements and manufacturer's safety data.
Required Plant / KitCAT4+ Cable Avoidance Tool (CAT) and Genny signal generator with valid calibration certificate • Fluke 1664FC or equivalent multifunction electrical tester (calibrated within 12 months) for insulation resistance, continuity, earth loop impedance, and RCD testing • Hydraulic cable crimping tool with dies suitable for 25-95mm² copper conductors and compression lugs to BS EN 13600 • 110V reduced low voltage (RLV) breaker, mini-digger (1.5-3 tonne) with trench box/shoring equipment to BS EN 13331 for excavations exceeding 1.2m depth • Torque screwdriver/wrench (calibrated) set to manufacturer's specifications for MCB/MCCB and busbar terminations (typically 2-4 Nm for terminals)
Review Cycle12 Months / Post-Incident
Instant AI Customization or Free Blank Word (.doc) Download

Need this RAMS customized with your Company Name, Site Postcode & Nearest A&E Hospital?

Dictate your site specifics on your phone in 45 seconds to auto-compile a signed PDF—or download our free blank Word (.doc) shell below.

Auto-Fill via Voice / CLP (45s)

2. 5×5 Hazard Risk Assessment Matrix (HASAWA 1974 / MHSWR 1999)

Identified Hazard & HarmInitial Risk (L×S)Mandatory Engineering, Isolation & Procedural ControlsResidual Risk
1. Contact with underground services (electric cables, gas mains, water, telecoms) during excavation
Harm: Electrocution, explosion, flooding, service disruption, prosecution under HSWA
4 × 5 = 20Obtain C2/C4 utility drawings from LSBUD. Conduct CAT & Genny scan to 1m beyond work area. Mark all detected services with paint/pins. Dig trial holes by hand within 500mm of detected services. Implement 'safe dig' protocol with hand tools only in high-risk zones. Maintain 300mm minimum clearance from HV cables. Establish exclusion zone and appoint banksman.2 × 4 = 8
2. Electric shock from contact with live 400V 3-phase conductors during termination or testing
Harm: Fatal or serious electric shock, cardiac arrest, burns, arc flash injuries
4 × 5 = 20Implement Permit-to-Work and isolation procedure per BS 7671 Regulation 14. Isolate supply at distribution board, lock-off with unique padlock, display 'Danger - Men Working' signage. Prove dead with voltage indicator on all phases and neutral. Apply temporary earth bonds. Use insulated tools to BS EN 60900. Minimum two competent persons (AP/QP) present. Insulating gloves and arc-rated PPE mandatory. Re-energise only after inspection and testing.1 × 4 = 4
3. Trench collapse or persons falling into excavation (600-800mm depth)
Harm: Crushing injuries, suffocation, fractures, head injuries, fatality
3 × 5 = 15Excavations >1.2m require trench box/shoring to BS EN 13331. Batter trench sides at safe angle (typically 45°) or use proprietary support. Spoil heaps minimum 1m from edge. Install barriers/fencing around excavation perimeter. Provide safe access/egress (ladder every 15m). Inspect excavation daily and after weather events. Competent person (SSSTS/SMSTS) to supervise. Exclude personnel when plant operating.2 × 3 = 6
4. Manual handling of heavy charging bollard units (50-80kg) and cable drums (25-50kg)
Harm: Musculoskeletal injuries, back strain, crush injuries to hands/feet, hernias
4 × 3 = 12Conduct task-specific manual handling assessment per HSE INDG143. Use mechanical aids: pallet truck, trolley, or telehandler with certified lifting accessories. Team lift (minimum 2 persons) with clear communication. Maintain neutral spine posture, bend knees, avoid twisting. Position bollard base adjacent to excavation before lowering. Use cable drum stands and avoid lifting full drums. Provide manual handling training to operatives.2 × 2 = 4
5. Vehicular strike from site traffic or public vehicles in car park/roadside locations
Harm: Multiple fatalities, serious crush injuries, traumatic amputation
3 × 5 = 15Implement Chapter 8 traffic management plan with appropriate signage (7001, 7101 series). Establish segregated work zone with barriers, cones, and delineators. Deploy trained banksman with high-vis and two-way radio. Coordinate with site management to restrict vehicle access during critical phases. Position plant to create physical barrier between works and traffic. All operatives wear Class 3 high-vis. Conduct toolbox talk on vehicle/plant interface risks.1 × 5 = 5

3. Step-by-Step Safe Sequence of Operations & Hold-Points

1

Utility surveys, permit acquisition, and site establishment

Pre-Construction & Site Setup

Obtain and review C2/C4 utility drawings from LSBUD/national grid. Conduct comprehensive CAT & Genny scan extending 1m beyond proposed trench route, marking all detected services with spray paint and photographic record. Dig trial holes by hand at 5m intervals where services indicated. Secure Permit-to-Work from client/duty holder. Erect Chapter 8 compliant traffic management, barriers, and signage. Position welfare facilities and establish 110V RLV supply from approved distribution unit. Conduct site induction and toolbox talk covering emergency procedures, isolation protocols, and buried service locations. Confirm competency of all electrical operatives (18th Edition, EV charging qualification).

Critical Hold-Point: HOLD POINT: Do not commence excavation until utility survey complete, trial holes confirm service locations, and Permit-to-Work signed by authorised person. Verify all operatives have seen utility drawings and understand 'safe dig' protocol.
2

Controlled excavation, duct laying, and backfill to specification

Excavation & Ducting Installation

Mark trench route (typically 600-800mm depth, 300mm width) with spray paint. Excavate using mini-digger with experienced operator, switching to hand tools within 500mm of detected services. Maintain safe battering angle or install trench support if depth exceeds 1.2m. Inspect excavation for unexpected services before proceeding. Lay 100-150mm diameter MDPE/HDPE ducting on 50mm sand bed with draw rope installed. Install warning tape 150mm above duct. Backfill in 150mm layers with mechanical compaction to 95% maximum dry density. Reinstate surface to match existing (tarmac/block paving). Photograph each stage for client records.

Critical Hold-Point: STOP WORK IMMEDIATELY if unexpected services encountered. Contact utility provider and reassess method. Never use mechanical excavator within 500mm of confirmed HV cables or gas mains. Daily excavation inspection mandatory before personnel entry.
3

SWA cable pulling, bollard foundation, and mechanical fixing

Cable Installation & Bollard Positioning

Pull 3-core or 4-core SWA armoured cable (typically 16-35mm² for 22kW, 25-50mm² for 50kW) through installed duct using draw rope and cable lubricant. Leave 1.5m service loop at each end. Excavate bollard foundation to manufacturer's specification (typically 600mm cube). Install M16/M20 foundation bolts set in concrete (C30/37 minimum) with template for accurate positioning. Allow concrete to cure (minimum 7 days or use rapid-set product per datasheet). Position bollard unit over bolts, ensuring IP rating seals intact. Torque foundation bolts to manufacturer's specification (typically 80-120Nm). Verify bollard is plumb using spirit level.

Critical Hold-Point: Ensure cable minimum bending radius maintained (typically 12x cable diameter for SWA). Do not drag cable over sharp edges. Verify bollard unit serial number matches commissioning documentation and warranty registration before fixing.
4

Isolation, lock-off, and prove-dead procedure at distribution board

Electrical Isolation & Preparation

Identify correct circuit at distribution board serving EV charging installation. Complete Permit-to-Work and isolation certificate. Isolate supply using main switch or MCCB, applying unique padlock and 'Danger - Men Working' tag. Test voltage indicator on known live source to confirm functionality. Prove dead on all three phases (L1, L2, L3) and neutral using voltage indicator at distribution board and at bollard termination point. Apply temporary earth bonds to isolated conductors. Establish 1m exclusion zone around open electrical enclosures. Post second person (competent) to monitor isolation and prevent unauthorised re-energisation.

Critical Hold-Point: CRITICAL HOLD POINT: Do not proceed with termination until isolation confirmed, proved dead on all conductors, and Permit-to-Work signed. Voltage indicator must be proven before and after use. Only Authorised Person (AP) or competent person under supervision may perform isolation.
5

Cable termination, earth bonding, and torque verification

3-Phase Termination & Earthing

Strip SWA cable outer sheath using cable knife, leaving armour wire intact for earth continuity. Fit SWA gland with earth tag to bollard enclosure, ensuring IP rating maintained. Strip phase conductors (L1-brown, L2-black, L3-grey) and neutral (blue) to correct length using cable strippers. Fit compression lugs using hydraulic crimping tool with correct die size. Terminate conductors to charging unit terminals per manufacturer's wiring diagram, maintaining phase rotation. Torque all terminals using calibrated torque driver (typically 2-4Nm for MCB terminals, verify manufacturer specification). Connect armour earth to bollard earth bar and verify continuity to MET. Install 30mA Type B RCD (DC fault detection) if not present at distribution board. Label all conductors and circuits per BS 7671 Chapter 51.

Critical Hold-Point: Verify correct phase rotation (L1-L2-L3) using phase rotation meter before final connection - incorrect rotation may damage vehicle charging systems. All terminations must be torqued to specification - loose connections cause arcing and fire risk. Insulating gloves mandatory during termination even when isolated.
6

Electrical testing, functional checks, and handover documentation

Testing, Commissioning & Energisation

Conduct electrical testing per BS 7671 Chapter 64 and IET Code of Practice: (1) Continuity of protective conductors and bonding (R1+R2 <0.5Ω typically); (2) Insulation resistance test at 500V DC (>1MΩ between live conductors and earth); (3) Polarity verification; (4) Earth loop impedance (Zs) test - must meet BS 7671 maximum values for protective device (typically <0.35Ω for 32A Type B MCB); (5) RCD trip time test at 1x and 5x rated current (<300ms at 5x). Record all results on Electrical Installation Certificate (EIC). Remove temporary earths and isolation locks. Re-energise circuit and verify 400V 3-phase supply at bollard using voltage meter. Conduct functional test: simulate vehicle connection, verify RFID/app authentication, confirm charging initiation and power delivery. Affix certification label and QR code to bollard. Provide client with test certificates, O&M manual, and warranty documentation.

Critical Hold-Point: FINAL HOLD POINT: Do not energise until all test results meet BS 7671 requirements and are documented. Ensure all personnel clear of bollard during first energisation. If any test fails, re-isolate immediately and rectify fault. Client/duty holder must sign acceptance before demobilisation.

Emergency Rescue, First Aid & Spill Protocol

In the event of electric shock: DO NOT TOUCH THE CASUALTY if still in contact with live conductors. Isolate power supply immediately using emergency stop or isolation switch. If isolation not possible, use non-conductive item (dry wood) to separate casualty from source. Call 999 immediately and request ambulance, stating 'electrical incident'. Commence CPR if casualty not breathing (30 compressions: 2 breaths). Use on-site AED if available. Treat electrical burns by cooling with water for 20 minutes and covering with sterile dressing. For trench collapse: Call 999 and request Fire & Rescue Service with technical rescue capability. Do not enter trench to attempt rescue - secondary collapse risk. Keep casualty calm and still if partially buried. For vehicle strike: Call 999 immediately. Do not move casualty unless in immediate danger. Control catastrophic bleeding using direct pressure and haemostatic dressings. All sites must have appointed First Aider with valid HSE Emergency First Aid at Work certificate and accessible first aid kit to BS 8599-1. Accident reporting: All injuries, dangerous occurrences, and near-misses must be recorded in site accident book. RIDDOR-reportable incidents (fatality, major injury, >7 day absence, dangerous occurrence) must be reported to HSE within required timescales. Preserve scene for investigation.

4. UK HSE Compliance FAQs: Commercial 22kW/50kW EV Charging Bollard Trenching & 3-Phase Termination

What specific electrical qualifications are legally required under the Electricity at Work Regulations 1989 for operatives terminating 3-phase EV charging equipment?

Regulation 16 of the Electricity at Work Regulations 1989 requires persons to be 'competent' to prevent danger and injury. For 3-phase EV charging termination, operatives must hold: (1) City & Guilds 2382-18 (18th Edition BS 7671 Requirements for Electrical Installations); (2) City & Guilds 2391-52 or equivalent (Inspection and Testing); (3) EV charging-specific qualification such as City & Guilds 2919 Electric Vehicle Charging Equipment Installation or equivalent demonstrating competence in Mode 3 charging, DC fault protection, and PME earthing considerations. Additionally, operatives should be designated as 'Authorised Persons' (AP) or work under direct supervision of an AP. Competency must be assessed and recorded by the employer, considering technical knowledge, experience, and ability to recognise limitations. For works on systems exceeding 1000V AC or DC fast charging (not applicable here but relevant for 50kW+ DC), additional high-voltage competency (e.g., City & Guilds 2357 Level 3) may be required.

How do we comply with BS 7671 Section 722 requirements for PME earthing systems when the charging point may be used by vehicles parked outside the equipotential zone?

BS 7671:2018+A2:2022 Section 722.411.4.1 addresses the specific risk of lost PEN (combined Protective Earth and Neutral) conductor in TN-C-S (PME) systems, which could result in exposed-conductive-parts of a vehicle rising to dangerous potential. Compliance options: (1) Install a Type B RCD (sensitive to DC fault currents from EV charging) with maximum 30mA rating - this is mandatory regardless of earthing system; (2) For outdoor installations on PME supplies, consider additional protection such as: (a) installation of an earth electrode to provide additional fault path (supplementary TT earthing), though this alone does not satisfy the requirement; (b) use of a charging unit with built-in PEN fault detection and automatic disconnection; (c) consultation with DNO regarding supply characteristics. (3) Ensure all extraneous-conductive-parts within 2.5m of the charging point are bonded to the MET with 10mm² minimum conductor per Regulation 722.411.4. (4) The IET Code of Practice for EV Charging (4th Edition) recommends risk assessment considering location, vehicle types, and earthing system. Document the earthing arrangement on the Electrical Installation Certificate and ensure the charging unit manufacturer's installation instructions are followed, as many modern units include integral PME protection.

What are the CDM 2015 Principal Designer and Principal Contractor duties specific to this EV charging installation, and what must be included in the Health & Safety File?

Under CDM Regulations 2015, if the project is notifiable (exceeds 30 days or 500 person-days), a Principal Designer (PD) and Principal Contractor (PC) must be appointed. Key duties: The PD must: (1) Identify and eliminate/control foreseeable risks during design - for EV charging this includes specifying cable routes avoiding existing services, designing-out work at height, and ensuring adequate access for maintenance; (2) Prepare pre-construction information including utility surveys, asbestos surveys (if works near buildings), and existing electrical system details; (3) Produce a Health & Safety File containing as-built drawings showing cable routes and depths, electrical test certificates, product data sheets for charging unit, O&M manuals, details of residual risks (e.g., buried cables), and emergency isolation procedures. The PC must: (1) Plan, manage, and monitor construction work to ensure it is carried out safely; (2) Ensure all contractors are competent and adequately resourced; (3) Ensure suitable site inductions, welfare facilities, and emergency procedures are in place; (4) Coordinate activities where multiple contractors are present; (5) Liaise with PD to update Health & Safety File with any design changes or additional information discovered during construction (e.g., unexpected services). For non-notifiable projects, the client has greater flexibility but must still ensure competent contractors and adequate planning. The completed Health & Safety File must be handed to the client and updated throughout the asset lifecycle to support safe maintenance and future modifications.

5. Operative Toolbox Talk & Competent Person Sign-Off Register

Competent Person & Operative Declaration: By signing below, the Site Supervisor confirms this assessment has been adapted and verified for actual site conditions, and operatives confirm they have attended the pre-start Toolbox Talk for Commercial 22kW/50kW EV Charging Bollard Trenching & 3-Phase Termination and will follow the safe system of work.

Operative / Supervisor Name Trade / Role & CSCS No. Signature Date & Time
1. (Site Supervisor):     
2.     
3.     
4.     
5.     
6.     