This Risk Assessment and Method Statement (RAMS) provides comprehensive safety controls for the dismantling of internal mezzanine floor structures using oxy-propane cutting equipment. The work is governed by CDM 2015 Regulations, BS 6187:2011 Code of Practice for Full and Partial Demolition, LOLER 1998 for lifting operations, and COSHH 2002 for hot work fume control. The document establishes a controlled sequence for structural assessment, isolation of services, hot work permitting, systematic dismantling using oxy-propane cutting, and safe lowering of components. All operatives must hold CSCS cards, CCNSG Safety Passport, and oxy-fuel cutting competency certification. A Temporary Works Coordinator must approve all lifting arrangements and structural support measures. The Principal Contractor must ensure adequate segregation from occupied areas, fire watch provisions, and emergency response capability throughout the works.
| Identified Hazard & Harm | Initial Risk (L×S) | Mandatory Engineering, Isolation & Procedural Controls | Residual Risk |
|---|---|---|---|
| 1. Structural collapse during cutting operations due to uncontrolled load redistribution or premature severance of primary structural members Harm: Multiple fatalities, crushing injuries, entrapment beneath collapsed steelwork | 4 × 5 = 20 | Competent Temporary Works Coordinator to design dismantling sequence with structural calculations. Install temporary propping and bracing before cutting primary members. Cut in reverse order of construction. Use sequential cutting with controlled lowering. Establish 5-metre exclusion zone around cutting area. Conduct pre-start structural survey and mark load-bearing members. Implement permit-to-cut system with sign-off at each stage. | 2 × 4 = 8 |
| 2. Fire or explosion from oxy-propane equipment malfunction, flashback, or ignition of combustible materials in vicinity Harm: Severe burns, respiratory injury from smoke inhalation, building fire, fatalities | 4 × 4 = 16 | Hot Work Permit system with 60-minute fire watch post-completion. Fit BS EN 730 flashback arrestors to both oxygen and propane regulators. Clear 10-metre radius of combustibles and protect non-removable materials with fire-retardant blankets. Daily pre-use inspection of hoses, regulators, and connections (reject if damaged). Isolate gas cylinders when not in use and store separately (minimum 3 metres apart). Provide two trained fire marshals with extinguishers. Ensure adequate ventilation to prevent gas accumulation. | 2 × 3 = 6 |
| 3. Falls from height during work on mezzanine floor or when accessing elevated cutting positions (typically 3-8 metres) Harm: Fatalities, spinal injuries, multiple fractures, head trauma | 5 × 5 = 25 | Collective protection prioritised: install edge protection (toe boards, mid-rails, top rails to BS EN 13374 Class A) to all open edges before work commences. Use MEWP with harness anchor points for cutting operations (operator training and daily pre-use checks). Where MEWP access not feasible, install temporary scaffold with full edge protection (NASC compliant, inspected per LOLER). Rescue plan in place with trained personnel and equipment. Prohibit ladders for work activities. Implement permit-to-work for height work. | 2 × 5 = 10 |
| 4. Inhalation of metal fume, carbon monoxide, and nitrogen oxides generated during oxy-propane cutting in enclosed building Harm: Metal fume fever, respiratory sensitisation, carbon monoxide poisoning, long-term lung disease | 5 × 3 = 15 | COSHH assessment completed with exposure monitoring. Provide local exhaust ventilation (LEV) or portable fume extraction at cutting point. Ensure general building ventilation with air changes calculated for space volume. Use RPE (FFP3 particulate respirators or powered air-purifying respirators) where LEV insufficient. Conduct atmospheric monitoring for CO and O2 levels (maintain >19.5% O2, <35ppm CO). Rotate operatives to limit exposure duration. Provide health surveillance for regular hot work operatives. Implement respiratory fit testing programme. | 2 × 2 = 4 |
| 5. Uncontrolled lowering or dropped loads during dismantling causing impact injuries to personnel below or structural damage Harm: Crushing injuries, fractures, head injuries, fatalities to ground-level personnel | 4 × 5 = 20 | Lifting plan prepared by Appointed Person (CPCS A61 or equivalent). All lifting equipment LOLER examined within last 6 months with certificates on site. Use correct slings for load (calculate weight and centre of gravity). Attach tag lines to control load swing. Establish exclusion zone beneath lifting operations with barriers and signage. Banksman to coordinate lifts with clear hand signals (CPCS trained). Lower components to designated lay-down area with level, load-bearing surface. Conduct toolbox talk on lifting operations before each shift. Prohibit personnel beneath suspended loads. | 2 × 4 = 8 |
Conduct intrusive structural survey by competent engineer to identify load-bearing members, connections, and existing defects. Obtain as-built drawings or create measured survey. Isolate and lock-out all services (electrical, gas, water, HVAC) within 5 metres of mezzanine with LOTO tags. Verify isolation with test equipment. Establish physical barriers (Heras fencing or solid hoarding) to create exclusion zone around work area with controlled access point. Install signage: 'Demolition in Progress - Authorised Personnel Only', 'Hot Work Area', 'Overhead Work'. Confirm fire alarm system operational or implement fire watch protocol. Conduct asbestos survey and obtain clearance certificate if building pre-2000.
Install temporary props and bracing to support mezzanine structure as per Temporary Works design (TWC Category 2 minimum). Erect edge protection to all open edges of mezzanine floor (top rail 950-1150mm, mid-rail, toe board minimum 150mm). Install scaffold or MEWP access routes to cutting locations. Fix lifting anchor points to building structure (load tested to 2x anticipated load) or position mobile crane/gantry system. Establish designated lay-down area on ground floor with marked zones for cut components. Position gas cylinders in external compound or well-ventilated area with segregation (oxygen/propane minimum 3m apart), secured upright with chains, and protected from weather and impact.
Issue Hot Work Permit valid for specific area and duration (maximum 8 hours). Clear 10-metre radius of all combustible materials (packaging, timber, flammable liquids). Cover non-removable combustibles with fire-retardant blankets. Position two fire extinguishers (CO2 and dry powder) within 5 metres of cutting location. Assign trained fire marshal to maintain continuous fire watch during cutting and for 60 minutes after completion. Set up oxy-propane equipment: inspect hoses for damage/perishing, check regulator gauges, fit flashback arrestors to both oxygen and propane lines, purge hoses before lighting. Test cut on scrap material to verify equipment function and flame characteristics. Ensure adequate ventilation and position fume extraction if required.
Work from safest accessible position (MEWP or scaffold platform). Remove mezzanine floor decking first (timber, metal deck, or concrete planks) working from perimeter inward to maintain safe working platform. Cut or unbolt handrails and balustrades. Remove secondary steelwork (purlins, joists, cross-bracing) in reverse order of construction. For each component: attach lifting sling and tag line before final severance, signal banksman, lift clear, and lower to lay-down area. Maintain edge protection by installing temporary barriers as permanent handrails removed. Keep cutting area clear of debris (remove offcuts regularly). Monitor structural stability continuously - stop work if any unexpected movement, cracking, or distortion observed.
Follow structural engineer's cutting sequence precisely (typically top-down, working from centre outward). Before cutting each primary member: verify temporary support in place, attach dual lifting slings with shackles (check SWL), attach tag lines, brief team on lift sequence. Cut beam/column in designated location (usually near connection but leaving stub for control). Make initial relief cut (25% depth) to prevent binding, then complete cut. Control member as it separates - do not allow free fall. Lower to ground using chain block or crane with constant communication between cutter and banksman. Once member landed, release slings and move to storage area. Inspect remaining structure after each cut for signs of distress. Adjust propping as load redistributes.
After final cut, maintain fire watch for 60 minutes minimum. Inspect entire work area for smouldering materials or hot spots using thermal imaging camera if available. Shut down oxy-propane equipment: close cylinder valves, bleed hoses, disconnect equipment, and return cylinders to secure storage. Remove all temporary works (props, edge protection, barriers) in safe sequence that maintains safety. Clear all debris, offcuts, and equipment from area. Inspect floor/walls for damage requiring repair. Conduct final inspection with Principal Contractor and building owner. Complete permit closure documentation. Reinstate fire alarm system if isolated. Hand back area with photographic record of completion and any remedial works required.
In the event of fire: Activate nearest fire alarm, evacuate area immediately, call 999, and attempt extinguishment only if safe to do so using CO2 or dry powder extinguishers (never water on gas fires). If gas leak detected: evacuate area, prohibit ignition sources, close cylinder valves if safe, ventilate space, and do not re-enter until atmosphere tested safe. For structural collapse: evacuate immediately, call 999 (request Fire & Rescue urban search and rescue), account for all personnel, do not attempt rescue unless trained and safe to do so. Falls from height: do not move casualty unless in immediate danger, call 999, administer first aid for spinal injury protocol, deploy rescue plan if suspended in harness (maximum suspension time 20 minutes). For burns: cool with running water for 20 minutes minimum, remove non-adherent clothing, cover with sterile non-fluffy dressing, seek medical attention for all burns >5cm or full thickness. Inhalation injury: move to fresh air, administer oxygen if trained and available, place in recovery position if unconscious, call 999 for suspected carbon monoxide poisoning. First aid provision: Minimum two First Aiders on site with HSE-approved training (FAW or EFAW). First aid room or designated point with stretcher, eye wash station, and burn dressings. Emergency contact numbers displayed at site entrance and on permit boards. Nearest A&E hospital location and route confirmed in site induction. Incident reporting: All injuries, near misses, and dangerous occurrences must be reported to Site Manager immediately and recorded in site accident book. RIDDOR-reportable events must be notified to HSE within required timescales (fatalities/specified injuries immediately, over-7-day injuries within 15 days).
Under CDM 2015 Regulation 8 (competence), all operatives must hold valid CSCS cards (or equivalent) demonstrating construction industry competence. Oxy-propane cutting operatives require specific certification in oxy-fuel cutting techniques (e.g., City & Guilds, ECITB, or manufacturer-accredited training) with evidence of practical assessment. Additionally, operatives working at height require IPAF or PASMA certification depending on access equipment used. The Appointed Person coordinating lifting operations must hold CPCS A61 or CITB Appointed Person qualification. The Temporary Works Coordinator must be qualified to BS 5975 standard (typically ICE or IStructE accredited). All competency certificates must be verified and copies held on site. The Principal Contractor must maintain a competency matrix demonstrating that the combined team has adequate skills, knowledge, and experience for the specific demolition task, including understanding of structural behaviour during progressive dismantling.
Using the HSE-aligned 5x5 matrix, residual risk scores of 1-3 (green) are broadly acceptable with routine monitoring; scores of 4-9 (amber) are tolerable with active supervision and control verification; scores of 10-15 (red) require senior management approval, enhanced controls, and continuous monitoring; scores of 16-25 (dark red) are unacceptable and work must not proceed until additional controls reduce risk. For this mezzanine dismantling RAMS, all residual scores have been reduced to 10 or below through engineering controls and safe systems of work. However, work must stop immediately if: any structural member shows unexpected movement, cracking, or distortion; temporary works fail or show signs of overload; atmospheric monitoring indicates O2 <19.5% or CO >35ppm; weather conditions deteriorate (wind >12m/s affecting lifting operations); equipment failure occurs (especially gas equipment or lifting gear); or any near-miss incident suggests controls are inadequate. The Site Manager must investigate, implement additional controls, and obtain approval from the Principal Designer before work resumes. Dynamic risk assessment by operatives is mandatory throughout, with authority to stop work if conditions change.
Under LOLER 1998 Regulation 9, all lifting equipment must be thoroughly examined by a competent person before first use on site, and subsequently at intervals not exceeding 6 months for equipment used for lifting persons (MEWPs, hoists) or 12 months for equipment used solely for lifting loads (chain blocks, slings, shackles). However, for demolition work involving lifting in potentially hazardous conditions, 6-monthly examination is recommended for all equipment. Each item must have a current examination certificate (form F2508A or equivalent) available on site, and equipment must display a unique identification number matching the certificate. Lifting accessories (slings, shackles, chains) must be colour-coded by quarter-year of examination for easy visual verification. Daily pre-use inspections must be conducted by the Appointed Person or trained operative, recorded in a site register, and any defects must result in immediate withdrawal from service. SWL (Safe Working Load) must be clearly marked on all equipment and never exceeded. For this mezzanine dismantling, a specific lifting plan must be prepared identifying all equipment, examination status, and lift sequences, signed off by the Appointed Person and retained for audit purposes.
Competent Person & Operative Declaration: By signing below, the Site Supervisor confirms this assessment has been adapted and verified for actual site conditions, and operatives confirm they have attended the pre-start Toolbox Talk for Internal Mezzanine Floor Dismantling & Oxy-Propane Structural Steel Cutting and will follow the safe system of work.
| Operative / Supervisor Name | Trade / Role & CSCS No. | Signature | Date & Time |
|---|---|---|---|
| 1. (Site Supervisor): | |||
| 2. | |||
| 3. | |||
| 4. | |||
| 5. | |||
| 6. |